OpenCAD
Approved

ქალაქი თბილისი, მირიან მეფის ქუჩა, N 99

AR11008995New constructionMulti-unit residential1 October 2024- Dighomi
Total floor area
10,746.6 m²
Building footprint
13,503.9 m²
Residential area
5,224.3 m²
Plot area
2,653 m²
Height
67.1 m
Depth below ground
7 m
Building volume
42,000 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7304722
Decision date
29 November 2024
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
გიორგი კირკიტაძე
Developer (company ID)
404513335

People

  • Client
    Name
    გიორგი ქაჯაია
    Personal number
    *********87
    Organization
    გ.თ.ბ
    Company code
    404513335
  • Chief architect
    Name
    გვანცა ზაქარიაშვილი
    Personal number
    *********00
    Organization
    შ.პ.ს "ნიუ მაქს"
    Company code
    404957579
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    თორნიკე მორალიშვილი
  • Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    გიორგი კირკიტაძე
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    ია მშვიდობაძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    მათე საჯაია
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    გიორგი ლოთიშვილი

The people the applicant named in the application form.

Parcel

Cadastral code
01.10.08.005.195
Owner
შპს "გ.თ.ბ" (404513335)
Area
2,653 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11008995
Status
Approved
Registered
1 October 2024
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
1 day
from the last re-submission to the decision
Rounds of remarks
15

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 29 November 2024City answer

    1. შეთანხმდეს ქ. თბილისში, მირიან მეფის ქუჩა, N99 არსებულ მიწის ნაკვეთზე (ს/კ: №01.10.08.005.195) მრავალბინიანი საცხოვრებელი სახლის არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2024 წლის 29 ნოემბრიდან 2027 წლის 29 ნოემბრის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: I რიგის სამუშაოები: 1. მოსამზადებელი სამუშაოები (სამშენებლო მოედნის მოწესრიგება, მათ შორის, ამორტიზებული ან სხვა არსებული ნაგებობების დაშლა და სამშენებლო ნაგვის მოცილება, შესანარჩუნებელი მწვანე ნარგავების დაცვა და მიწისქვეშა საინჟინრო კომუნიკაციების გადატანა, დამცავი ღონისძიებების მოწყობის სამუშაოები, ქვაბულის გამაგრების სამუშაოები, ხიმინჯების მოწყობა და სხვა); 2. შენობა-ნაგებობის გრუნტზე დაკვალვა და ძირითადი ღერძების დაფიქსირება; 3. მიწის ნაკვეთის გრუნტის ზედაპირის ცვლილების შემდეგ გრუნტის შეცვლილ ზედაპირზე შენობა-ნაგებობის გრუნტზე დაკვალვა და ძირითადი ღერძების დაფიქსირება.; I I რიგის სამუშაოები: 4. შენობა-ნაგებობების მიწის სამუშაოები, შენობა-ნაგებობების ფუძის მოწყობის სამუშაოები და შენობა-ნაგებობების საძირკვლის მოწყობის სამუშაოები; <span lang="GEO/KAT" style="font-family:"Sylfaen",serif;mso-

    Show more
  2. 29 November 2024Decision7304722 - Granted
  3. 28 November 2024City answer
  4. 28 November 2024Files uploaded
  5. 20 November 2024City answer
  6. 20 November 2024Files uploaded
  7. 20 November 2024Files uploaded
  8. 20 November 2024Files uploaded
  9. 20 November 2024Files uploaded
  10. 14 November 2024City answer
  11. 14 November 2024Files uploaded
  12. 14 November 2024Files uploaded
  13. 14 November 2024Files uploaded
  14. 14 November 2024Files uploaded
  15. 13 November 2024Files uploaded
  16. 5 November 2024City answer
  17. 5 November 2024Files uploaded
  18. 1 October 2024Files uploaded
  19. 30 September 2024Files uploaded
  20. 20 September 2024City answer
  21. 19 September 2024City answer
  22. 19 September 2024Files uploaded
  23. 27 August 2024City answer
  24. 27 August 2024Files uploaded
  25. 27 August 2024Files uploaded
  26. 27 August 2024Files uploaded
  27. 27 August 2024Files uploaded
  28. 27 August 2024Files uploaded
  29. 27 August 2024Files uploaded
  30. 27 August 2024Files uploaded
  31. 17 August 2024City answer
  32. 17 August 2024Files uploaded
  33. 17 August 2024Files uploaded
  34. 17 August 2024Files uploaded
  35. 16 August 2024Files uploaded
  36. 16 August 2024Files uploaded
  37. 6 August 2024City answer
  38. 6 August 2024Files uploaded
  39. 6 August 2024Files uploaded
  40. 6 August 2024Files uploaded
  41. 6 August 2024Files uploaded
  42. 23 July 2024City answer
  43. 23 July 2024Files uploaded
  44. 23 July 2024Files uploaded
  45. 1 July 2024City answer
  46. 1 July 2024Files uploaded
  47. 1 July 2024Files uploaded
  48. 1 July 2024Files uploaded
  49. 6 June 2024City answer
  50. 6 June 2024Files uploaded
  51. 6 June 2024Files uploaded
  52. 6 June 2024Files uploaded
  53. 6 June 2024Files uploaded
  54. 6 June 2024Files uploaded
  55. 6 June 2024Files uploaded
  56. 12 April 2024City answer
  57. 12 April 2024Files uploaded
  58. 12 April 2024Files uploaded
  59. 18 March 2024City answer
  60. 18 March 2024Files uploaded
  61. 6 February 2024Deadline extendedby 15 days, new deadline: 19 March 2024
  62. 31 December 2023Files uploaded
  63. 31 December 2023Files uploaded
  64. 31 December 2023Files uploaded
  65. 30 December 2023Files uploaded
  66. 30 December 2023Files uploaded
  67. 30 December 2023Files uploaded

Some older entries, and the rest of very long texts, are not shown here.

Documents

Drawings and project files60

  • გენერალური გეგმა_30.12.2023.pdfOpen ↗
  • გენერალური გეგმა_30.12.2023.dwg
  • გეგმები_30.12.2023.pdfOpen ↗
  • ჭრილები_30.12.2023.pdfOpen ↗
  • ფასადები_30.12.2023.pdfOpen ↗
  • ვიზუალიზაცია_30.12.2023.pdfOpen ↗
Show all (60)
  • 30.12.2023_CAD.pla
  • გეგმები_1.30.12.2023.pdfOpen ↗
  • 30.12.2023_CAD.pla
  • გენერალური გეგმა_30.12.2023.pdfOpen ↗
  • 06.06.2024_გენერალური გეგმა.pdfOpen ↗
  • 06.06.2024_Generaluri gegma.dwg
  • 06.06.2024_CAD.pla
  • 06.06.2024_გეგმები.pdfOpen ↗
  • 01.07.2023_გენერალური გეგმა.pdfOpen ↗
  • 01.07.2024_გენერალური გეგმა.dwg
  • 01.07.2024_გეგმები_41-ე_მისაწვდომობა.pdfOpen ↗
  • 01.07.2024_ფასადები.pdfOpen ↗
  • 01.07.2024_ვიზუალიზაცია და ფოტომონტაჟი.pdfOpen ↗
  • 01.07.2024_CAD.pla
  • 23.07.2024_გენერალური გეგმა.pdfOpen ↗
  • 23.07.2024_გენერალური გეგმა.dwg
  • 23.07.2024_გეგმები.pdfOpen ↗
  • 23.07.2024_ჭრილები.pdfOpen ↗
  • 23.07.2023_ფასადები.pdfOpen ↗
  • 23.07.2024.pla
  • 06.08.2024_გენერალური გეგმა.pdfOpen ↗
  • 06.08.2024_გენერალური გეგმა.dwg
  • 06.08.2024_გეგმები.pdfOpen ↗
  • 06.08.2024_ჭრილი.pdfOpen ↗
  • 06.08.2024_ფასადი.pdfOpen ↗
  • 06.08.2024_CAD.pla
  • 16.08.2024_გენერალური გეგმა.pdfOpen ↗
  • 16.08.2024_გენერალური გეგმა.dwg
  • 16.08.2024_გეგმები.pdfOpen ↗
  • 16.08.2024_ფასადები.pdfOpen ↗
  • 16.08.2024_ფასადები.pdfOpen ↗
  • 16.08.2024_CAD.pla
  • 16.08.2024_ჭრილები.pdfOpen ↗
  • 27.08.2024_ვიზუალიზაცია და მონტაჟი.pdfOpen ↗
  • 27.02.2024_გეგმები.pdfOpen ↗
  • 27.08.2024_გეგმები.pdfOpen ↗
  • 27.08.2024_ფასადები.pdfOpen ↗
  • 1_27.8.2024.pla
  • 27.08.2024_გეგმები.pdfOpen ↗
  • 16.09.2024CAD.pla
  • 1.30.09.2024_CAD.pla
  • 13.11.2024_გენერალური გეგმა.pdfOpen ↗
  • 13.11.2024_გენერალური გეგმა.dwg
  • 14.11.2024_გენერალური გეგმა.pdfOpen ↗
  • 14.11.2024_გენერალური გეგმა.dwg
  • 14.11.2024_გეგმები.pdfOpen ↗
  • 14.11.2024_CAD.pla
  • 14.11.2024._გეგმები.pdfOpen ↗
  • 14.11.2024_ჭრილები.pdfOpen ↗
  • 20.10.2024_გენერალური გეგმა.pdfOpen ↗
  • 20.11.2024_გენერალური გეგმა.dwg
  • 20.11.2024_გეგმები.pdfOpen ↗
  • 20.11.2024_გეგმები.pdfOpen ↗
  • 20.11.2024_CAD.pla

Consents and orders7

  • 2024_03_18 კომუნიკაციის წარმომადგენლების თანხმობები.pdfOpen ↗
  • თანხმობები და სქემები, 01.10.08.005.195.pdfOpen ↗
  • 2024_06_06 კომუნიკაციის წარმომადგენლების თანხმობები.pdfOpen ↗
  • 2024_05_16 დამატებითი თანხმობები.pdfOpen ↗
  • 2024_07_01 თანამესაკუთრეების თანხმობები.pdfOpen ↗
  • 2024_08_05 ურბანულის ბრძანების ცვლილება გაერთიანებული [number].pdfOpen ↗
Show all (7)
  • თანხმობები და სქემები, 01.10.08.005.195.pdfOpen ↗

Reports and surveys6

  • ექსპერტიზა_გეოლოგია.pdfOpen ↗
  • ექსპერტიზა_კონსტრუქცია.pdfOpen ↗
  • გეოლოგიური დასკვნის საექსპერტო შეფასება, გთბ 01.10.08.005.195.pdfOpen ↗
  • 01.10.08.005.195_დასკვნა_მშენებლობის გავლენაზე.pdfOpen ↗
  • 01.10.08.005.195_საექსპერტო დასკვნა პროექტის კონსტრუქციულ ნაწილზე.pdfOpen ↗
  • 01.10.08.005.195_დასკვნა_მშენებლობის გავლენაზე.pdfOpen ↗

Other files48

  • არსებული ფოტოები_30.12.2023.pdfOpen ↗
  • მაქს.სიმაღლის განსაზღვრის სქემა_30.12.2023.pdfOpen ↗
  • 1.jpgOpen ↗
  • 2.jpgOpen ↗
  • 3.jpgOpen ↗
  • 31.12.2023_დამატებითი დოკუმენტაცია.rarOpen ↗
Show all (48)
  • მშენებლობის ორგანიზების პროექტი.pdfOpen ↗
  • 2024_04_12 დამატებითი დოკუმენტაცია.rarOpen ↗
  • 06.06.2024_ბანერი.pdfOpen ↗
  • 2024_06_06 დამატებითი დოკუმენტაცია.rarOpen ↗
  • R1_G.jpgOpen ↗
  • R2_G.jpgOpen ↗
  • R3_G.jpgOpen ↗
  • 01.07.2024_ბანერი.pdfOpen ↗
  • 2024_07.01_დამატებითი დოკუმენტაცია.rarOpen ↗
  • 01.07.2024_დენდროლოგიური პროექტი.pdfOpen ↗
  • 2024_07.01_დამატებითი დოკუმენტაცია.rarOpen ↗
  • 23.07.2024_დენდროლოგია.pdfOpen ↗
  • 06.08.2024_მაქსიმალური სიმაღლის განსაზღვრის სქემა.pdfOpen ↗
  • 06.08.2024_დამატებითი დოკუმენტაცია.rarOpen ↗
  • ექსპერტიზა დიდი დიღ. სრული.pdfOpen ↗
  • მოპ, 2024_08_05 გ.თ.ბ დიდი დიღომი 01.10.08.005.195.pdfOpen ↗
  • 17.08.2024_დამატებითი დოკუმენტაცია.rarOpen ↗
  • R1 copy.jpgOpen ↗
  • R2 copy.jpgOpen ↗
  • R3 copy.jpgOpen ↗
  • R_M.jpgOpen ↗
  • ტ.ზ.შ მირიან მეფის ქ. N99 + სამუშაო ფაილი.rarOpen ↗
  • 27.08.2024_დამატებითი დოკუმენტაცია.rarOpen ↗
  • 27.08.2024_დამატებითი დოკუმენტაცია.rarOpen ↗
  • Gegmebi_19.09.2024.pdfOpen ↗
  • Fasadebi_19.09.2024.pdfOpen ↗
  • Vizulaizacia.pdfOpen ↗
  • 1.JPGOpen ↗
  • 1.JPGOpen ↗
  • 1.JPGOpen ↗
  • 1.JPGOpen ↗
  • 1.JPGOpen ↗
  • 30.09.2024_Gegmebi.pdfOpen ↗
  • 30.09.2024_რენდერები და მონტაჟი.pdfOpen ↗
  • R1 copy.jpgOpen ↗
  • R2 copy.jpgOpen ↗
  • R3 copy.jpgOpen ↗
  • M copy.jpgOpen ↗
  • 30.09.2024_Fasadebi.pdfOpen ↗
  • გადახდის ქვითარი.pdfOpen ↗
  • ექსპერტიზა დიდი დიღ. სრული 2.pdfOpen ↗
  • საპატრულო, სატრანსპორტო და კორექტირებული სქემა, 01.10.08.005.195.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal