ქალაქი თბილისი , ქუჩა შეშელიძე , N 18
- Total floor area
- 57,536.1 m²
- Building footprint
- 64,760 m²
- Residential area
- 25,435.4 m²
- Plot area
- 9,377 m²
- Height
- 105.6 m
- Depth below ground
- 8.6 m
- Building volume
- 166,512.3 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 7665673
- Decision date
- 15 October 2025
- Outcome
- Granted
- Construction period
- 15 October 2025 – 15 November 2027
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- მარიამ პაპუკაშვილი
- Developer (company ID)
- 400347246
People
- Client
- Name
- მიხეილ მიქაბერიძე
- Personal number
- *********02
- Organization
- შპს ალფა სახლი გლდანში
- Company code
- 400347246
- Chief architect
- Name
- მარიამ პაპუკაშვილი
- Personal number
- *********58
- Organization
- შპს სტუდიო ალფა სახლი
- Company code
- 404664573
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- დემური ტაბატაძე
- Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- მარიამ პაპუკაშვილი
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- გუგა ჭოხონელიძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- დემური ტაბატაძე
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- ლევანი ოქროპირიძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.11.04.026.046
- Owner
- შპს "ხიდმშენი N2" (205269500) (205269500)
- Area
- 9,377 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 3 October 2026
Plots and zoning
- 01.11.04.026.046Registry extract ↗ (opens in a new tab)
- Zone
- Industrial
- Sub-zone
- s-1
- K1
- 0
- K2
- 0
- Industrial zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
- K3
- 0
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR11069211
- Status
- Approved
- Registered
- 28 January 2025
- Type
- Change to approved project
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Length of the case
- 5 days
- from the last re-submission to the decision
- Rounds of remarks
- 21
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 15 October 2025City answer
1. შეთანხმდეს ქ. თბილისში, ქუჩა შეშელიძე , N 18 არსებულ მიწის ნაკვეთზე (ს/კ: №01.11.04.026.046) მრავალფუნქციური კომპლექსის/შენობის კორექტირებული არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2025 წლის 15 ოქტომბრიდან 2027 წლის 15 ნოემბრის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 21) 26 სართულების ძირითადი კონსტრუქციული სისტემებისა, შენობა-ნაგებობის სახურავისა და გადახურვის მოწყობა +88.50, +94.80 და 97.00 ნიშნულზე ; 22) არამზიდი კონსტრუქციების მოწყობა ; 23) შენობა-ნაგებობის ლოკალური საერთო სარგებლობის საინჟინრო-ტექნიკური ქსელების მოწყობა ; 24) ტექნოლოგიური მოწყობილობების მონტაჟი ; 25) შენობა-ნაგებობის გარე მოსაპირკეთებელი სამუშაოები ; 26) მიწის ნაკვეთის კეთილმოწყობის სამუშაოები ; გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. საქართველოს სივრცის დაგეგმარების, არქიტექტურული და სამშენებლო საქმიანობის კოდექსის 1415 მუხლის შესაბამისად, შენობა-ნაგებობის მშენებლობისას მშენებლობის საჯარო ზედამხედველობის შესაბამისი ორგანოსთვის საეტაპო ოქმის დადგენილი წესით წარუდგენლობისთვის სამშენებლო სამართალდამრღვევს 2025 წლის 31 დეკემბრამდე არ დაეკისრება ამ კოდექსის 132-ე მუხლით გათვალისწინებული პასუხისმგებლობა. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან.
Show moreShow less
- 15 October 2025Decision7665673 - Granted
- 10 October 2025City answer
- 10 October 2025Files uploaded
- 10 October 2025Files uploaded
- 10 October 2025Files uploaded
- 10 October 2025Files uploaded
- 8 October 2025City answer
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 8 October 2025Files uploaded
- 3 October 2025City answer
- 3 October 2025Files uploaded
- 3 October 2025Files uploaded
- 3 October 2025Files uploaded
- 3 October 2025Files uploaded
- 1 October 2025City answer
- 1 October 2025Files uploaded
- 1 October 2025Files uploaded
- 1 October 2025Files uploaded
- 1 October 2025Files uploaded
- 26 September 2025City answer
- 26 September 2025Files uploaded
- 24 September 2025City answer
- 24 September 2025Files uploaded
- 24 September 2025Files uploaded
- 22 September 2025Files uploaded
- 22 September 2025Files uploaded
- 22 September 2025Files uploaded
- 18 September 2025City answer
- 16 September 2025City answer
- 16 September 2025Files uploaded
- 16 September 2025Files uploaded
- 16 September 2025Files uploaded
- 16 September 2025Files uploaded
- 16 September 2025Files uploaded
- 16 September 2025Files uploaded
- 12 September 2025Files uploaded
- 12 September 2025Files uploaded
- 12 September 2025Files uploaded
- 11 September 2025Files uploaded
- 11 September 2025Files uploaded
- 11 September 2025Files uploaded
- 11 September 2025Files uploaded
- 11 August 2025City answer
- 11 August 2025Files uploaded
- 11 August 2025Files uploaded
- 11 August 2025Files uploaded
- 11 August 2025Files uploaded
- 11 August 2025Files uploaded
- 8 August 2025Files uploaded
- 8 August 2025Files uploaded
- 8 August 2025Files uploaded
- 6 August 2025City answer
- 6 August 2025Files uploaded
- 6 August 2025Files uploaded
- 6 August 2025Files uploaded
- 6 August 2025Files uploaded
- 6 August 2025Files uploaded
- 6 August 2025Files uploaded
- 4 August 2025City answer
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 4 August 2025Files uploaded
- 29 July 2025City answer
- 29 July 2025Files uploaded
- 14 July 2025City answer
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 14 July 2025Files uploaded
- 11 July 2025Files uploaded
- 11 July 2025Files uploaded
- 9 July 2025City answer
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 9 July 2025Files uploaded
- 4 July 2025City answer
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 4 July 2025Files uploaded
- 2 July 2025Files uploaded
- 26 June 2025City answer
- 25 June 2025City answer
- 25 June 2025Files uploaded
- 25 June 2025Files uploaded
- 25 June 2025Files uploaded
- 23 June 2025Files uploaded
- 23 June 2025Files uploaded
- 23 June 2025Files uploaded
- 23 June 2025Files uploaded
- 20 June 2025Files uploaded
- 20 June 2025Files uploaded
- 6 June 2025City answer
- 6 June 2025Files uploaded
- 6 June 2025Files uploaded
- 6 June 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 20 May 2025Files uploaded
- 11 March 2025City answer
- 18 February 2025City answer
- 18 February 2025Files uploaded
- 18 February 2025Files uploaded
- 18 February 2025Files uploaded
- 18 February 2025Files uploaded
- 17 February 2025Files uploaded
- 17 February 2025Files uploaded
- 17 February 2025Files uploaded
- 17 February 2025Files uploaded
- 17 February 2025Files uploaded
- 17 February 2025Files uploaded
- 5 February 2025Files uploaded
- 5 February 2025Files uploaded
- 5 February 2025Files uploaded
- 5 February 2025Files uploaded
- 5 February 2025Files uploaded
- 28 January 2025Files uploaded
- 28 January 2025Files uploaded
- 27 January 2025Files uploaded
- 24 January 2025Files uploaded
- 24 January 2025Files uploaded
- 24 January 2025Files uploaded
- 24 January 2025Files uploaded
- 24 January 2025Files uploaded
- 22 January 2025Files uploaded
- 22 January 2025Files uploaded
- 22 January 2025Files uploaded
- 22 January 2025Files uploaded
- 19 December 2024Files uploaded
- 19 December 2024Files uploaded
- 9 December 2024Files uploaded
- 6 December 2024Files uploaded
- 6 December 2024Files uploaded
Documents
Drawings and project files112
- გლდანი__არქივი.pla
- გენ-გეგმა.pdfOpen ↗
- ჭრილები.pdfOpen ↗
- ფასადები.pdfOpen ↗
- გენ-გეგმა DWG.dwg
- გეგმები - 27.01.pdfOpen ↗
Show all (112)Show less
- გეგმები - 28.01.pdfOpen ↗
- გენ-გეგმა 1.pdfOpen ↗
- გენ-გეგმა.dwg
- გლდანი__არქივი - 05.02.pla
- გეგმები - 05.02.pdfOpen ↗
- ჭრილები - 17.02..pdfOpen ↗
- გენ-გეგმა - 17.02.pdfOpen ↗
- გეგმები - 17.02.pdfOpen ↗
- გენ-გეგმა DWG.dwg
- ფასადები - 17.02..pdfOpen ↗
- გლდანი 18.02..pla
- გენ-გეგმა - 20.05.2025.pdfOpen ↗
- გენ-გეგმა - 20.05.2025.dwg
- გენ-გეგმა - 20.05.2025.pdfOpen ↗
- გენ-გეგმა - 20.05.2025.dwg
- ჭრილები - 19.05.2025.pdfOpen ↗
- ფასადები - 19.05.2025.pdfOpen ↗
- ვიზუალიზაცია 20.05.2025.pdfOpen ↗
- შეშელიძე 20.05.2025.pla
- ჭრილები - 05.06.2025.pdfOpen ↗
- ფასადები - 05.06.25.pdfOpen ↗
- შეშელიძე 05.06.25.pla
- გაერთიანებული გეგმები - 06.06.2025.pdfOpen ↗
- გენ-გეგმა 20.06.2025.pdfOpen ↗
- გენ-გეგმა - 20.06.2025.dwg
- გაერთიანებული გეგმები - 23.06.25.pdfOpen ↗
- გლდანი.შეშელიძე 23.06.25.pla
- გლდანი.შეშელიძე 24.06.25.pla
- გაერთიანებული გეგმები - 25.06.pdfOpen ↗
- გაერთიანებული გეგმები - 04.07.2025.pdfOpen ↗
- ჭრილები 04.07.2025.pdfOpen ↗
- ფასადები - 04.07.2025.pdfOpen ↗
- გენ-გეგმა 04.07.2025.pdfOpen ↗
- გენ-გეგმა - 04.07.2025.dwg
- გლდანი.ასატვირთი04.07.pla
- გაერთიანებული გეგმები - 04.07.25.pdfOpen ↗
- გლდანი.04.07.2025.pla
- ჭრილები 04.07.25.pdfOpen ↗
- გენ-გეგმა 04.07.25.pdfOpen ↗
- ფასადები 04.07.25.pdfOpen ↗
- გლდანი.შეშელიძე 4.07.25.dwg
- გენ-გეგმა 09.07.25.pdfOpen ↗
- გლდანი.შეშელიძე 09.07.25.dwg
- ჭრილები 09.07.25.pdfOpen ↗
- ფასადები 09.07.25.pdfOpen ↗
- გლდანი.შეშელიძე 09.07.25.pla
- გაერთიანებული გეგმები - 09.07.25.pdfOpen ↗
- გენ-გეგმა 11.07.25.pdfOpen ↗
- გლდანი.შეშელიძე 09.07.25.dwg
- გლდანი.შეშელიძე 14.07.25.pla
- გლდანი.შეშელიძე. გენ.გეგმა 14.07.2025.dwg
- გენ-გეგმა 14.07.25.pdfOpen ↗
- არსებული სიტუაციის ამსახველი ფოტომასალა 07.10.2025.pdfOpen ↗
- გაერთიანებული გეგმები - 14.07.25.pdfOpen ↗
- გენ-გეგმა 04.08.2025.pdfOpen ↗
- გენ-გეგმა 04.08.2025.dwg
- ჭრილები 4.08.25.pdfOpen ↗
- ფასადები 04.08.25.pdfOpen ↗
- შეშელიძე 04.08.pla
- შეშელიძე 04.08.25.pla
- გეგმები - 04.08.25.pdfOpen ↗
- ჭრილები 6.08.25 1.pdfOpen ↗
- ფასადები 06.08.25.pdfOpen ↗
- გენ-გეგმა 06.08.2025.pdfOpen ↗
- შეშელიძე 06.08.2025.dwg
- გაერთიანებული გეგმები 6.08.25 02.pdfOpen ↗
- შეშელიძე.06.08.pla
- შეშელიძე 08.08.2025.pla
- გენ-გეგმა 08.08.2025.pdfOpen ↗
- შეშელიძე 08.08.2025.dwg
- გაერთიანებული გეგმები 10.08.25.pdfOpen ↗
- ფასადები 11.08.25.pdfOpen ↗
- გლდანი 11.08.25 ასატვირთი.pla
- ჭრილები 11.08.25.pdfOpen ↗
- გენ-გეგმა 10.09.2025.pdfOpen ↗
- გენ-გეგმა - 10.09.2025.dwg
- შეშელიძე ასატვირთი 09.09.2025.pla
- გაერთიანებული გეგმები - 10.09.25.pdfOpen ↗
- ჭრილები 10.09.25.pdfOpen ↗
- ფასადები - 10.09.pdfOpen ↗
- გენ-გეგმა 15.09.2025.pdfOpen ↗
- გენ-გეგმა - 15.09.2025.dwg
- გაერთიანებული გეგმები - 15.09.25.pdfOpen ↗
- ჭრილები 15.09.25.pdfOpen ↗
- ფასადები - 15.09.pdfOpen ↗
- შეშელიძე ასატვირთი 16.09.2025.pla
- ჭრილები 26.09.25.pdfOpen ↗
- ჭრილები 01.10.2025.pdfOpen ↗
- გაერთიანებული გეგმები - 01.10.2025.pdfOpen ↗
- ფასადები -01.10.2025.pdfOpen ↗
- შეშელიძე 01.10.2025 ასატვირთი.pla
- ფასადები -01.10.2025..pdfOpen ↗
- გაერთიანებული გეგმები - 03.10.2025.pdfOpen ↗
- ჭრილები 03.10.2025.pdfOpen ↗
- გაერთიანებული გეგმები - 03.10.2025.pdfOpen ↗
- გაერთიანებული გეგმები - 03.10.2025.pdfOpen ↗
- შეშელიძე 08.10.25 ასატვირთი.pla
- გლდანი 08.10.25 ასატვირთი.pla
- გლდანი 08.10.25 ასატვირთი ფაილი.pla
- გაერთიანებული გეგმები - 08.10.pdfOpen ↗
- შეშელიძე m 08.10.pla
- გაერთიანებული გეგმები - 08.10 მ.pdfOpen ↗
- გენ-გეგმა 09.10.2025.pdfOpen ↗
- გენ-გეგმა - 09.10.2025.dwg
- შეშელიძე m 10.10.25.pla
- გაერთიანებული გეგმები - 10.10.25.pdfOpen ↗
Reports and surveys10
Other files96
- შეთანხმებული ფოტომონტაჟი.pdfOpen ↗
- ბანერი.pdfOpen ↗
- კონტრუქცია 20.01.pdfOpen ↗
- ფოტოები.pdfOpen ↗
- სატრანსპორტო + ხაზოვანები.pdfOpen ↗
- 1.jpgOpen ↗
Show all (96)Show less
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 4.jpgOpen ↗
- სიმაღლის სქემა.pdfOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები.pdfOpen ↗
- მშენებლობის ორგანიზების პროექტი.pdfOpen ↗
- 41 ექსპერტიზა; 01.11.04.026.046 - 28.01.2025.pdfOpen ↗
- საყრდენი კედელი 1.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები.pdfOpen ↗
- საყრდენი კედელი - 17.02.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა - 17.02.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 17.02.pdfOpen ↗
- არსებული ფოტოები - 17.02.pdfOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები.pdfOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 4.jpgOpen ↗
- ფოტომონტაჟი და აქსონომეტრია.pdfOpen ↗
- გრუნტის ცვლილება 20.05.2025.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა - 19.05.2025.pdfOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 3.jpgOpen ↗
- 4.jpgOpen ↗
- გრუნტის ცვლილება 20.06.2025-compressed.pdfOpen ↗
- გრუნტის ცვლილება 23.06.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 23.06.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 23.06.pdfOpen ↗
- გრუნტის ცვლილება 23.06.pdfOpen ↗
- გამწვანების პროექტი 04.07.2025_compressed.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილების სქემა04.07.2025.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილების სქემა04.07.2025.pdfOpen ↗
- ფოტომონტაჟი 04.07.2025.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილების სქემა04.07.2025.pdfOpen ↗
- არსებული ფოტოები 09.07.25.pdfOpen ↗
- სიმაღლის სქემა - 04.07.pdfOpen ↗
- არსებული ფოტოები -.pdfOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები.pdfOpen ↗
- სიმაღლის სქემა - 09.07.pdfOpen ↗
- გამწვანების პროექტი 09.07.2025.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილების სქემა 09.07.2025 1 (2).pdfOpen ↗
- ექსპერტიზა გლდანი 01.11.04.026.046 - 11.07.2025.pdfOpen ↗
- საყრდენი კედელი - 11.07.25.pdfOpen ↗
- არსებული ფოტოები 07.10.2025.pdfOpen ↗
- 322-2025.pdfOpen ↗
- ექსპერტიზა გლდანი - 04.08.2025.pdfOpen ↗
- b.jpgOpen ↗
- c.jpgOpen ↗
- d.jpgOpen ↗
- 5.jpgOpen ↗
- გაერთიანებული ლიფტები 4.08.25.pdfOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები 04.08.pdfOpen ↗
- სიმაღლის სქემა 04.08.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 04.08.25.pdfOpen ↗
- განმარტება ფუნქციურ გადანაწილებაზე და კ2 ათვისებაზე.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 06.08..pdfOpen ↗
- სიმაღლის სქემა 04.08.pdfOpen ↗
- 1.jpgOpen ↗
- 3-.jpgOpen ↗
- 4.jpgOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები 11.08.pdfOpen ↗
- გრუნტის ცვლილება 11.09.2025.pdfOpen ↗
- საყრდენი კედელი - 10.09.2025.pdfOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები 11.09.pdfOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 4.jpgOpen ↗
- 1.jpgOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 10.09.2025.pdfOpen ↗
- განმარტება ფუნქციურ გადანაწილებაზე და კ2 ათვისებაზე.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა - 10.09.2025.pdfOpen ↗
- 41 ექსპერტიზა გლდანი - 11.09.2025.pdfOpen ↗
- 41 ექსპერტიზა გლდანი - 11.09.2025.pdfOpen ↗
- გრუნტის ცვლილება 16.09.2025.pdfOpen ↗
- საყრდენი კედელი - 16.09.2025.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა - 15.09.2025.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 10.09.2025.pdfOpen ↗
- 1.jpgOpen ↗
- 3.jpgOpen ↗
- 5.jpgOpen ↗
- 4.jpgOpen ↗
- ფოტომონტაჟი და აქსონომეტრიული ხედები 16.09.25.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 22.09.2025.pdfOpen ↗
- საყრდენი კედელი - 22.09.2025.pdfOpen ↗
- მშენ. ორგანიზების პროექტი და ეტაპები - 22.09.2025_compressed.pdfOpen ↗
- გრაფიკი, ეტაპები და ქვითრები- 24.09.2025.pdfOpen ↗
- კორექტირებული ექსპერტიზა - 03.10.2025.pdfOpen ↗
- სიმაღლის განსაზღვრის სქემა - 09.10.2025.pdfOpen ↗
- გრუნტის ცვლილების სქემა 10.10.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal