ქალაქი თბილისი , დასახლება ვარკეთილი , მასივი III , კვარტალი VI , კორპუსი 12 , მიმდებარედ (ნაკვეთი 31/015); ქალაქი თბილისი , გზატკეცილი კახეთი , N 66
AR11163033New constructionMulti-unit residential12 October 2026- Varketili
- Total floor area
- 31,231.6 m²
- Building footprint
- 36,469.9 m²
- Residential area
- 17,319.9 m²
- Plot area
- 5,429 m²
- Height
- 68.9 m
- Depth below ground
- 3.6 m
- Building volume
- 121,427.1 m³
Figures as the applicant entered them in the form; not verified.
Applicant
- Name
- სოფიკო აბესაძე
- Organization
- 11250
- Developer (company ID)
- 405412361
People
- Client
- Name
- გიორგი მეტრეველი
- Personal number
- *********12
- Organization
- შპს სფერა
- Company code
- 405412361
- Chief architect
- Name
- დოდო ჩუბინიძე
- Personal number
- *********63
- Organization
- შპს ''ვაით სტუდიო''
- Company code
- 404934372
- Co-authors
- Name
- სოფიკო აბესაძე
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- მამუკა ბარათაშვილი
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.19.20.031.015
- Owner
- ქალაქ თბილისის თვითმმართველი ერთეული
- Area
- 1,426 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 1 October 2026
Plots and zoning
- 01.19.20.031.015Registry extract ↗ (opens in a new tab)
- Zone
- Recreational
- Sub-zone
- rz-1
- K1
- 0
- K2
- 0
- K3
- 0
- 01.19.20.031.009Registry extract ↗ (opens in a new tab)
- Zone
- Commercial / business
- Sub-zone
- ssz-2
- K1
- 0.7
- K2
- 4.6
- K3
- 0.1
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR11163033
- Status
- Interim decision
- Registered
- 12 October 2026
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Open since
- 12 October 2026
- Waiting on
- the applicant
- Rounds of remarks
- 0
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 12 October 2026Files uploaded
- 12 October 2026Files uploaded
- 2 October 2026Files uploaded
- 1 October 2026Files uploaded
- 1 October 2026Files uploaded
- 30 September 2026Files uploaded
- 30 September 2026Files uploaded
- 30 September 2026Files uploaded
- 29 September 2026Files uploaded
- 29 September 2026Files uploaded
- 29 September 2026Files uploaded
- 29 September 2026Files uploaded
Documents
Drawings and project files5
- varketili gen.gegma.dwg
- varketili proekti 30.09.26.pla
- varketili Proekti 30.09.26.pla
- varketili gen.gegma.pla
- varketili 3D 30.09.2026.pdfOpen ↗
Other files12
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.