OpenCAD
Approved

ქალაქი თბილისი, გივი ჟვანიას ქუჩა, N 2

AR11087197Change to approved projectOther use17 April 2025
Total floor area
3,931.7 m²
Building footprint
4,502.7 m²
Plot area
3,102 m²
Height
29.4 m
Depth below ground
12 m
Building volume
17,452.8 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7624654
Decision date
12 September 2025
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
მაია გოთუა
Developer (company ID)
204929140

People

  • Client
    Name
    მაია გოთუა
    Personal number
    *********76
    Organization
    შპს ალერგიისა და იმუნოლოგიის ცენტრი
    Company code
    204929140
  • Chief architect
    Name
    პაატა ქურდიანი
    Personal number
    *********18
    Organization
    შ.პ.ს. "პროექტი"
    Company code
    202338504
  • Co-authors
    Name
    ქეთევან ქურდიანი, ერიკ კისელიოვი
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ქეთევან კალანდაძე
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გ. სადრაძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    გიორგი რეხვიაშვილი
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    ქართლოს მაისურაძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.13.01.008.068
Owner
შპს "ალერგიისა და იმუნოლოგიის ცენტრი" (204929140)
Area
3,102 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

  • Zone
    Special
    Sub-zone
    specz-1
    K1
    0
    K2
    0
    Special zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
    K3
    0

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11087197
Status
Approved
Registered
17 April 2025
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
1 day
from the last re-submission to the decision
Rounds of remarks
17

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 12 September 2025City answer

    1. შეთანხმდეს ქ. თბილისში, ქალაქი თბილისი , ლუბლიანას ქუჩა , N78-ში, არსებულ მიწის ნაკვეთზე (ს/კ: №01.13.01.008.068) პოლიკლინიკის რეკონსტრუქციის კორექტირებული არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2025 წლის 12 სექტემბრიდან 2025 წლის 25 სექტემბრის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 6) არამზიდი კონსტრუქციების მოწყობა. 7) შენობა-ნაგებობის ლოკალური საერთო სარგებლობის საინჟინრო ტექნიკური ქსელების მონტაჟი. +0,00 და +6,60 ნიშნულებზე (გარდა +3,30 და +9,90 ნიშნულებისა. 8) შენობა-ნაგებობის გარე მოსაპირკეთებელი სამუშაოები. 9) შიდა მოსაპირკეთებელი სამუშაოები +0,00 და +6,60 ნიშნულებზე (გარდა +3,30 და +9,90 ნიშნულებისა) 10) ტექნოლოგიური მოწყობილობების მონტაჟი +0,00 და +6,60 ნიშნულებზე (გარდა +3,30 და +9,90 ნიშნულებისა) 11) მიწის ნაკვეთის კეთილმოწყობის სამუშაოები. გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. საქართველოს სივრცის დაგეგმარების, არქიტექტურული და სამშენებლო საქმიანობის კოდექსის 1415 მუხლის შესაბამისად, შენობა-ნაგებობის მშენებლობისას მშენებლობის საჯარო ზედამხედველობის შესაბამისი ორგანოსთვის საეტაპო ოქმის დადგენილი წესით წარუდგენლობისთვის სამშენებლო სამართალდამრღვევს 2025 წლის 31 დეკემბრამდე არ დაეკისრება ამ კოდექსის 132-ე მუხლით გათვალისწინებული პასუხისმგებლობა. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან.

    Show more
  2. 12 September 2025Decision7624654 - Granted
  3. 11 September 2025City answer
  4. 11 September 2025Files uploaded
  5. 11 September 2025Files uploaded
  6. 11 September 2025Files uploaded
  7. 4 September 2025City answer
  8. 4 September 2025Files uploaded
  9. 4 September 2025Files uploaded
  10. 4 September 2025Files uploaded
  11. 4 September 2025Files uploaded
  12. 4 September 2025Files uploaded
  13. 30 August 2025City answer
  14. 30 August 2025Files uploaded
  15. 29 August 2025Files uploaded
  16. 27 August 2025Files uploaded
  17. 25 August 2025City answer
  18. 25 August 2025Files uploaded
  19. 25 August 2025Files uploaded
  20. 14 August 2025City answer
  21. 14 August 2025Files uploaded
  22. 14 August 2025Files uploaded
  23. 14 August 2025Files uploaded
  24. 8 August 2025City answer
  25. 8 August 2025Files uploaded
  26. 8 August 2025Files uploaded
  27. 8 August 2025Files uploaded
  28. 5 August 2025City answer
  29. 4 August 2025Files uploaded
  30. 4 August 2025Files uploaded
  31. 4 August 2025Files uploaded
  32. 4 August 2025Files uploaded
  33. 1 August 2025Files uploaded
  34. 1 August 2025Files uploaded
  35. 31 July 2025Files uploaded
  36. 30 July 2025City answer
  37. 30 July 2025Files uploaded
  38. 28 July 2025City answer
  39. 28 July 2025Files uploaded
  40. 28 July 2025Files uploaded
  41. 28 July 2025Files uploaded
  42. 28 July 2025Files uploaded
  43. 28 July 2025Files uploaded
  44. 22 July 2025City answer
  45. 22 July 2025Files uploaded
  46. 16 July 2025City answer
  47. 16 July 2025Files uploaded
  48. 15 July 2025Files uploaded
  49. 15 July 2025Files uploaded
  50. 27 June 2025Files uploaded
  51. 26 June 2025City answer
  52. 26 June 2025Files uploaded
  53. 26 June 2025Files uploaded
  54. 26 June 2025Files uploaded
  55. 24 June 2025City answer
  56. 24 June 2025Files uploaded
  57. 24 June 2025Files uploaded
  58. 24 June 2025Files uploaded
  59. 23 June 2025Files uploaded
  60. 18 June 2025City answer
  61. 18 June 2025Files uploaded
  62. 18 June 2025Files uploaded
  63. 18 June 2025Files uploaded
  64. 18 June 2025Files uploaded
  65. 16 June 2025City answer
  66. 16 June 2025Files uploaded
  67. 16 June 2025Files uploaded
  68. 16 June 2025Files uploaded
  69. 16 June 2025Files uploaded
  70. 16 June 2025Files uploaded
  71. 28 May 2025Deadline extendedby 10 days, new deadline: 17 June 2025
  72. 7 May 2025City answer
  73. 7 May 2025Files uploaded
  74. 6 May 2025Files uploaded
  75. 6 May 2025Files uploaded
  76. 6 May 2025Files uploaded
  77. 6 May 2025Files uploaded
  78. 6 May 2025Files uploaded
  79. 6 May 2025Files uploaded
  80. 6 May 2025Files uploaded
  81. 17 April 2025Files uploaded
  82. 16 April 2025Files uploaded
  83. 16 April 2025Files uploaded
  84. 16 April 2025Files uploaded
  85. 14 April 2025Files uploaded
  86. 14 April 2025Files uploaded
  87. 14 April 2025Files uploaded
  88. 14 April 2025Files uploaded
  89. 14 April 2025Files uploaded

Documents

Drawings and project files17

  • CL_7,1_sarTulebis gegmebi.pla
  • CL_7,1_Gengegma.dwg
  • CL_7,2_sarTulebis gegmebi__.pla
  • CL_7,2_sarTulebis gegmebi.pla
  • CL_7,2_Gengegma.pla
  • CL_7,2_sarTulebis gegmebi.pla
Show all (17)
  • CL_7,2_sarTulebis_gegmebi.pla
  • CL_7,2_sarTulebis gegmebi__.pla
  • CL_7,3_sarTulebis gegmebi.pla
  • CL_7,4_sarTulebis gegmebi.pla
  • CL_7,5_sarTulebis gegmebi.pla
  • CL_7,5_sarTulebis gegmebi-.pla
  • CL_7,5_sarTulebis gegmebi.pla
  • CL_7,5_sarTulebis gegmebi040925.pla
  • CL_7,5_sarTulebis gegmebi-04-09-25.pla
  • _CL_7,5_sarTulebis gegmebi.pla
  • CL_7,3_sarTulebis gegmebi.pla

Consents and orders1

  • თანხმობა სამშენებლო პროექტის კორექტირებაზე ალერგ და იმუნოლოგია 20.06.225.pdfOpen ↗

Reports and surveys14

  • geologia.pdfOpen ↗
  • საექსპერტო დასკვნა 41 - 15.04.2025-signed.pdfOpen ↗
  • საექსპერტო დასკვნა 41 - 15.04.2025-signed.pdfOpen ↗
  • საექსპერტო დასკვნა 41 - 22.06.2025-signed.pdfOpen ↗
  • საექსპერტო დასკვნა 41 - 14.07.2025-signed.pdfOpen ↗
  • CL_საექსპერტო დასკვნა 41 - 14.07.2025-signed (1).pdfOpen ↗
Show all (14)
  • დასკვნა-41-280~1.PDFOpen ↗
  • საექსპერტო დასკვნა 41 - 14.08.2025.pdfOpen ↗
  • საექსპერტო დასკვნა მისაწვდომობის სტანდარტი - 14.08.2025.pdfOpen ↗
  • CL_7,2_ 41 დასკვნა ორიგინალი.pdfOpen ↗
  • CL_7,2_ 41 დასკვნა ორიგინალი-.pdfOpen ↗
  • CL_7,2_ 41 დასკვნა ორიგინალი040925.pdfOpen ↗
  • _CL_7,2_ 41 დასკვნა ორიგინალი.pdfOpen ↗
  • CL_7,3_ 41 დასკვნა ორიგინალი.pdfOpen ↗

Other files96

Show all (96)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal