ქალაქი თბილისი , ბეშენოვას ქუჩა N9 / ლიპტოვის ქუჩა N8; ქალაქი თბილისი , ბეშენოვას ქუჩა N30
- Total floor area
- 22,469.9 m²
- Building footprint
- 24,770.9 m²
- Plot area
- 19,257 m²
- Height
- 26.6 m
- Depth below ground
- 4 m
- Building volume
- 74,819 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 7465473
- Decision date
- 1 May 2025
- Outcome
- Granted
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ელგუჯა პატაშური
- Developer (company ID)
- 404906722
People
- Client
- Name
- რუსუდან გიორგაძე
- Personal number
- *********23
- Organization
- შპს ჯინო პარკი
- Company code
- 404906722
- Chief architect
- Name
- მაცაცო ჯინჭარაშვილი
- Personal number
- *********00
- Organization
- შ.პ.ს "line georgia"
- Company code
- 406030593
- Co-authors
- Name
- შავლეგო მაღრაძე, გურამ სიჭინავა
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- დავით გვასალია
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- გიორგი გურგენიძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.12.21.001.634
- Owner
- შპს "ჯინო პარკი" (404906722)
- Area
- 19,257 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 10 October 2026
Plots and zoning
- 01.12.21.001.634Registry extract ↗ (opens in a new tab)
- Zone
- Recreational
- Sub-zone
- rz-2
- K1
- 0.2
- K2
- 0
- K3
- 0
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR11080805
- Status
- Approved
- Registered
- 28 March 2025
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Length of the case
- 1 day
- from the last re-submission to the decision
- Rounds of remarks
- 9
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 1 May 2025City answer
შეთანხმდეს: ქ. თბილისში, ბეშენოვას ქუჩა N9/ლიპტოვის ქუჩა N8; ქალაქი თბილისი, ბეშენოვას ქუჩა N30-ში, კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (საკადასტრო კოდი N 01.12.21.001.634), სასტუმროს არქიტექტურული პროექტი.
Show moreShow less
- 1 May 2025Decision7465473 - Granted
- 30 April 2025City answer
- 30 April 2025Files uploaded
- 29 April 2025City answer
- 29 April 2025Files uploaded
- 25 April 2025City answer
- 25 April 2025Files uploaded
- 25 April 2025City answer
- 25 April 2025Files uploaded
- 24 April 2025Files uploaded
- 18 April 2025City answer
- 18 April 2025Files uploaded
- 18 April 2025Files uploaded
- 16 April 2025City answer
- 16 April 2025Files uploaded
- 15 April 2025Files uploaded
- 15 April 2025Files uploaded
- 15 April 2025Files uploaded
- 11 April 2025City answer
- 11 April 2025Files uploaded
- 11 April 2025Files uploaded
- 11 April 2025Files uploaded
- 11 April 2025Files uploaded
- 11 April 2025Files uploaded
- 11 April 2025Files uploaded
- 28 March 2025Files uploaded
- 27 March 2025Files uploaded
- 27 March 2025Files uploaded
- 27 March 2025Files uploaded
- 27 March 2025Files uploaded
- 27 March 2025Files uploaded
- 13 March 2025City answer
- 10 March 2025Files uploaded
- 10 March 2025Files uploaded
- 10 March 2025Files uploaded
- 10 March 2025Files uploaded
- 10 March 2025Files uploaded
- 10 March 2025Files uploaded
Documents
Drawings and project files28
- ჭრილები.pdfOpen ↗
- გენგეგმა.dwg
- ფასადები.pdfOpen ↗
- სასტუმრო_მე-4 სექტორი.pla
- გეგმები 41 მისაწვდომობა.pdfOpen ↗
- გენგეგმა 2.dwg
Show all (28)Show less
- ჭრილები 2.pdfOpen ↗
- ფასადები 2.pdfOpen ↗
- გეგმები 41 მისაწვდომობა 2.pdfOpen ↗
- სასტუმრო_მე-4 სექტორი 2.pla
- ფასადები 22.pdfOpen ↗
- გენგეგმა 3.pdfOpen ↗
- გენგეგმა 3.dwg
- ჭრილები 3.pdfOpen ↗
- ფასადები 3.pdfOpen ↗
- სასტუმრო_მე-4 სექტორი 3.pla
- გეგმები 41 მისაწვდომობა 3.pdfOpen ↗
- გეგმები 41 მისაწვდომობა 33.pdfOpen ↗
- გენგეგმა 4.pdfOpen ↗
- ჭრილები 4.pdfOpen ↗
- ფასადები 4.pdfOpen ↗
- გენგეგმა 4.dwg
- გეგმები 41 მისაწვდომობა 4.pdfOpen ↗
- გეგმები 41 მისაწვდომობა 44.pdfOpen ↗
- სასტუმრო_მე-4 სექტორი 4.pla
- გეგმები 41 მისაწვდომობა 5.pdfOpen ↗
- გენგეგმა 5.pdfOpen ↗
- გენგეგმა 5.dwg
Reports and surveys9
Other files29
- არსებული ფოტოები.pdfOpen ↗
- ფოტომონტაჟი.pdfOpen ↗
- Scene 80.jpgOpen ↗
- Scene 81.jpgOpen ↗
- Scene 83.jpgOpen ↗
- Scene 85.jpgOpen ↗
Show all (29)Show less
- Scene 86.jpgOpen ↗
- ჯინო სასტუმრო IV სექტორი A.pdfOpen ↗
- ექსპერტიზა A.pdfOpen ↗
- სატრანსპორტო კვლევა ჯინო.pdfOpen ↗
- სიმაღლის სქემა.pdfOpen ↗
- ზეგავლენა მომიჯნავეებზე.pdfOpen ↗
- ექსპერტიზა A-2.pdfOpen ↗
- 4 სექტორი გამწვანება.pdfOpen ↗
- ფოტომონტაჟი 2.pdfOpen ↗
- ტაქსაცია+გამწვანება 3.pdfOpen ↗
- Scene 80 -3.jpgOpen ↗
- Scene 81 -3.jpgOpen ↗
- Scene 83 -3.jpgOpen ↗
- Scene 85 -3.jpgOpen ↗
- Scene 86 -3.jpgOpen ↗
- ფოტომონტაჟი 3.pdfOpen ↗
- ტაქსაცია+გამწვანება 33.pdfOpen ↗
- ექსპერტიზა A-4.pdfOpen ↗
- ექსპერტიზა A-5.pdfOpen ↗
- ტაქსაცია+დენდროლოგია 4.pdfOpen ↗
- IV სექტორი გამწვანება+ტაქსაცია.pdfOpen ↗
- ახალი გამწვანება.pdfOpen ↗
- ახალი გამწვანება 4.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal