ქალაქი თბილისი , ჩიხი ქვემო გომი , N 4

AR11113509New constructionMulti-unit residential24 December 2025
Total floor area
576.2 m²
Building footprint
687 m²
Residential area
227.7 m²
Plot area
273 m²
Height
17.4 m
Depth below ground
7.7 m
Building volume
2,898 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
8061021
Decision date
26 August 2026
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
კახაბერ კახიშვილი
Developer (company ID)
404554488

People

  • Client
    Name
    დავით კარდანახიშვილი
    Personal number
    *********56
  • Chief architect
    Name
    კახაბერ კახიშვილი
    Personal number
    *********63
    Organization
    შპს "ვერკრაუმი"
    Company code
    405156842
  • Co-authors
    Name
    ლუკა გოგლიძე
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    ზურაბ გუბელიძე
  • Specialist
    Name
    მიხეილ ბუჯიაშვილი
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    მიხეილ ბუჯიაშვილი

The people the applicant named in the application form.

Parcel

Cadastral code
01.18.03.070.012
Owner
მიხეილი სეფიაშვილი (P/N: 3-1412313-4)
Area
273 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 3 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11113509
Status
Approved
Registered
24 December 2025
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
2 days
from the last re-submission to the decision
Rounds of remarks
20

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 26 August 2026City answer

    1. შეთანხმდეს ქალაქ თბილისში (სექტორი - კრწანისი), ქვემო გომის ჩიხი N4-ში არსებულ მიწის ნაკვეთზე (ს/კ 01.18.03.070.012) მრავალბინიანი საცხოვრებელი სახლის არქიტექტურული პროექტი.

    Show more
  2. 26 August 2026Decision8061021 - Granted
  3. 24 August 2026City answer
  4. 24 August 2026Files uploaded
  5. 21 August 2026City answer
  6. 21 August 2026Files uploaded
  7. 18 August 2026City answer
  8. 18 August 2026Files uploaded
  9. 11 August 2026City answer
  10. 10 August 2026Files uploaded
  11. 31 July 2026City answer
  12. 31 July 2026Files uploaded
  13. 29 July 2026City answer
  14. 29 July 2026Files uploaded
  15. 28 July 2026Files uploaded
  16. 28 July 2026Files uploaded
  17. 21 July 2026City answer
  18. 21 July 2026Files uploaded
  19. 20 July 2026Files uploaded
  20. 20 July 2026Files uploaded
  21. 20 July 2026Files uploaded
  22. 3 July 2026City answer
  23. 3 July 2026Files uploaded
  24. 3 July 2026Files uploaded
  25. 3 July 2026Files uploaded
  26. 3 July 2026Files uploaded
  27. 17 June 2026Files uploaded
  28. 10 June 2026City answer
  29. 10 June 2026Files uploaded
  30. 13 May 2026City answer
  31. 8 May 2026Files uploaded
  32. 8 May 2026Files uploaded
  33. 8 May 2026Files uploaded
  34. 29 April 2026City answer
  35. 29 April 2026Files uploaded
  36. 29 April 2026Files uploaded
  37. 29 April 2026Files uploaded
  38. 22 April 2026City answer
  39. 22 April 2026Files uploaded
  40. 22 April 2026Files uploaded
  41. 1 April 2026City answer
  42. 1 April 2026Files uploaded
  43. 1 April 2026Files uploaded
  44. 27 March 2026City answer
  45. 27 March 2026Files uploaded
  46. 26 March 2026City answer
  47. 26 March 2026Files uploaded
  48. 10 March 2026City answer
  49. 10 March 2026Files uploaded
  50. 10 March 2026Files uploaded
  51. 9 March 2026Files uploaded
  52. 4 March 2026Files uploaded
  53. 13 February 2026City answer
  54. 13 February 2026Files uploaded
  55. 13 February 2026Files uploaded
  56. 24 December 2025Files uploaded
  57. 5 December 2025City answer
  58. 4 December 2025City answer
  59. 4 December 2025Files uploaded
  60. 4 December 2025Files uploaded
  61. 17 October 2025Files uploaded
  62. 17 October 2025Files uploaded
  63. 17 October 2025Files uploaded

Documents

Drawings and project files98

  • გენ-გეგმა.pdfOpen ↗
  • გენ-გეგმა.dwg
  • გეგმები.pdfOpen ↗
  • ჭრილები.pdfOpen ↗
  • ფასადები.pdfOpen ↗
  • BTR_25-10-17.pla
Show all (98)
  • გენ. გეგმა_02.pdfOpen ↗
  • გეგმები_02.pdfOpen ↗
  • ჭრილები_02.pdfOpen ↗
  • BTR_25-11-20.pla
  • ფასადები_02.pdfOpen ↗
  • გეგმები_03.pdfOpen ↗
  • ჭრილები_03.pdfOpen ↗
  • ფასადები_03.pdfOpen ↗
  • BTR_25-12-23.pla
  • გენ-გეგმა_04.pdfOpen ↗
  • გენ-გეგმა 04.dwg
  • გეგმები_04.pdfOpen ↗
  • ჭრილები_04.pdfOpen ↗
  • ფასადები_04.pdfOpen ↗
  • გენ. გეგმა_05.pdfOpen ↗
  • გენ. გეგმა_05.dwg
  • გეგმები_05.pdfOpen ↗
  • ჭრილები_05.pdfOpen ↗
  • ფასადები_05.pdfOpen ↗
  • BTR_26-03-09.pla
  • გენ. გეგმა_06.pdfOpen ↗
  • გენ. გეგმა_06.dwg
  • გეგმები_06.pdfOpen ↗
  • ფასადები_06.pdfOpen ↗
  • BTR_26-03-26.pla
  • ჭრილები_06.pdfOpen ↗
  • გენ. გეგმა_07.pdfOpen ↗
  • გენ. გეგმა_07.dwg
  • გეგმები_07.pdfOpen ↗
  • ჭრილები_07.pdfOpen ↗
  • ფასადები_07.pdfOpen ↗
  • BTR_2026-03-27 archive.pla
  • გენ. გეგმა_08.pdfOpen ↗
  • გენ. გეგმა_08.dwg
  • ჭრილები_08.pdfOpen ↗
  • ფასადები_08.pdfOpen ↗
  • BTR_26-04-01.pla
  • გეგმები_08.pdfOpen ↗
  • გენ. გეგმა_09.pdfOpen ↗
  • გენ. გეგმა_09.dwg
  • გეგმები_09.pdfOpen ↗
  • ჭრილები_09.pdfOpen ↗
  • ფასადები_09.pdfOpen ↗
  • BTR_26-04-22.pla
  • გეგმები_10.pdfOpen ↗
  • ჭრილები_10.pdfOpen ↗
  • ფასადები_10.pdfOpen ↗
  • BTR_2026-04-29.pla
  • გენ. გეგმა_10.pdfOpen ↗
  • გენ. გეგმა_10.dwg
  • გეგმები_10.pdfOpen ↗
  • გეგმები_11.pdfOpen ↗
  • ჭრილები_11.pdfOpen ↗
  • ფასადები_11.pdfOpen ↗
  • გენ. გეგმა_11.pdfOpen ↗
  • გენ. გეგმა_11.dwg
  • BTR_2026-05-04.pla
  • BTR_26-06-09.pla
  • გეგმები_12.pdfOpen ↗
  • ჭრილები_12.pdfOpen ↗
  • ფასადები_12.pdfOpen ↗
  • გეგმები_13.pdfOpen ↗
  • ჭრილები_13.pdfOpen ↗
  • ფასადები_13.pdfOpen ↗
  • BTR_2026-06-16.pla
  • გეგმები-14.pdfOpen ↗
  • ფასადები-14.pdfOpen ↗
  • BTR_2026-07-03.pla
  • ფასადები-15.pdfOpen ↗
  • ჭრილები-15.pdfOpen ↗
  • გენ. გეგმა-15.pdfOpen ↗
  • გენ. გეგმა-15.dwg
  • გეგმები-15.pdfOpen ↗
  • გეგმები-15.pdfOpen ↗
  • BTR_2026-07-20.pla
  • ფასადები-16.pdfOpen ↗
  • გენ. გეგმა-16.pdfOpen ↗
  • გეგმები-16.pdfOpen ↗
  • ფასადები-16.pdfOpen ↗
  • BTR_2026-07-28.pla
  • გეგმები-17.pdfOpen ↗
  • ფასადები17.pdfOpen ↗
  • BTR_2026-07-31.pla
  • გეგმები-18.pdfOpen ↗
  • ფასადები-18.pdfOpen ↗
  • BTR_2026-08-10.pla
  • გეგმები-19.pdfOpen ↗
  • BTR_2026-08-18.pla
  • გეგმები-20.pdfOpen ↗
  • BTR_2026-08-21.pla
  • გეგმები_21.pdfOpen ↗
  • BTR_2026-08-24.pla

Reports and surveys5

  • კონსტრუქციის ექსპერტიზა.pdfOpen ↗
  • _41 დასკვნა და მისაწვდომობა_ბეთლმი.pdfOpen ↗
  • კონსტრუქციების ექსპერტიზა.pdfOpen ↗
  • გეოლოგია, კონსტრუქცია.rarOpen ↗
  • _41 დასკვნა და მისაწვდომობა_ბეთელმი (03).pdfOpen ↗

Other files83

Show all (83)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal