ქალაქი თბილისი, მარატ ნოზაძის ქუჩა, N 9

AR11072251Change to approved projectOther use21 March 2025- Mukhiani
Total floor area
5,927 m²
Building footprint
756.6 m²
Plot area
1,100 m²
Height
27 m
Depth below ground
3 m
Building volume
4,180 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7592580
Decision date
14 August 2025
Outcome
Granted
Construction period
14 August 2025 – 14 August 2027
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
მარიამ ეფრემიძე
Developer (company ID)
406131289

People

  • Client
    Name
    სამეჰ კამალ ჰანნა ავდალლჰ
    Personal number
    *********92
    Organization
    შპს "ლოფთ დეველოპმენტი"
    Company code
    406131289
  • Chief architect
    Name
    მარიამ ეფრემიძე
    Personal number
    *********96
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    ალექსანდრე ყურაშვილი
  • Specialist
    Name
    ბელა გოგოლაური
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ბელა გოგოლაური
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გიორგი თოფირძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    ალექსანდრე ყურაშვილი
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    თინათინ ცხაკაია

The people the applicant named in the application form.

Parcel

Cadastral code
01.11.13.001.093
Owner
შპს მინამარკ.პიტერ (400146882)
Area
1,100 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 3 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11072251
Status
Approved
Registered
21 March 2025
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
1 day
from the last re-submission to the decision
Rounds of remarks
10

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 14 August 2025City answer

    1. შეთანხმდეს: ქ. თბილისში, მუხიანის საცხოვრებელი რაიონი , შ.პ.ს "დარიალი"-ს მიმდებარედ, (ნაკვეთი N1/29), კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (საკადასტრო კოდი N 01.11.13.001.093), მრავალფუნქციური შენობის კორექტირებული არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად <span style="font-size:11.0pt; font-family:"Sylfaen",serif;mso-bidi-font-family:Sylfaen;color:bla

    Show more
  2. 14 August 2025Decision7592580 - Granted
  3. 13 August 2025City answer
  4. 13 August 2025Files uploaded
  5. 13 August 2025Files uploaded
  6. 6 August 2025City answer
  7. 6 August 2025Files uploaded
  8. 30 July 2025City answer
  9. 30 July 2025Files uploaded
  10. 21 July 2025City answer
  11. 21 July 2025Files uploaded
  12. 21 July 2025Files uploaded
  13. 2 July 2025City answer
  14. 2 July 2025Files uploaded
  15. 1 July 2025Files uploaded
  16. 1 July 2025Files uploaded
  17. 24 June 2025City answer
  18. 24 June 2025Files uploaded
  19. 24 June 2025Files uploaded
  20. 24 June 2025Files uploaded
  21. 9 June 2025City answer
  22. 2 June 2025Files uploaded
  23. 14 May 2025City answer
  24. 14 May 2025Files uploaded
  25. 14 May 2025Files uploaded
  26. 14 May 2025Files uploaded
  27. 14 May 2025Files uploaded
  28. 21 March 2025Files uploaded
  29. 21 March 2025Files uploaded
  30. 21 March 2025Files uploaded
  31. 16 January 2025Deadline extendedby 15 days, new deadline: 21 March 2025
  32. 15 January 2025City answer
  33. 30 December 2024Files uploaded
  34. 30 December 2024Files uploaded
  35. 30 December 2024Files uploaded

Some older entries, and the rest of very long texts, are not shown here.

Documents

Drawings and project files23

  • გეგმები 21.03.2025.pdfOpen ↗
  • ჭრილები 21.03.2025.pdfOpen ↗
  • ფასადები 21.03.2025.pdfOpen ↗
  • gldani_koreqtireba.pla
  • გენგეგმა 21.03.2025.pdfOpen ↗
  • გენგეგმა 21.03.2025.dwg
Show all (23)
  • ჭრილები 14.05.2025.pdfOpen ↗
  • gldani_koreqtireba.pla
  • ფასადები 14.05.2025.pdfOpen ↗
  • გეგმები 14.05.2025.pdfOpen ↗
  • gldani_koreqtireba 41.pln 27.pla
  • გეგმები 24.06.2025.pdfOpen ↗
  • ჭრილები 24.06.2025.pdfOpen ↗
  • ფასადები 24.06.2025.pdfOpen ↗
  • გეგმები 01.07.2025.pdfOpen ↗
  • ფასადები 01.07.2025.pdfOpen ↗
  • gldani_koreqtireba 41-30,06.pla
  • ფასადები 21.07.2025.pdfOpen ↗
  • Gldani_koreqtireba 41-21.07.2025.pla
  • ფასადები 29.07.2025.pdfOpen ↗
  • გლდანი-ვექტორული 29.07.2025.pla
  • გლდანი-ვექტორული-31.07.pla
  • გლდანი-ვექტორული-12.08.pla

Consents and orders1

  • თანამესაკუთრეების თანხმობა.pdfOpen ↗

Reports and surveys4

  • მომიჯნავეების დასკვნა.pdfOpen ↗
  • გეოლოგიის შეფასება.pdfOpen ↗
  • კონსტრუქცია.pdfOpen ↗
  • 41-კორექტირებული დასკვნა.pdfOpen ↗

Other files41

  • ფოტოები 29.12.2024.pdfOpen ↗
  • კალენდარული 30.12.2024.pdfOpen ↗
  • დამატებითი ფაილი 30.12.2024.rarOpen ↗
  • სიმაღლის განმსაზღვრელი სქემა 21.03.2025.pdfOpen ↗
  • შეთანხმებული აქსონომეტრიული ხედები.pdfOpen ↗
  • აქსონომეტრიული ხედები 21.03.2025.pdfOpen ↗
Show all (41)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal