ქალაქი თბილისი , ვარაზის ხევში
- Total floor area
- 613.3 m²
- Building footprint
- 625.8 m²
- Plot area
- 1,210 m²
- Height
- 12.2 m
- Depth below ground
- 3.6 m
- Building volume
- 2,460 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 2932473
- Decision date
- 10 November 2016
- Outcome
- Granted
- Construction period
- 12 November 2016 – 12 November 2017
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ვანო გარსევანიშვილი
- Organization
- 13018
- Developer (company ID)
- 204900358
People
- Client
- Name
- ვანო გარსევანიშვილი
- Personal number
- *********36
- Organization
- შპს "ვარაზის ხევი 95"
- Company code
- 204900358
- Chief architect
- Name
- ნუგზარ დვალიშვილი
- Personal number
- *********88
- Organization
- შპს "ნოა"
- Company code
- 400054631
- Co-authors
- Name
- ანა ბერძენიშვილი
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- ანა გინტური
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.14.14.010.002
- Owner
- შპს "ვარაზის ხევი 95" (204900358) (204900358)
- Area
- 1,210 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 3 October 2026
Plots and zoning
- 01.14.14.010.002Registry extract ↗ (opens in a new tab)
- Zone
- Recreational
- Sub-zone
- rz-2
- K1
- 0.2
- K2
- 0
- K3
- 0
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR1436774
- Status
- Approved
- Registered
- 23 September 2016
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 3 October 2026
Case progress
- Length of the case
- 7 days
- from the last re-submission to the decision
- Rounds of remarks
- 5
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 10 November 2016City answer
1. შეთანხმდეს ქ. თბილისში (სექტორი – ვაკე), ვარაზის ხევში, შ.პ.ს. "ვარაზის ხევი 95"-ის საკუთრების მიწის ნაკვეთზე რესტორნის არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2016 წლის 12 ნოემბრიდან 2017 წლის 12 ნოემბრის ჩათვლით. 4. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე სამშენებლო მოედანზე იქონიოს პასუხისმგებელი პირის მიერ ხელმოწერილი სამშენებლო დოკუმენტი კანონით გათვალისწინებული სრული შემადგენლობით, მათ შორის: 4.1. სამშენებლო მიწის ნაკვეთის საინჟინრო-გეოლოგიური კვლევა; 4.2. საჭიროების შემთხვევაში შენობა-ნაგებობებისა და მიწის ნაკვეთ(ებ)ის კვლევა „მშენებლობის ნებართვის გაცემის წესისა და სანებართვო პირობების შესახებ“ საქართველოს მთავრობის 24.03.2009 წლის №57 დადგენილების 35-ე მუხლის შესაბამისად; 4.3. მშენებლობის ორგანიზაციის პროექტი საქართველოს მთავრობის 24.03.2009 წლის №57 დადგენილების 61-ე მუხლის და „მშენებლობის უსაფრთხოების წესების“ (დამტკიცებული საქართველოს მთავრობის 28.03.2007 წლის №62 დადგენილებით) მოთხოვნათა შესაბამისად; 4.4. კონსტრუქციული პროექტი, რომელიც შედგება შენობა-ნაგებობის ძირითადი კონსტრუქციული სისტემის დეტალური პროექტისაგან, მათ შორის, ფუძე-საძირკვლისაგან. 4.5. მწვანე ნარგავების (გარდა ხილ-კენკროვანი მცენარეებისა) ჭრის/გადარგვის აუცილებლობის შემთხვევაში ქ. თბილისის მერიის ეკოლოგიისა და გამწვანების საქალაქო სამსახურიდან მიღებული შესაბამისი ნებართვა. 4.6. მიწისზედა/მიწისქვეშა ხაზობრივი ნაგებობების არსებობის შემთხვევაში, შესაბამისი მესაკუთრის თანხმობა/ნებართვა.
Show moreShow less
- 10 November 2016Decision2932473 - Granted
- 4 November 2016City answer
- 3 November 2016City answer
- 3 November 2016Files uploaded
- 3 November 2016Files uploaded
- 3 November 2016Files uploaded
- 18 October 2016City answer
- 18 October 2016Files uploaded
- 18 October 2016Files uploaded
- 18 October 2016Files uploaded
- 28 September 2016City answer
- 28 September 2016Files uploaded
- 28 September 2016Files uploaded
- 28 September 2016Files uploaded
- 27 September 2016Files uploaded
- 27 September 2016Files uploaded
- 27 September 2016Files uploaded
- 23 September 2016Files uploaded
- 23 September 2016Files uploaded
- 23 September 2016Files uploaded
- 23 September 2016Files uploaded
- 23 September 2016Files uploaded
- 5 September 2016Files uploaded
- 5 September 2016Files uploaded
- 2 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
- 1 September 2016Files uploaded
Documents
Drawings and project files16
- gengegma.pla
- proeqti.pla
- gengegma.pla
- proeqti.pla
- TOPO,GENGEGMA.pla
- PROEQTI.pla
Show all (16)Show less
- TOPO,GENGEGMA.pla
- PROEQTI.pla
- PROEQTI.pla
- TOPO,GENGEGMA.pla
- PROEQTI.pla
- TOPO,GEN.pla
- PROEQTI-koreq.pla
- TOPO,GEN.pla
- PROEQTI-koreq.pla
- proeqti.pla
Consents and orders1
- უნივერსიტეტი თანხმობა.pdfOpen ↗
Other files58
- [number]_26) fotoebi.pdfOpen ↗
- GENGEGMA.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- CHRILEBI.pdfOpen ↗
- FASADEBI.pdfOpen ↗
- [number]_51) klalend.grafiki.pdfOpen ↗
Show all (58)Show less
- CHRILEBI.pdfOpen ↗
- sxivi.pdfOpen ↗
- GENGEGMA.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- rend.pdfOpen ↗
- [number]_29) 1.jpgOpen ↗
- [number]_29) 2.jpgOpen ↗
- [number]_29) 3.jpgOpen ↗
- [number]_29) 4.jpgOpen ↗
- [number]_29) 5.jpgOpen ↗
- TOPO,GENGEGMA.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- CHRILEBI.pdfOpen ↗
- FASADEBI.pdfOpen ↗
- simg.ganm.pdfOpen ↗
- [number]_29) 1.jpgOpen ↗
- [number]_29) 2.jpgOpen ↗
- [number]_29) 3.jpgOpen ↗
- [number]_29) 4.jpgOpen ↗
- [number]_38) 5.jpgOpen ↗
- axali,rend.pdfOpen ↗
- CHRILEBI,sardaf gansh..pdfOpen ↗
- [number]_51) klalend.grafiki.pdfOpen ↗
- SABUTEBI,KVLEVA.pdfOpen ↗
- docs.pdfOpen ↗
- TOPO,GENGEGMA 2.pdfOpen ↗
- grafiki 3.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- CHRILEBI, sardaf ganshla.pdfOpen ↗
- FASADEBI.pdfOpen ↗
- SXIVI.pdfOpen ↗
- REND,MONT.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- TOPO,GENGEGMA.pdfOpen ↗
- GEGMEBI.pdfOpen ↗
- CHRILEBI,sardaf ganshla.pdfOpen ↗
- FASADEBI.pdfOpen ↗
- SXIVI.pdfOpen ↗
- REND,MONT.pdfOpen ↗
- TOPOGENGEGMA 4.pdfOpen ↗
- TOPO,GEN.pdfOpen ↗
- GEGMEBI-koreq.pdfOpen ↗
- CHRILEBI-koreqt.pdfOpen ↗
- FASADEBI-koreqt.pdfOpen ↗
- REND,MONT.pdfOpen ↗
- TOPO, GEN.pdfOpen ↗
- GEGMEBI-koreq.pdfOpen ↗
- dendrologia.pdfOpen ↗
- CHRILEBI.pdfOpen ↗
- AR1451512.pdfOpen ↗
- mosakrebeli,tanxmoba.pdfOpen ↗
- DOC.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal