OpenCAD
Approved

ქალაქი თბილისი , დაბა წყნეთი , ქუჩა რუსთაველი , N1 ; ქალაქი თბილისი , დაბა წყნეთი , რუსთაველის ქუჩა N1-ის მიმდებარედ

AR11029575New constructionOther use11 May 2024- Tskneti
Total floor area
4,432 m²
Building footprint
4,351 m²
Residential area
746 m²
Plot area
840 m²
Height
26 m
Depth below ground
3 m
Building volume
80,564 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7262715
Decision date
24 October 2024
Outcome
Granted
Construction period
24 October 2024 – 24 February 2027
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
თამარი ქოჩიაშვილი
Developer (company ID)
204888817

People

  • Client
    Name
    დავით გაჩეჩილაძე
    Personal number
    *********92
    Organization
    შპს ლუნა 2010
    Company code
    204888817
  • Chief architect
    Name
    თამარი ქოჩიაშვილი
    Personal number
    *********10
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    ოთარ ჩხიკვაძე
  • Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ლუკა ჭკადუა
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გუგა ჭოხონელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    ოთარ ჩხიკვაძე
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    ლევანი ოქროპირიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.20.01.065.067
Owner
შპს "ლუნა 2010" (204888817)
Area
840 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11029575
Status
Approved
Registered
11 May 2024
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
7 days
from the last re-submission to the decision
Rounds of remarks
11

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 24 October 2024City answer

    1. შეთანხმდეს ქალაქ თბილისში, სექტორი - წყნეთი, დაბა წყნეთი, ქუჩა რუსთაველი, N1, კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (საკადასტრო კოდი N 01.20.01.065.067), მრავალფუნქციური კომპლექსი/შენობის არქიტექტურული პროექტის საფუძველზე მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 2. მშენებლობის ვადა განისაზღვროს 2024 წლის 24 ოქტომბრიდან 2027 წლის 24 თებერვლის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 3. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 1) არსებული შენობის დემონტაჟი; 2) მოსამზადებელი სამუშაოები მოედნის მოწესრიგება; 3) დაკვალვა, ძირითადი ღერძების დაფიქსირება; 4) მიწის სამუშაოები, საძირკვლის მოწყობა ძირითადი კონსტრუქციული სისტემის მოწყობა ნულოვან ნიშნულამდე; 5) ძირითადი კარკასის მონტაჟი 0.00 და +22.35 ნიშნულამდე; 6) სახურავის მოწყობა, არამზიდი კონსტრუქციების მოწყობა; 7) ლოკალური და საერთო საინჟინრო ქსელების მოწყობა; 8) გარე მოსაპირკეთებელი სამუშაოები; 9) ტექნოლოგიური მოწყობილობების მონტაჟი ტერიტორიის კეთილმოწყობა; 10) სამშენებლო ნარჩენების გატანა. გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. საქართველოს სივრცის დაგეგმარების, არქიტექტურული და სამშენებლო საქმიანობის კოდექსის 1415 მუხლის შესაბამისად, შენობა-ნაგებობის მშენებლობისას მშენებლობის საჯარო ზედამხედველობის შესაბამისი ორგანოსთვის საეტაპო ოქმის დადგენილი წესით წარუდგენლობისთვის სამშენებლო სამართალდამრღვევს 2025 წლის 31 დეკემბრამდე არ დაეკისრება ამ კოდექსის 132-ე მუხლით გათვალისწინებული პასუხისმგებლობა. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან.

    Show more
  2. 24 October 2024Decision7262715 - Granted
  3. 23 October 2024City answer
  4. 17 October 2024City answer
  5. 17 October 2024Files uploaded
  6. 15 October 2024City answer
  7. 9 October 2024City answer
  8. 9 October 2024Files uploaded
  9. 7 October 2024Files uploaded
  10. 7 October 2024Files uploaded
  11. 3 October 2024City answer
  12. 3 October 2024Files uploaded
  13. 2 October 2024Files uploaded
  14. 2 October 2024Files uploaded
  15. 19 September 2024City answer
  16. 19 September 2024Files uploaded
  17. 19 September 2024Files uploaded
  18. 19 September 2024Files uploaded
  19. 19 September 2024Files uploaded
  20. 2 September 2024City answer
  21. 2 September 2024Files uploaded
  22. 2 September 2024Files uploaded
  23. 2 September 2024Files uploaded
  24. 2 September 2024Files uploaded
  25. 2 September 2024Files uploaded
  26. 2 September 2024Files uploaded
  27. 8 August 2024City answer
  28. 8 August 2024Files uploaded
  29. 16 July 2024City answer
  30. 16 July 2024Files uploaded
  31. 25 June 2024City answer
  32. 25 June 2024Files uploaded
  33. 23 June 2024Files uploaded
  34. 23 June 2024Files uploaded
  35. 23 June 2024Files uploaded
  36. 23 June 2024Files uploaded
  37. 18 June 2024Deadline extendedby 15 days, new deadline: 11 July 2024
  38. 21 April 2024Files uploaded
  39. 21 April 2024Files uploaded
  40. 21 April 2024Files uploaded
  41. 21 April 2024Files uploaded
  42. 21 April 2024Files uploaded
  43. 21 April 2024Files uploaded
  44. 20 April 2024Files uploaded
  45. 20 April 2024Files uploaded
  46. 16 April 2024Files uploaded

Documents

Drawings and project files27

  • გენგეგმა 20 აპრილი.pdfOpen ↗
  • გენგეგმა 20 აპრ.dwg
  • გეგმები 20 აპრილი.pdfOpen ↗
  • ჭრილები 20 აპრილი.pdfOpen ↗
  • ფასადები დეტალებით 20 აპრილი.pdfOpen ↗
  • წყნეთი 20 აპრილი.dwg
Show all (27)
  • გენგეგმა.pdfOpen ↗
  • გენგეგმა.dwg
  • გეგმები 24 ივნისი.pdfOpen ↗
  • ფასადები კვანძებით 24 ივნისი.pdfOpen ↗
  • წყნეთი სამუშაო ფაილი 24 ივნისი.dwg
  • გენგეგმა 30 აგვისტო.pdfOpen ↗
  • გენგეგმა 30 აგვისტო.dwg
  • გეგმები 31 აგვისტო.pdfOpen ↗
  • ჭრილები 30 აგვისტო.pdfOpen ↗
  • წყნეთი dwg 31 აგვისტო.dwg
  • ფასადები კვანძებით 30 აგვისტო.pdfOpen ↗
  • გეგმები 16 სექტემბერი.pdfOpen ↗
  • წყნეთი dwg 16 სექტემბერი.dwg
  • გეგმები 30 sept.pdfOpen ↗
  • წყნეთი სამუშაო ფაილი .dwg
  • გეგმები 30 sept.pdfOpen ↗
  • ფასადები 2 ოქტ კვანძებით.pdfOpen ↗
  • გენგეგმა 18 ოქტომბერი.pdfOpen ↗
  • გენგეგმა 18 ოქტომბერი.dwg
  • გეგმები 18 ოქტ.pdfOpen ↗
  • სამუშაო ფაილი წყნეთი 18 ოქტომბერი.dwg

Consents and orders4

  • თელასის. გარემოს ცადვის. სილქნეტის. თბილისი ენერჯის თანხმობები.pdfOpen ↗
  • შპს ლუნა თბილსერვისის თანხმობა.pdfOpen ↗
  • თბილისი ენერჯი და თბილსერვისის თანხმობები.pdfOpen ↗
  • თბილისი ენერჯი და თბილსერვისის თანხმობები.pdfOpen ↗

Reports and surveys12

  • დასკვნა ზემოქმედებაზე_1.pdfOpen ↗
  • წყნეთი გეოლოგია ექსპერტიზით.pdfOpen ↗
  • დასკვნა კონსტრუქციებზე.pdfOpen ↗
  • 2024.04.01-კონსტრუქციები წყნეთი.pdfOpen ↗
  • საინჟინრო ქსელები 24 ივნისი.pdfOpen ↗
  • დასკვნა კონსტრუქციებზე.pdfOpen ↗
Show all (12)
  • დასკვნა ზემოქმედება.pdfOpen ↗
  • გეოლოგია-01.20.01.065.067-განახლებული-2024.pdfOpen ↗
  • 2024.09.17-კონსტრუქციები.pdfOpen ↗
  • დასკვნა დაძაბულ-დეფორმირებულ მდგომარეობაზე.pdfOpen ↗
  • დასკვნა დაძაბულ-დეფორმირებულ მდგომარეობაზე.pdfOpen ↗
  • სივრცითი მოდელის ანგარიში.pdfOpen ↗

Other files34

  • ფოტოსურათები 20 აპრილი.pdfOpen ↗
  • სიმაღლის სხივი 20აპრ.pdfOpen ↗
  • შეთანხმებული სატრანსპორტო სქემები.pdfOpen ↗
  • მშენებლობის ორგანიზების პროექტი (2).pdfOpen ↗
  • ექსპერტიზა და ანალიზი წყნეთი.pdfOpen ↗
  • დენდროლოგია 20 აპრილი.pdfOpen ↗
Show all (34)
  • ენერგოეფექტურობა წყნეთი (ხელმოწერილი).pdfOpen ↗
  • ფოტომონტაჟი და აქს ხედები.pdfOpen ↗
  • ფოტო1.jpgOpen ↗
  • ფოტო2.jpgOpen ↗
  • ფოტო3.jpgOpen ↗
  • ფოტო4.jpgOpen ↗
  • საინფორმაციო აბრა 20 პრილი.pdfOpen ↗
  • ენერგოეფექტურობა წყნეთი 19 ივნისი.pdfOpen ↗
  • სიმაღლის სხივი.pdfOpen ↗
  • აბრა 24 ივნისი.pdfOpen ↗
  • მშენებლობის ორგანიზების პროექტი 19 ივნისი.pdfOpen ↗
  • სიმაღლის სხივი 24 ივნისი.pdfOpen ↗
  • წყნეთი, რუსთაველის ქუჩა #1- საექსპერტო შეფასება-signed.pdfOpen ↗
  • small1.jpgOpen ↗
  • small2.jpgOpen ↗
  • small3.jpgOpen ↗
  • small4.jpgOpen ↗
  • საკადასტრო სერვიტუტით 28 აგვისტო.pdfOpen ↗
  • საკადასტრო სერვიტუტით 28 აგვისტო.pdfOpen ↗
  • ფოტომონტაჟი და აქს ხედები 18 სექტემბერი.pdfOpen ↗
  • სამშენებლო მოსაკრებელი ნაწილი.pdfOpen ↗
  • ფოტომონტაჟი და აქს ხედები 2 ოქტომბერი.pdfOpen ↗
  • 2024.10.02.pdfOpen ↗
  • B&W_Photo - 5.jpgOpen ↗
  • 1.jpgOpen ↗
  • 2.jpgOpen ↗
  • 3-small.jpgOpen ↗
  • სამშენებლო მოსაკრებელი ნაწილი 2-ოქტ.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal