ქალაქი თბილისი , პეტრე იბერის ქუჩის შესახვევი N13
- Total floor area
- 74,754.9 m²
- Building footprint
- 79,729.8 m²
- Residential area
- 37,386.9 m²
- Plot area
- 40,230 m²
- Height
- 89.1 m
- Depth below ground
- 6.4 m
- Building volume
- 111,595 m³
Figures as the applicant entered them in the form; not verified.
Applicant
- Name
- მარიამ პაპუკაშვილი
- Developer (company ID)
- 404665331
People
- Client
- Name
- გიორგი ხუციშვილი
- Personal number
- *********61
- Organization
- შპს დიდი დიღომი რეზიდენსი
- Company code
- 404665331
- Chief architect
- Name
- მარიამ პაპუკაშვილი
- Personal number
- *********58
- Organization
- შპს სტუდიო ალფა სახლი
- Company code
- 404664573
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- დემური ტაბატაძე
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- მარიამ პაპუკაშვილი
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- ილია ცხომელიძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- გიორგი მჭედლიშვილი
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- ლევანი ოქროპირიძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.10.06.022.010
- Owner
- შპს "დიდი დიღომი რეზიდენსი " (404665331)
- Area
- 40,230 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 1 October 2026
Plots and zoning
- 01.10.06.022.010Registry extract ↗ (opens in a new tab)
- Zone
- Industrial
- Sub-zone
- s-1
- K1
- 0
- K2
- 0
- Industrial zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
- K3
- 0
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR11008730
- Status
- Interim decision
- Registered
- 30 December 2023
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Waiting on
- the applicant
- since 30 July 2026 (116 days)
- Rounds of remarks
- 16
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 30 July 2026City answer
ქ. თბილისის მუნიციპალიტეტის სსიპ – ქ. თბილისის მუნიციპალიტეტის არქიტექტურის სამსახურმა განიხილა თქვენ მიერ ელექტრონულად ატვირთული განცხადება და მასზე თანდართული დოკუმენტაცია, პასუხად გაცნობებთ შემდეგს: 01... საჭიროა წარმოდგენილი იქნას ქალაქ თბილისის მუნიციპალიტეტის მთავრობის 2023 წლის 6 სექტემბრის N23.1331.1470 განკარგულების მე-2-მე-4 პუნქტების შესრულების დამადსტურებელი დოკუმენტაცია - შესაბამისი თანხის დაანგარიშების წერილი და თანხის გადახდის დამადასტურებელი ქვითარი. 02...საპროექტო ტერიტორიის გენერალური გეგმა, მასშტაბი 1:500. -> .გენერალური გეგმის pdf ფაილი.: მიწის ნაკვეთი დატვირთულ იქნას სერვიტუტით გრგ-ს შესაბამისად. 03.."მშენებლობის ნებართვის მოსაკრებელი -> .მოსაკრებელის რიცხვითი მაჩვენებელი: კ2 საანგარიშო კოეფიციენტის დაზუსტების შემდგომ, გადახდილ იქნას კ-2 კოეფიციენტის მაჩვენებლის გათვალისწინებით 1 კვ. მ-ზე, 6 ლარის ოდენობით. 04.შენობა-ნაგებობის ყველა სართულისა და სახურავის გეგმები, მასშტაბი 1:100. -> .გეგმების pdf ფაილი.: ვინაიდან სახურავის გეგმების დოკუმენტაციაზე ფიქსირდება ექსპლიკაცია ტერასა(შესაბამისი ფართით) საჭიროა ან წაიშალოს აღნიშნული ფართი და ტერასის ექსპლიკაცია ან მიენოჭოს შესბამისი დაკავებულობა და აღნიშნულის შესაბამისად დაკორექტირდეს საპროექტო დოკუმენტაცია. არასრულყოფილი დოკუმენტაციის გამო სამსახური ამ ეტაპზე ვერ გიდგენთ ყველა შესაძლო ხარვეზს. გაითვალისწინეთ, რომ თქვენ გეძლევათ 15 დღიანი ვადა მითითებული ხარვეზის გამოსასწორებლად, თუ დადგენილ ვადაში განმცხადებელი არ წარმოადგენს შესაბამის დოკუმენტაციას, განცხადება დარჩება განუხილველი.
Show moreShow less
- 29 July 2026City answer
- 28 July 2026Files uploaded
- 27 July 2026Files uploaded
- 23 July 2026Files uploaded
- 16 June 2026City answer
- 9 June 2026City answer
- 9 June 2026Files uploaded
- 9 June 2026Files uploaded
- 5 June 2026City answer
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 4 June 2026Files uploaded
- 27 March 2026City answer
- 27 March 2026Files uploaded
- 27 March 2026Files uploaded
- 27 March 2026Files uploaded
- 20 March 2026City answer
- 20 March 2026Files uploaded
- 20 March 2026Files uploaded
- 20 March 2026Files uploaded
- 20 March 2026Files uploaded
- 20 March 2026Files uploaded
- 20 March 2026Files uploaded
- 17 March 2026Files uploaded
- 5 March 2026City answer
- 5 March 2026Files uploaded
- 5 March 2026Files uploaded
- 28 February 2026Files uploaded
- 28 February 2026Files uploaded
- 28 February 2026Files uploaded
- 28 February 2026Files uploaded
- 20 November 2024City answer
- 29 October 2024City answer
- 29 October 2024Files uploaded
- 28 October 2024Files uploaded
- 28 October 2024Files uploaded
- 28 October 2024Files uploaded
- 7 October 2024City answer
- 7 October 2024Files uploaded
- 4 October 2024Files uploaded
- 27 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 2 September 2024Files uploaded
- 30 August 2024Files uploaded
- 8 August 2024Files uploaded
- 7 August 2024City answer
- 2 July 2024City answer
- 13 June 2024City answer
- 13 June 2024Files uploaded
- 13 June 2024Files uploaded
- 13 June 2024Files uploaded
- 13 June 2024Files uploaded
- 12 June 2024Files uploaded
- 12 June 2024Files uploaded
- 12 June 2024Files uploaded
- 12 June 2024Files uploaded
- 12 June 2024Files uploaded
- 12 June 2024Files uploaded
- 11 June 2024Files uploaded
- 4 June 2024City answer
- 4 June 2024Files uploaded
- 29 May 2024Files uploaded
- 29 May 2024Files uploaded
- 29 May 2024Files uploaded
- 29 May 2024Files uploaded
- 29 May 2024Files uploaded
- 2 May 2024City answer
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 2 May 2024Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
- 29 December 2023Files uploaded
Documents
Drawings and project files59
- #1.pla
- ჭრილები 01.pdfOpen ↗
- ფასადები 01.pdfOpen ↗
- გენგეგმა შენობა 2.pdfOpen ↗
- გენ-გეგმა.pla
- 010 ჭრილები #2.pdfOpen ↗
Show all (59)Show less
- 010 ფასადები #2.pdfOpen ↗
- #2.pla
- #2.pla
- გენ.გეგმა #2.pdfOpen ↗
- გენ.გეგმა #2.dwg
- გეგმები შენობა #2 -1.pdfOpen ↗
- ჭრილები #2; -1.pdfOpen ↗
- ფასადები #2; -1.pdfOpen ↗
- შენობა #2 1.05.24 ასატვირთი10.pla
- ვიზუალიზაცია.pdfOpen ↗
- მონტაჟი და ვიზუალიზაცია #2.pdfOpen ↗
- A.G_შენობა #2 29.05.pla
- გენ.გეგმა -2.pdfOpen ↗
- გენგეგმა #2 29.05.24.dwg
- მისაწვდომობის გეგმები -3.pdfOpen ↗
- გენგეგმა -3.pdfOpen ↗
- გენგეგმა -3.dwg
- შენობა #2 -3.pla
- შენ. #2.pla
- 449.pla
- 010 შენობა #2; 02,09,2024 ასატვირთი.pla
- გენგეგმა -4.pdfOpen ↗
- გენგეგმა -4.dwg
- გეგმები; შენობა #2; 010.pdfOpen ↗
- ჭრილები; შენობა 2 - 2.pdfOpen ↗
- ფასადები; შენ. #2 - 2.pdfOpen ↗
- მონტაჟი და ვიზუალიზაცია #2 -2.pdfOpen ↗
- გეგმები; შენობა #2; 010 -2.pdfOpen ↗
- გეგმები; შენობა #2; 010 - 2.pdfOpen ↗
- 010 შენობა #2 - 07.10.2024.pla
- გეგმები გაერთიანებული 13.02.2026.pdfOpen ↗
- გენგეგმა.pdfOpen ↗
- გენგეგმა .dwg
- ჭრილები 13.02.2026.pdfOpen ↗
- ფასადები 13.02.2026.pdfOpen ↗
- 23.02.2026 shenoba #2 ასატვირთი.pla
- 17.03.2026 shenoba #2 A ასატვირთი.pla
- 19.03.2026 shenoba #2 ასატვირთი.pla
- გეგმები გაერთიანებული 20.03.2026.pdfOpen ↗
- ფასადები 13.03.2026.pdfOpen ↗
- ჭრილები 13.03.2026.pdfOpen ↗
- გეგმები გაერთიანებული. 20.03.2026.pdfOpen ↗
- გეგმები გაერთიანებული. 27.03.2026.pdfOpen ↗
- ჭრილები 27.03.2026.pdfOpen ↗
- 27.03.2026 shenoba #2 ასატვირთი.pla
- გეგმები გაერთიანებული 21.05.2026.pdfOpen ↗
- ჭრილები 07.05.2026.pdfOpen ↗
- 14.05.2026 shenoba #2.pla
- ფასადები 07.05.2026.pdfOpen ↗
- გენგეგმა 23.07.2026.pdfOpen ↗
- გენგეგმა 23.07.2026.dwg
- გეგმები გაერთიანებული 23.07.2026.pdfOpen ↗
- 23.07.2026 shenoba #2.pla
Consents and orders3
Reports and surveys9
Other files59
- მონტაჟი 1.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა 01.pdfOpen ↗
- ბანერი #1.pdfOpen ↗
- მშ. ორგ პროექტი 01.pdfOpen ↗
- არს. ფოტოები.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა 01.pdfOpen ↗
Show all (59)Show less
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 010 shenoba #2.pdfOpen ↗
- #2----1.jpgOpen ↗
- #2----2.jpgOpen ↗
- #2----3.jpgOpen ↗
- #2----4.jpgOpen ↗
- სიმაღლის განსაზღვრის სქემა #2.pdfOpen ↗
- ექსპერტიზა N2; 23.04.2024.pdfOpen ↗
- მშ. ორგანიზება; შენობა #2; 010.pdfOpen ↗
- ექსპერტიზა; 010.pdfOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 4.jpgOpen ↗
- ენერგოეფექტურობა; შენ. #2; 010.pdfOpen ↗
- არსებული ფოტოები; #2.pdfOpen ↗
- სატრანსპორტო კვლევა.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილება შენობა #2 1.pdfOpen ↗
- 41 და არქიტექტურა -2.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილების გვეგმა.pdfOpen ↗
- გამწვანება შენ. #2; 010 -2.pdfOpen ↗
- გამწვანება შენ. #2; 010 -2.pdfOpen ↗
- ბანერი; შენ. #2.pdfOpen ↗
- 41 და არქიტექტურა -3.pdfOpen ↗
- ბანერი; შენ. #2.pdfOpen ↗
- სატრანსპორტო კვლევა.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა #2 -2.pdfOpen ↗
- გამწვანება შენ. #2; 010 -3.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილება -2.pdfOpen ↗
- გამწვანება; შენობა 2; 010.pdfOpen ↗
- ურბანულის პოზიციები - გაერთიანებული.pdfOpen ↗
- 010 შენობა 2 მშენებლობის ორგანიზება.pdfOpen ↗
- პარკინგის სქემა - 010.pdfOpen ↗
- 010 2 shenoba.pdfOpen ↗
- მშენებლობის ორგანიზების პროექტი 19.02.2026.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილება-03.02.2026.pdfOpen ↗
- 010 პარკინგების განაწილების სქემა.pdfOpen ↗
- 010 2 shenoba - 03.02.2026.pdfOpen ↗
- 010 პარკირების გადანაწილების სქემა.. 20.03.2026.pdfOpen ↗
- 010 2 shenoba.pdfOpen ↗
- 5.jpgOpen ↗
- 3.jpgOpen ↗
- 2.jpgOpen ↗
- 1.jpgOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 5.jpgOpen ↗
- EQSPERTIZA.pdfOpen ↗
- გავლენა.pdfOpen ↗
- 2.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal