ქალაქი თბილისი , ქუჩა შორაპნის , N 28-ა
- Total floor area
- 854.6 m²
- Building footprint
- 155.1 m²
- Residential area
- 569.5 m²
- Plot area
- 456 m²
- Height
- 22.2 m
- Depth below ground
- 2.2 m
- Building volume
- 2,733.1 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 1901405
- Decision date
- 19 May 2015
- Outcome
- Granted
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ზურაბ მელქაძე
- Developer (company ID)
- 405078124
People
- Client
- Name
- ზურაბ მელქაძე
- Personal number
- *********74
- Organization
- შპს სკაიჰაუს
- Company code
- 405078124
- Chief architect
- Name
- მშვიდობაძე კარლო
- Organization
- შ.პ.ს.. ოპტიმუსი
- Company code
- 404420998
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- თამაზი ქვრივიშვილი
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- გაიოზ ჭანკვეტაძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.17.13.025.011
- Owner
- ერთობლივი საქმიანობის ამხანაგობა "ალფას ჰაუს N4"
- Area
- 456 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 3 October 2026
Plots and zoning
- 01.17.13.025.011Registry extract ↗ (opens in a new tab)
Document
- Number
- AR1280517
- Status
- Approved
- Registered
- 23 January 2015
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 3 October 2026
Case progress
- Length of the case
- 4 days
- from the last re-submission to the decision
- Rounds of remarks
- 10
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 19 May 2015Decision1901405 - Granted
- 19 May 2015City answer
1. შეთანხმდეს: ქ. თბილისში, სექტორი ისანი, შორაპნის #28ა, კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (საკ. კოდი №01.17.13.025.011), მრავალბინიანი საცხოვრებელი სახლის არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2015 წლის 19 მაისის 2016 წლის 19 მაისის ჩათვლით. 4. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე სამშენებლო მოედანზე იქონიოს პასუხისმგებელი პირის მიერ ხელმოწერილი სამშენებლო დოკუმენტი კანონით გათვალისწინებული სრული შემადგენლობით, მათ შორის: 4.1. სამშენებლო მიწის ნაკვეთის საინჟინრო-გეოლოგიური კვლევა; 4.2. საჭიროების შემთხვევაში შენობა-ნაგებობებისა და მიწის ნაკვეთ(ებ)ის კვლევა „მშენებლობის ნებართვის გაცემის წესისა და სანებართვო პირობების შესახებ“ საქართველოს მთავრობის 24.03.2009 წლის №57 დადგენილების 35-ე მუხლის შესაბამისად; 4.3. მშენებლობის ორგანიზაციის პროექტი საქართველოს მთავრობის 24.03.2009 წლის №57 დადგენილების 61-ე მუხლის და „მშენებლობის უსაფრთხოების წესების“ (დამტკიცებული საქართველოს მთავრობის 28.03.2007 წლის №62 დადგენილებით) მოთხოვნათა შესაბამისად; 4.4. კონსტრუქციული პროექტი, რომელიც შედგება შენობა-ნაგებობის ძირითადი კონსტრუქციული სისტემის დეტალური პროექტისაგან, მათ შორის, ფუძე-საძირკვლისაგან. 4.5. მწვანე ნარგავების (გარდა ხილ-კენკროვანი მცენარეებისა) ჭრის/გადარგვის აუცილებლობის შემთხვევაში ქ. თბილისის მერიის ეკოლოგიისა და გამწვანების საქალაქო სამსახურიდან მიღებული შესაბამისი ნებართვა. 4.6. მიწისზედა/მიწისქვეშა ხაზობრივი ნაგებობების არსებობის შემთხვევაში, შესაბამისი მესაკუთრის თანხმობა/ნებართვა.
Show moreShow less
- 15 May 2015City answer
- 15 May 2015Files uploaded
- 13 May 2015City answer
- 13 May 2015Files uploaded
- 28 April 2015City answer
- 28 April 2015Files uploaded
- 28 April 2015Files uploaded
- 28 April 2015Files uploaded
- 28 April 2015Files uploaded
- 28 April 2015Files uploaded
- 24 April 2015City answer
- 24 April 2015Files uploaded
- 24 April 2015Files uploaded
- 22 April 2015City answer
- 22 April 2015Files uploaded
- 22 April 2015Files uploaded
- 20 April 2015City answer
- 20 April 2015Files uploaded
- 20 April 2015Files uploaded
- 8 March 2015City answer
- 8 March 2015Files uploaded
- 8 March 2015Files uploaded
- 8 March 2015Files uploaded
- 8 March 2015Files uploaded
- 4 March 2015City answer
- 4 March 2015Files uploaded
- 1 March 2015City answer
- 1 March 2015Files uploaded
- 1 March 2015Files uploaded
- 1 March 2015Files uploaded
- 28 February 2015Files uploaded
- 28 February 2015Files uploaded
- 21 January 2015Files uploaded
- 21 January 2015Files uploaded
- 21 January 2015Files uploaded
Documents
Drawings and project files11
- generalurigegma.pla
- asatvirtiproeqti.pla
- asatvirtiproeqti.pla
- asatvirtigeneralurigegma.pla
- proeqti3.pla
- proeqti5.pla
Show all (11)Show less
- generalurigegma.pla
- shorapani2.pla
- shorapani3.pla
- proeqti4.pla
- shorapani5.pla
Reports and surveys1
- სამეწარმეოამონაწერი.pdfOpen ↗
Other files56
- generalurigegmashorapani.pdfOpen ↗
- gegmebishorapani.pdfOpen ↗
- wrilebishorapani.pdfOpen ↗
- fasadebishorapani.pdfOpen ↗
- fotomonta48.pdfOpen ↗
- dddd.jpgOpen ↗
Show all (56)Show less
- eduardi2.jpgOpen ↗
- xzxcz.jpgOpen ↗
- kalendarulishorapani.pdfOpen ↗
- arsebulisuratebi2.pdfOpen ↗
- simaglisganmsazgvrelisqema.pdfOpen ↗
- asatvirtifasadebi2.pdfOpen ↗
- asatvirtiwrilebi2.pdfOpen ↗
- asatvirtigegmebi2.pdfOpen ↗
- gengegmatopo.pdfOpen ↗
- shorapani1 (1).jpgOpen ↗
- shorapani1 (2).jpgOpen ↗
- shorapani1 (3).jpgOpen ↗
- amonawerigamwvaneba.pdfOpen ↗
- fotomontaji1234.pdfOpen ↗
- simaglisqema1.pdfOpen ↗
- gegmebi3.pdfOpen ↗
- wrilebi3.pdfOpen ↗
- fasadebi3.pdfOpen ↗
- 333.jpgOpen ↗
- gk1.pdfOpen ↗
- wk1.pdfOpen ↗
- fk1.pdfOpen ↗
- output111.pdfOpen ↗
- e222.jpgOpen ↗
- ee3322.jpgOpen ↗
- fotomontaji[number].pdfOpen ↗
- generalurigegma.pdfOpen ↗
- ertianigegmebi.pdfOpen ↗
- ertianiwrilebi.pdfOpen ↗
- ertianifasadebi.pdfOpen ↗
- 1.jpgOpen ↗
- 2.jpgOpen ↗
- 4.jpgOpen ↗
- ertianigegmebi2.pdfOpen ↗
- ertianebiwrilebi2.pdfOpen ↗
- ertianifasadebi3.pdfOpen ↗
- daskvnaazomviti.pdfOpen ↗
- ipotyekaristanxmoba.pdfOpen ↗
- simagle4.pdfOpen ↗
- wrilebi4.pdfOpen ↗
- grafiki4.pdfOpen ↗
- Untitled.pdfOpen ↗
- DASQVNA-EDIIIK.pdfOpen ↗
- gegmebi3.pdfOpen ↗
- simagle55.pdfOpen ↗
- gtafiki6.pdfOpen ↗
- gegmebi73.pdfOpen ↗
- DASQVNA TAMAZI.pdfOpen ↗
- grafiki7.pdfOpen ↗
- DownloadServlet.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal