ქალაქი თბილისი, დავით აღმაშენებლის ხეივანი, N 200

AR11163387New constructionMulti-unit residential1 October 2026- Dighomi
Total floor area
57,816.6 m²
Building footprint
66,663.5 m²
Residential area
33,618.6 m²
Plot area
29,641 m²
Height
125.5 m
Depth below ground
8.3 m
Building volume
224,389 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Applicant

Name
აკაკი ჩხაიძე
Developer (company ID)
405578520

People

  • Client
    Name
    თემურ გიგნიძე
    Personal number
    *********13
    Organization
    შპს "ქეფითალ სითი გრუფ ინვესტი"
    Company code
    405578520
  • Chief architect
    Name
    მამუკა ჩხაიძე
    Personal number
    *********32
    Organization
    შპს"სტუდია9"
    Company code
    404429515
  • Co-authors
    Name
    ლაშა ღვინიანიძე
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    გაიოზი ჭანკვეტაძე
  • Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ბორის დგებუაძე
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    ნინა არეშიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    გაიოზ ჭანკვეტაძე
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    სპარტაკ მელიქიშვილი

The people the applicant named in the application form.

Parcel

Cadastral code
01.10.06.005.014
Owner
შპს "ქეფითალ სითი გრუფ ინვესთ" (405578520)
Area
29,641 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 21 November 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR11163387
Status
Interim decision
Registered
1 October 2026
Type
New construction

Source: TAS, the city's permit system - read from TAS 21 November 2026

Case progress

Waiting on
the applicant
since 18 November 2026 (5 days)
Rounds of remarks
2

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 20 November 2026Files uploaded
  2. 20 November 2026Files uploaded
  3. 20 November 2026Files uploaded
  4. 20 November 2026Files uploaded
  5. 18 November 2026City answer

    ქ. თბილისის მუნიციპალიტეტის სსიპ – ქ. თბილისის მუნიციპალიტეტის არქიტექტურის სამსახურმა განიხილა თქვენ მიერ ელექტრონულად ატვირთული განცხადება და მასზე თანდართული დოკუმენტაცია, პასუხად გაცნობებთ შემდეგს: 1..ტექნიკურ - ეკონომიკური მაჩვენებლები (მეათედების სიზუსტით) გადამოწმდება დოკუმენტაციის განახლების შემდეგ. 2..შენობა-ნაგებობის ყველა სართულისა და სახურავის გეგმები, მასშტაბი 1:100. -> .გეგმების pdf ფაილი.: - ვინაიდან საპროექტო ბლოკისთვის აუცილებელი ავტოსადგომების რაოდენობა გათვალისწინებულია ა2 ბლოკში, საჭიროა პარალელურად დაკორექტირდეს აღნშნული ბლოკის პროექტი და აისახოს ბ ბლოკისთვის აუცილებელი ავტოსადგომებიც - გეგმებზე დაიტანეთ „ა“ და „ბ“ ტიპის ბინები. 3..შენობა-ნაგებობის მაქსიმალური სიმაღლის განსაზღვრის სქემა. -> .სიმაღლის განმსაზღვრელი სქემის pdf ფაილი.: საჭიროა დაიცვათ გრგ-თი დადგენილი მაქსიმალური სიმაღლე 120მ. 4..საპროექტო შენობა-ნაგებობის ვექტორული CAD ფაილი. -> .საპროექტო შენობა-ნაგებობის ვექტორული ფაილი AutoCad - ის ან ArchiCad - ის სახით. : სრულყოფილად წარმოადგინეთ ფუნქციური გადანაწილების კროკები B1, B2 და B3 ბლოკებისთვის. პროცენტულობა იანგარიშეთ საერთო ფართით. კ2-ის ანგარიში მოიყვანეთ ურთიერთშესაბამისობაში. განაახლეთ დადგენილი ხარვეზების შესაბამისად. 5.. არქიტექტურულ და კონსტრუქციულ ნაწილში არ არის შესაბამისობაში მონოლითური კედლები და სახურავის გეგმები (კიბის უჯრედის ნაწილში). მომიჯნავე შენობა-ნაგებობებზე ზეგავლენის კვლევაში შესწორდეს საპროექტო შენობების სართულიანობა. წარმოსადგენია კონსტრუქციული პროექტის საექსპერტო შეფასება. 6. გაცნობებთ, რომ სამსახურმა საკითხი შესასწავლად გადაგზავნა გარემოს დაცვის საქალაქო სამსახურში წერილის ნომერი 60-01263223048 საქმის წარმოების დასრულების შემდეგ პასუხს მიიღებთ შეტყობინების ველში. 7. მშენებლობის ორგანიზების კალენდარული გრაფიკი. -> .მშენებლობის ორგანიზების კალენდარული გრაფიკის pdf ფაილი.: შენობის ფუნქცია შეუსაბამეთ საპროექტო დოკუმენტაციას. 8.."მშენებლობის ნებართვის მოსაკრებელი -> .მოსაკრებელის რიცხვითი მაჩვენებელი: გადახდილ იქნას მშენებლობის ნებართვის მოსაკრებელი, საპროექტო კ-2 კოეფიციენტის საანგარიშო ფართის შესაბამისად 1 კვ.მ-ზე 10 ლარის ოდენობით. არასრულყოფილი დოკუმენტაციის გამო სამსახური ამ ეტაპზე ვერ გიდგენთ ყველა შესაძლო ხარვეზს. გაითვალისწინეთ, რომ თქვენ გეძლევათ 15 დღიანი ვადა მითითებული ხარვეზის გამოსასწორებლად, თუ დადგენილ ვადაში განმცხადებელი არ წარმოადგენს შესაბამის დოკუმენტაციას, განცხადება დარჩება განუხილველი.

    Show more
  6. 17 November 2026Status changedInterim decision → Back for re-review
  7. 17 November 2026Files uploaded
  8. 17 November 2026Files uploaded
  9. 17 November 2026Files uploaded
  10. 17 November 2026Files uploaded
  11. 17 November 2026Files uploaded
  12. 17 November 2026Files uploaded
  13. 17 November 2026Files uploaded
  14. 17 November 2026Files uploaded
  15. 17 November 2026Files uploaded
  16. 17 November 2026Files uploaded
  17. 17 November 2026Files uploaded
  18. 17 November 2026Files uploaded
  19. 17 November 2026Files uploaded
  20. 17 November 2026Files uploaded
  21. 17 November 2026Files uploaded
  22. 17 November 2026Files uploaded
  23. 17 November 2026Files uploaded
  24. 17 November 2026Files uploaded
  25. 6 November 2026City answer
  26. 6 November 2026Files uploaded
  27. 6 November 2026Files uploaded
  28. 6 November 2026Files uploaded
  29. 6 November 2026Files uploaded
  30. 6 November 2026Files uploaded
  31. 6 November 2026Files uploaded
  32. 6 November 2026Files uploaded
  33. 6 November 2026Files uploaded
  34. 6 November 2026Files uploaded
  35. 6 November 2026Files uploaded
  36. 6 November 2026Files uploaded
  37. 6 November 2026Files uploaded
  38. 6 November 2026Files uploaded
  39. 6 November 2026Files uploaded
  40. 1 October 2026Files uploaded
  41. 1 October 2026Files uploaded
  42. 1 October 2026Files uploaded
  43. 1 October 2026Files uploaded
  44. 1 October 2026Files uploaded
  45. 1 October 2026Files uploaded
  46. 1 October 2026Files uploaded
  47. 1 October 2026Files uploaded
  48. 1 October 2026Files uploaded
  49. 1 October 2026Files uploaded
  50. 1 October 2026Files uploaded
  51. 1 October 2026Files uploaded
  52. 1 October 2026Files uploaded
  53. 30 September 2026Files uploaded
  54. 30 September 2026Files uploaded

Documents

Drawings and project files24

  • 2026.11.05_A.1.5 ფასადები.pdfOpen ↗
  • 2026.11.17_A.1.6 ჭრილები - არქიტექტურა.pdfOpen ↗
  • 2026.11.17_გეგმები.pdfOpen ↗
  • +2026.11.17.pla
  • 2026.10.01_გეგმები არქიტექტურა.pdfOpen ↗
  • 2026.11.06_ვექტორული ფაილი.pla
Show all (24)
  • 2026.10.01_გეგმები_41.pdfOpen ↗
  • 2026.11.17_გეგმები.pdfOpen ↗
  • 2026.11.06_გეგმები.pdfOpen ↗
  • 2026.11.17.pla
  • 2026.10.01_ფასადები.pdfOpen ↗
  • 2026.10.01_B1_B2_B3_გენ-გეგმა.dwg
  • 2026.10.01_გენგეგმა.pdfOpen ↗
  • 2026.10.01_ვიზუალიზაცია.pdfOpen ↗
  • 2026.11.16_A.3.3 გენ.გეგმა B1-B2.pdfOpen ↗
  • 2026.11.16_A.3.3 გენ.გეგმა B1-B2.dwg
  • 2026.11.17_A.1.5 ფასადები.pdfOpen ↗
  • 2026.11.06_გეგმები_არქიტექტურა.pdfOpen ↗
  • 2026.11.03_ჭრილები.pdfOpen ↗
  • 2026.11.17_გეგმები არქიტექტურა.pdfOpen ↗
  • 2026.10.01_ჭრილები.pdfOpen ↗
  • 2026.11.05_A.3.3 გენ.გეგმა B1-B2.pdfOpen ↗
  • 2026.11.05_A.3.3 გენ.გეგმა B1-B2 (1)_0.გენ.გეგმა B1-B2.dwg
  • 2026.10.01_B1_B2.pla

Consents and orders2

  • ურბანულის პასუხი_ზეგავლენის და ნიშნულის თანხმობა.pdfOpen ↗
  • 2026.11.06_იპოთეკარის თანხმობა.pdfOpen ↗

Reports and surveys10

  • 2026.11.17_B-1-B-2__დიდი_დიღომი_41_დასკვნა.pdfOpen ↗
  • 2026.11.06_კონსტრუქცია+ინჟინერია.rarOpen ↗
  • 2026.11.20_კონსტრუქცია+ინჟინერია.rarOpen ↗
  • 2026.11.06_B-1-B2__დიდი_დიღომი_41_დასკვნა_მისაწვდომობა.pdfOpen ↗
  • 2026.11.17_დასკვნა მომიჯნავეები B1, B2, B3 ბლოკები.pdfOpen ↗
  • საინჟინროს თანხმობები.pdfOpen ↗
Show all (10)
  • გეოლოგია_გეოფიზიკა.pdfOpen ↗
  • 2026.11.06_კონსტრუქცია+ინჟინერია.rarOpen ↗
  • 2026.11.06_კონსტრუქცია+ინჟინერია+41.rarOpen ↗
  • 2026.11.19_დასკვნა მომიჯნავეები B1, B2, B3 ბლოკები.pdfOpen ↗

Other files27

  • 1.pdfOpen ↗
  • 2026.10.01_სიმაღლის განსაზღვრის სქემა.pdfOpen ↗
  • 2026.11.06_ენერგოეფექტურობა_დიდი დიღომი B-1-B-2-signed.pdfOpen ↗
  • 2026.11.05_სიმაღლის განსაზღვრის სქემა1_შეკუმშული.pdfOpen ↗
  • 1.pdfOpen ↗
  • ფოტოფიქსაცია.pdfOpen ↗
Show all (27)
  • B1-B2_ბანერი.pdfOpen ↗
  • ბანერი_B1-B2.pdfOpen ↗
  • 1Cam_02_V2.jpgOpen ↗
  • 1Cam_04_V2 ).jpgOpen ↗
  • 1Cam_12.jpgOpen ↗
  • Cam_02 copy.jpgOpen ↗
  • Cam_04 copy.jpgOpen ↗
  • Cam_03 copy.jpgOpen ↗
  • Cam_06 copy.jpgOpen ↗
  • Cam_05 copy.jpgOpen ↗
  • 606.07.25-I606 - საექსპერტო შეფასება.pdfOpen ↗
  • 2026.11.20_A.1.8 სიმაღლის განსაზღვრის სქემა (შემცირებული).pdfOpen ↗
  • 2026.11.17_A.1.9 ფოტომონტაჟი.pdfOpen ↗
  • 2026.11.17_ბანერი_B1-B2.pdfOpen ↗
  • 2026.11.17_POS - GANMARTEBITI - AGMASHENEBLIS #200 - B1 da B2 korpusi.pdfOpen ↗
  • 2026.11.19_POS - GANMARTEBITI - AGMASHENEBLIS #200 - B1 da B2 korpusi.pdfOpen ↗
  • 2026.11.04_ფოტოფიქსაცია.pdfOpen ↗
  • სქემა.pdfOpen ↗
  • გამწვანება.pdfOpen ↗
  • ქონების მართვა გადახდის ქვითარი.pdfOpen ↗
  • 2026.11.17_სიმაღლის განსაზღვრის სქემა (2).pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal