Approved

ქალაქი თბილისი , გამზირი დ.გურამიშვილი , N 84

AR11063145Change to approved projectOther use20 February 2025
Total floor area
4,760.7 m²
Building footprint
5,092.3 m²
Plot area
8,530 m²
Height
15.1 m
Depth below ground
2.1 m
Building volume
6,500 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7911579
Decision date
7 May 2026
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
ბექარი კინწურაშვილი
Developer (company ID)
206314898

People

  • Client
    Name
    მარიამ დუდუჩავა
    Personal number
    *********19
    Organization
    შ.პ.ს ''ლიბო გრუპ''
    Company code
    206314898
  • Chief architect
    Name
    ბექარი კინწურაშვილი
    Personal number
    *********81
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    იუზა გეფერიძე
  • SpecialistIII კლასს დაქვემდებარებული შენობა-ნაგებობების მშენებლობის განხორციელების დოკუმენტების პროექტების არქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე“ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთ
    Name
    ლევან ოქროპირიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.12.01.003.276
Owner
შპს "ლიბო გრუპ" (206314898)
Area
8,530 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

  • Zone
    Transport
    Sub-zone
    tz-3
    K1
    0
    K2
    0
    Transport zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
    K3
    0

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11063145
Status
Approved
Registered
20 February 2025
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
2 days
from the last re-submission to the decision
Rounds of remarks
14

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 7 May 2026City answer

    1. შეთანხმდეს ქალაქ თბილისში, გამზირი დ.გურამიშვილი, N84 შპს „ლიბო გრუპ“-ის კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (საკადასტრო კოდი N 01.12.01.003.276) საწყობის კორექტირებული არქიტექტურული პროექტი . 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2026 წლის 7 მაისიდან 2027 წლის 7 აპრილის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 6) ფასადის საკედლე პანელის მოწყობა 7) სახურავის მოწყობა 8) კარფანჯრების მონტაჟი 9) საინჟინრო ნაწილების მონტაჟი 10) გარე ტერიტორიის კეთილმოწყობა გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. საქართველოს სივრცის დაგეგმარების, არქიტექტურული და სამშენებლო საქმიანობის კოდექსის 1415 მუხლის შესაბამისად, შენობა-ნაგებობის მშენებლობისას მშენებლობის საჯარო ზედამხედველობის შესაბამისი ორგანოსთვის საეტაპო ოქმის დადგენილი წესით წარუდგენლობისთვის სამშენებლო სამართალდამრღვევს 2026 წლის 31 დეკემბრამდე არ დაეკისრება ამ კოდექსის 132-ე მუხლით გათვალისწინებული პასუხისმგებლობა. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან.

    Show more
  2. 7 May 2026Decision7911579 - Granted
  3. 5 May 2026City answer
  4. 5 May 2026Files uploaded
  5. 1 May 2026City answer
  6. 30 April 2026Files uploaded
  7. 28 April 2026Files uploaded
  8. 23 April 2026City answer
  9. 23 April 2026Files uploaded
  10. 14 April 2026City answer
  11. 14 April 2026Files uploaded
  12. 14 April 2026Files uploaded
  13. 14 April 2026Files uploaded
  14. 7 April 2026Files uploaded
  15. 29 January 2026City answer
  16. 29 January 2026Files uploaded
  17. 30 December 2025City answer
  18. 29 December 2025Files uploaded
  19. 29 December 2025Files uploaded
  20. 29 December 2025Files uploaded
  21. 29 December 2025Files uploaded
  22. 29 December 2025Files uploaded
  23. 24 December 2025City answer
  24. 24 December 2025Files uploaded
  25. 23 December 2025Files uploaded
  26. 23 December 2025Files uploaded
  27. 23 December 2025Files uploaded
  28. 1 July 2025City answer
  29. 1 July 2025Files uploaded
  30. 1 July 2025Files uploaded
  31. 1 July 2025Files uploaded
  32. 3 June 2025City answer
  33. 3 June 2025Files uploaded
  34. 3 June 2025Files uploaded
  35. 3 June 2025Files uploaded
  36. 3 June 2025Files uploaded
  37. 3 June 2025Files uploaded
  38. 7 May 2025City answer
  39. 7 May 2025Files uploaded
  40. 7 May 2025Files uploaded
  41. 7 May 2025Files uploaded
  42. 7 May 2025Files uploaded
  43. 7 April 2025City answer
  44. 6 April 2025Files uploaded
  45. 6 April 2025Files uploaded
  46. 6 April 2025Files uploaded
  47. 6 April 2025Files uploaded
  48. 6 April 2025Files uploaded
  49. 16 March 2025City answer
  50. 14 March 2025Files uploaded
  51. 14 March 2025Files uploaded
  52. 14 March 2025Files uploaded
  53. 13 March 2025Files uploaded
  54. 10 March 2025City answer
  55. 8 March 2025Files uploaded
  56. 8 March 2025Files uploaded
  57. 8 March 2025Files uploaded
  58. 20 February 2025Files uploaded
  59. 17 February 2025Files uploaded
  60. 17 February 2025Files uploaded
  61. 16 February 2025Files uploaded
  62. 16 February 2025Files uploaded
  63. 21 January 2025Files uploaded
  64. 21 January 2025Files uploaded
  65. 23 October 2024Files uploaded
  66. 23 October 2024Files uploaded
  67. 23 October 2024Files uploaded
  68. 23 October 2024Files uploaded

Documents

Drawings and project files53

  • გენ-გეგმა.dwg
  • კორექტირებული გეგმები.pdfOpen ↗
  • კორექტირებული ჭრილები.pdfOpen ↗
  • კორექტირებული ფასადები.pdfOpen ↗
  • კორექტირებული ფასადები.pdfOpen ↗
  • გეგმები.pdfOpen ↗
Show all (53)
  • ჭრილები.pdfOpen ↗
  • ფასადები.pdfOpen ↗
  • გეგმები 01.pdfOpen ↗
  • ჭრილები 01.pdfOpen ↗
  • ფასადები 01.pdfOpen ↗
  • სამუშაო ფაილი 01.pla
  • ჭრილები 01.pdfOpen ↗
  • სამუშაო ფაილი 01_.pla
  • გეგმები 02.pdfOpen ↗
  • ჭრილები 02.pdfOpen ↗
  • ფასადები 02.pdfOpen ↗
  • სამუშაო ფაილი - 02.pla
  • გეგმები 03.pdfOpen ↗
  • ჭრილები 03.pdfOpen ↗
  • ფასადები 03.pdfOpen ↗
  • სამუშაო ფაილი - 03.pla
  • გეგმები 04.pdfOpen ↗
  • სამუშაო ფაილი 04.pla
  • გეგმები 04_.pdfOpen ↗
  • ჭრილები 04.pdfOpen ↗
  • ფასადები 04.pdfOpen ↗
  • სამუშაო ფაილი 05.pla
  • ჭრილები 05.pdfOpen ↗
  • ფასადები 05.pdfOpen ↗
  • გეგმები 05.pdfOpen ↗
  • სამუშაო ფაილი 06.pla
  • ფასადები 06.pdfOpen ↗
  • ჭრილები 06.pdfOpen ↗
  • გეგმები 06.pdfOpen ↗
  • სამუშაო ფაილი 07.pla
  • ფასადები 07.pdfOpen ↗
  • ჭრილები 07.pdfOpen ↗
  • გეგმები 07.pdfOpen ↗
  • სამუშაო ფაილი 08.pla
  • გენ-გეგმა 01.dwg
  • გეგმები 08.pdfOpen ↗
  • ჭრილები 08.pdfOpen ↗
  • ფასადები 08.pdfOpen ↗
  • სამუშაო 08.pla
  • გეგმები 08.pdfOpen ↗
  • გეგმები 09.pdfOpen ↗
  • ჭრილები 09.pdfOpen ↗
  • ფასადები 09.pdfOpen ↗
  • სამუშაო 09.pla
  • გეგმები 09.pdfOpen ↗
  • გეგმები 10.pdfOpen ↗
  • სამუშაო 10.pla

Consents and orders2

  • ელმავალმშენებელი და თანამესაკუთრეთა თანხმობები.pdfOpen ↗
  • იპოთეკარის და სხვ. თანხმობები.pdfOpen ↗

Reports and surveys7

  • ტოპო და გენ-გეგმა.pdfOpen ↗
  • ლიბო საინჟინრო პროექტი.pdfOpen ↗
  • ლიბო საინჟინრო პროექტი_1.pdfOpen ↗
  • ლიბო საინჟინრო პროექტი_2.pdfOpen ↗
  • ტოპო და გენ-გეგმა 01.pdfOpen ↗
  • საინჟინრო ქსელები 01.pdfOpen ↗
Show all (7)
  • კორექტ. საინჟინრო ქსელები 02.pdfOpen ↗

Other files77

  • შეთანხმებული აქს. ხედები.pdfOpen ↗
  • ექსპერტიზა 30.10.pdfOpen ↗
  • მინდიბილობა და დამოწმებული დოკუმენტაციები.pdfOpen ↗
  • სქემა.pdfOpen ↗
  • კორექტ. აქს. ხედები.pdfOpen ↗
  • 1_5 - Photo.jpgOpen ↗
Show all (77)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal