ქალაქი თბილისი , პეტრე იბერის ქუჩის შესახვევი N13

AR11008808New constructionMulti-unit residential30 December 2023- Dighomi
Total floor area
77,827.1 m²
Building footprint
73,154.9 m²
Residential area
36,885.4 m²
Plot area
40,230 m²
Height
88.9 m
Depth below ground
6.4 m
Building volume
111,595 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Applicant

Name
მარიამ პაპუკაშვილი
Developer (company ID)
404665331

People

  • Client
    Name
    გიორგი ხუციშვილი
    Personal number
    *********61
    Organization
    შპს დიდი დიღომი რეზიდენსი
    Company code
    404665331
  • Chief architect
    Name
    მარიამ პაპუკაშვილი
    Personal number
    *********58
    Organization
    შპს სტუდიო ალფა სახლი
    Company code
    404664573
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    დემური ტაბატაძე
  • Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    მარიამ პაპუკაშვილი
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    ილია ცხომელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    გიორგი მჭედლიშვილი
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    ლევანი ოქროპირიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.10.06.022.010
Owner
შპს "დიდი დიღომი რეზიდენსი " (404665331)
Area
40,230 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

  • Zone
    Industrial
    Sub-zone
    s-1
    K1
    0
    K2
    0
    Industrial zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
    K3
    0

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11008808
Status
Interim decision
Registered
30 December 2023
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Waiting on
the applicant
since 7 September 2026 (77 days)
Rounds of remarks
8

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 7 September 2026City answer

    შეტყობინებაში დაფიქსირებული მოთხოვნის საფუძველზე განცხადება გიბრუნდებათ შუალედურის სტატუსით განხილვის გარეშე. გაითვალისწინეთ, რომ თქვენ გეძლევათ 15 დღიანი ვადა მითითებული ხარვეზის გამოსასწორებლად, თუ დადგენილ ვადაში განმცხადებელი არ წარმოადგენს შესაბამის დოკუმენტაციას, განცხადება დარჩება განუხილველი.

  2. 4 September 2026City answer
  3. 24 August 2026City answer
  4. 24 August 2026Files uploaded
  5. 24 August 2026Files uploaded
  6. 6 August 2026Files uploaded
  7. 4 August 2026City answer
  8. 4 August 2026Files uploaded
  9. 4 August 2026Files uploaded
  10. 30 July 2026City answer
  11. 30 July 2026Files uploaded
  12. 23 July 2026City answer
  13. 23 July 2026Files uploaded
  14. 23 July 2026Files uploaded
  15. 21 July 2026City answer
  16. 21 July 2026Files uploaded
  17. 21 July 2026Files uploaded
  18. 21 July 2026Files uploaded
  19. 17 July 2026City answer
  20. 17 July 2026Files uploaded
  21. 17 July 2026Files uploaded
  22. 17 July 2026Files uploaded
  23. 24 October 2024Files uploaded
  24. 24 October 2024Files uploaded
  25. 24 October 2024Files uploaded
  26. 24 October 2024Files uploaded
  27. 24 October 2024Files uploaded
  28. 24 October 2024Files uploaded
  29. 24 October 2024Files uploaded
  30. 24 October 2024Files uploaded
  31. 24 October 2024Files uploaded
  32. 24 October 2024Files uploaded
  33. 24 October 2024Files uploaded
  34. 24 October 2024Files uploaded
  35. 8 October 2024Files uploaded
  36. 30 August 2024Files uploaded
  37. 29 December 2023Files uploaded
  38. 29 December 2023Files uploaded
  39. 29 December 2023Files uploaded
  40. 29 December 2023Files uploaded
  41. 29 December 2023Files uploaded
  42. 29 December 2023Files uploaded
  43. 29 December 2023Files uploaded
  44. 29 December 2023Files uploaded
  45. 29 December 2023Files uploaded
  46. 29 December 2023Files uploaded

Documents

Drawings and project files32

  • გენგეგმა შენობა 4.pdfOpen ↗
  • გენ-გეგმა.pla
  • #1.pla
  • გეგმები #4.pdfOpen ↗
  • ჭრილები 01.pdfOpen ↗
  • ფასადები 01.pdfOpen ↗
Show all (32)
  • 010 ჭრილები #4.pdfOpen ↗
  • 010 ფასადები #4.pdfOpen ↗
  • 012 ჭრილები #1.pdfOpen ↗
  • A.G_შენობა #4 Tas ასატვირტი.pla
  • გენგეგმა.pdfOpen ↗
  • გენგეგმა.dwg
  • შენობა #4 - 22.10.24.pla
  • გეგმები 22.10.pdfOpen ↗
  • ჭრილები 22.10.pdfOpen ↗
  • ფასადები 22.10.pdfOpen ↗
  • გეგმები 22.10.pdfOpen ↗
  • ფასადები 22.10.pdfOpen ↗
  • ფასადები 16.07.2026.pdfOpen ↗
  • ჭრილები 16.07.2026.pdfOpen ↗
  • გეგმები გაერთიანებული 16.07.2026.pdfOpen ↗
  • შენობა #4 17.07.2026 შემციირებული.pla
  • გენგეგმა 21.07.2026.pdfOpen ↗
  • გენგეგმა 21.07.2026.dwg
  • გეგმები გაერთიანებული 21.07.2026.pdfOpen ↗
  • შენობა #4 21.07..2026 შემციირებული.pla
  • გენგეგმა 23.07.2026.pdfOpen ↗
  • გენგეგმა 23.07.2026.dwg
  • გენგეგმა 06.08.2026.pdfOpen ↗
  • გენგეგმა 06.08.2026.dwg
  • გეგმები გაერთიანებული 24.08.2026.pdfOpen ↗
  • შენობა #4 11.08.2026 შემცირებული.pla

Consents and orders3

  • დროებითი და მუდმივი სქემები თანხმობებით - 010.pdfOpen ↗
  • დროებითი და მუდმივი სქემები თანხმობებით; 010-2.pdfOpen ↗
  • bank of georgia იპოთეკარის თანხმობა 2026.pdfOpen ↗

Reports and surveys7

  • გეოლოგია 01.pdfOpen ↗
  • კონსტრუქციის საექსპერტო 01.pdfOpen ↗
  • გეოლოგიის საექსპერტო; 010.pdfOpen ↗
  • გეოლოგიური კვლევა; 010.pdfOpen ↗
  • შენობა №4 - შპს სტუდია ალფა სახლი - პეტრე იბერის შესახვევი 13 - საინჟინრო სისტემების პროექტი. 30.07.2026.pdfOpen ↗
  • 010. შენობა # 4. კონსტრუქცია ასატვირთი. 04.08.2026_Optimized.pdfOpen ↗
Show all (7)
  • 010 4 შენობა, მომიჯნავეებზე დასკვნა.pdfOpen ↗

Other files38

  • არს. ფოტოები.pdfOpen ↗
  • სიმაღლის განსაზღვრის სქემა 01.pdfOpen ↗
  • მონტაჟი 4.pdfOpen ↗
  • სიმაღლის განსაზღვრის სქემა 01.pdfOpen ↗
  • ბანერი #1.pdfOpen ↗
  • მშ. ორგ პროექტი 01.pdfOpen ↗
Show all (38)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal