AR11039648New constructionOther use3 June 2024
Total floor area
18,773.7 m²
Building footprint
2,521,067 m²
Plot area
22,007 m²
Height
21.4 m
Depth below ground
7.6 m
Building volume
81,640 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7262966
Decision date
24 October 2024
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
ელგუჯა პატაშური
Developer (company ID)
404906722

People

  • Client
    Name
    ნოდარ გიორგაძე
    Organization
    შპს ეკო ინვესტი
    Company code
    400237463
  • Chief architect
    Name
    მაცაცო ჯინჭარაშვილი
    Personal number
    *********00
    Organization
    შ.პ.ს "line georgia"
    Company code
    406030593
  • Co-authors
    Name
    გურამი სიჭინავა
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    დავით გვასალია
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    გიორგი გურგენიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.12.21.001.538
Owner
შპს ''პრომენადა'' (400405325)
Area
22,007 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 10 October 2026

Plots and zoning

  • Zone
    Environmental protection
    Sub-zone
    gdz-3
    K1
    0
    K2
    0
    Environmental protection zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
    K3
    0

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11039648
Status
Approved
Registered
3 June 2024
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
6 days
from the last re-submission to the decision
Rounds of remarks
14

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 24 October 2024City answer

    1. შეთანხმდეს ქ. თბილისში, ქალაქი თბილისი , ბეშენოვას ქუჩა N9 / ლიპტოვის ქუჩა N8; ქალაქი თბილისი , ბეშენოვას ქუჩა N30 ; ქალაქი თბილისი , ბეშენოვას ქუჩა N26 ; ქალაქი თბილისი , ბეშენოვას ქუჩა N28 ; ქალაქი თბილისი , ბეშენოვას ქუჩა N22 ; ქალაქი თბილისი , ბეშენოვას ქუჩა N24 -ში, არსებულ მიწის ნაკვეთზე (ს/კ: №01.12.21.001.538) სასტუმროს არქიტექტურული პროექტი.

  2. 24 October 2024Decision7262966 - Granted
  3. 23 October 2024City answer
  4. 18 October 2024City answer
  5. 18 October 2024Files uploaded
  6. 18 October 2024Deadline extendedby 15 days, new deadline: 11 November 2024
  7. 26 September 2024City answer
  8. 26 September 2024Files uploaded
  9. 25 September 2024Files uploaded
  10. 19 September 2024City answer
  11. 19 September 2024Files uploaded
  12. 19 September 2024Files uploaded
  13. 17 September 2024City answer
  14. 17 September 2024Files uploaded
  15. 17 September 2024Files uploaded
  16. 17 September 2024Files uploaded
  17. 6 September 2024City answer
  18. 6 September 2024Files uploaded
  19. 6 September 2024Files uploaded
  20. 6 September 2024Files uploaded
  21. 3 September 2024Files uploaded
  22. 3 September 2024Files uploaded
  23. 14 August 2024City answer
  24. 14 August 2024Files uploaded
  25. 14 August 2024Files uploaded
  26. 23 July 2024City answer
  27. 23 July 2024Files uploaded
  28. 23 July 2024Files uploaded
  29. 23 July 2024Files uploaded
  30. 23 July 2024Files uploaded
  31. 19 July 2024City answer
  32. 19 July 2024Files uploaded
  33. 17 July 2024Files uploaded
  34. 16 July 2024Files uploaded
  35. 5 July 2024City answer
  36. 5 July 2024Files uploaded
  37. 24 June 2024Files uploaded
  38. 18 June 2024City answer
  39. 18 June 2024Files uploaded
  40. 18 June 2024Files uploaded
  41. 18 June 2024Files uploaded
  42. 17 June 2024Files uploaded
  43. 12 June 2024City answer
  44. 12 June 2024Files uploaded
  45. 12 June 2024Files uploaded
  46. 12 June 2024Files uploaded
  47. 12 June 2024Files uploaded
  48. 12 June 2024Files uploaded
  49. 12 June 2024Files uploaded
  50. 6 June 2024City answer
  51. 6 June 2024Files uploaded
  52. 6 June 2024Files uploaded
  53. 6 June 2024Files uploaded
  54. 6 June 2024Files uploaded
  55. 31 May 2024Files uploaded
  56. 31 May 2024Files uploaded
  57. 31 May 2024Files uploaded
  58. 31 May 2024Files uploaded
  59. 31 May 2024Files uploaded
  60. 31 May 2024Files uploaded
  61. 31 May 2024Files uploaded
  62. 31 May 2024Files uploaded
  63. 31 May 2024Files uploaded
  64. 31 May 2024Files uploaded

Documents

Drawings and project files50

  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი.pla
  • A.05 გენ გეგმა.pdfOpen ↗
Show all (50)
  • A.05 გენ გეგმა.dwg
  • სასტუმრო_მე-5 სექტორი.pla
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • A.02 Sections.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • გეგმები.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი.pla
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • A.05 გენ გეგმა.pdfOpen ↗
  • გეგმები.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი.pla
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • გეგმები.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი.pla
  • გეგმები.pdfOpen ↗
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • სასტუმრო_მე-5 სექტორი.pla
  • სასტუმრო_მე-5 სექტორი.pla
  • A.05 გენ გეგმა.pdfOpen ↗
  • A.05 გენ გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • A.05 გენ გეგმა.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი.pla
  • გეგმები.pdfOpen ↗
  • A.02 Sections.pdfOpen ↗
  • სასტუმრო_მე-5 სექტორი თაბაშირ მუყაოს კედლებით.pla

Consents and orders1

  • სატრანსპორტო თანხმობებით.pdfOpen ↗

Reports and surveys10

  • გეოლოგია, s.k. 01.12.21.001.538.rarOpen ↗
  • გეოლოგია და საინჟინრო.rarOpen ↗
  • გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
Show all (10)
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗
  • კონსტრუქცია, გეოლოგია, საინჟინრო, ჯვპ-ს თანხმობა.rarOpen ↗

Other files43

  • A.03 Elevations.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • ჯინო სასტუმრო, ენერგო ეფექტურობა.pdfOpen ↗
  • satransporto kvleva Jino (1).zipOpen ↗
  • satransporto kvleva Jino (1).zipOpen ↗
  • შეთანხმებული სქემები.pdfOpen ↗
Show all (43)
  • ტერიტორიის სურათები.pdfOpen ↗
  • Scene 71.jpgOpen ↗
  • Scene 72.jpgOpen ↗
  • Scene 73.jpgOpen ↗
  • Scene 74.jpgOpen ↗
  • Scene 75.jpgOpen ↗
  • montaj.pdfOpen ↗
  • ექსპერტიზა sc-1.pdfOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • montaj.pdfOpen ↗
  • ჯინო სასტუმრო, ენერგო ეფექტურობა.pdfOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • montaj.pdfOpen ↗
  • montaj.pdfOpen ↗
  • ექსპერტიზა sc-1.pdfOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • Scene 71_2.jpgOpen ↗
  • Scene 72_2.jpgOpen ↗
  • Scene 73_2.jpgOpen ↗
  • Scene 77 copy.jpgOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • ექსპერტიზა sc-1.pdfOpen ↗
  • ჯინო ზეგავლენა მომიჯნავე.pdfOpen ↗
  • A.03 Elevations.pdfOpen ↗
  • გამწვანების პროექტი, ჯინო, სექტორი 5.pdfOpen ↗
  • ექსპერტიზა sc-1.pdfOpen ↗
  • ექსპერტიზა sc-1.pdfOpen ↗
  • 02, გამწვანების პროექტი, ჯინო, სექტორი 5.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • 02, გამწვანების პროექტი, ჯინო, სექტორი 5 ++.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • A.04 სიმაღლის განსაზღვრა.pdfOpen ↗
  • ჯინო 5 seqt axali taqs.pdfOpen ↗
  • 03, გამწვანების პროექტი. ჯინო. სექტორი 5.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal