OpenCAD
Not reviewed

ქალაქი თბილისი , მუხაძის ქუჩა N5-ის მიმდებარედ

AR11061721Change to approved projectOther use11 October 2024- Orkhevi
Total floor area
2,611.3 m²
Building footprint
2,677.7 m²
Plot area
3,349 m²
Height
9.6 m
Depth below ground
1 m
Building volume
22,000 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7252824
Decision date
16 October 2024
Outcome
Other
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
ლაშა ჩიკვილაძე
Developer (company ID)
406132288

People

  • Client
    Name
    ლაშა ჩიკვილაძე
    Personal number
    *********10
    Organization
    შპს ქორუგატორი
    Company code
    406132288
  • Chief architect
    Name
    თორნიკე სადრაძე
    Personal number
    *********18
    Organization
    შ.პ.ს ურბან სკეტჩერსი
    Company code
    400357939
  • Co-authors
    Name
    თამარ ნკოლაშვილი
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    გაიოზ ჭანკვეტაძე
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    თორნიკე სადრადძე
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    ილია ცხომელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    დემური ტაბატაძე
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    დავით კურდღელია

The people the applicant named in the application form.

Parcel

Cadastral code
01.19.17.003.052
Owner
თეა დოლიძე (P/N: *********43)
Area
3,349 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 3 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11061721
Status
Not reviewed
Registered
11 October 2024
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
5 days
from registration to the decision
Rounds of remarks
1

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 16 October 2024City answer

    შეტყობინებით დაფიქსირებული მოთხოვნიდან გამომდინარე AR11061721 განცხადება რჩება განუხილველი.

  2. 16 October 2024Decision7252824 - Other
  3. 11 October 2024Files uploaded

Documents

Drawings and project files5

  • gengegma.dwg
  • გეგმები დაკორექტირებული 41 მისაწვდომობა.pdfOpen ↗
  • ჭრილები კორექტირება.pdfOpen ↗
  • ფასადები დაკორექტირებული.pdfOpen ↗
  • საწყობი კორექტირება.pla

Reports and surveys3

  • დასკვნა მომიჯნავეები მუხაძის ქუჩა.pdfOpen ↗
  • [number]_11) გეოლოგია და ექსპერტიზა.pdfOpen ↗
  • [number]_40) კონსტრუქცია დაკორექტირებული.pdfOpen ↗

Other files12

  • gengegma.pdfOpen ↗
  • არსებული 11.10.2024.pdfOpen ↗
  • simaRlis gansazRvris sqema.pdfOpen ↗
  • აქსონომეტირა მონტაჯი.pdfOpen ↗
  • მონტაჟი აქსონომეტრია დაკორექტირებული.pdfOpen ↗
  • 1.jpgOpen ↗
Show all (12)
  • 2.jpgOpen ↗
  • 3.jpgOpen ↗
  • გამწვანების პროექტი.pdfOpen ↗
  • [number]_52) 41 misawvdomoba eqspertiza.pdfOpen ↗
  • [number]_11) ბანერი.pdfOpen ↗
  • ორგანიზების გრაფიკი ჩაბარების აქტები.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal