ქალაქი თბილისი , ქუჩა იალბუზი , N 17-ის მიმდებარედ / ქალაქი თბილისი , ქუჩა 300 არაგველი , N 22 , მიმდებარედ / ქალაქი თბილისი , 300 არაგველის IIგასასვლელი N23-ის მიმდებარედ/ ქალაქი თბილისი , ქუჩა 300 არაგველი , N 2/3 / ქალაქი თბილისი , ქუჩა 300 არაგველი , N 31 / ქალაქი თბილისი , ქუჩა 300 არაგველი , N 31 / ქალაქი თბილისი , ქუჩა 300 არაგველი , N22 / ქალაქი თბილისი , იალბუზის ქუჩის ასახვევთან არსებული ფერდობი (ნაკვეთი 138/074)/ ქალაქი თბილისი , იალბუზის ქუჩის ასახვევთან არსებული ფერდობი/ ქალაქი თბილისი , ქუჩა 300 არაგველი , N22-ის მიმდებარედ
- Total floor area
- 8,835.3 m²
- Building footprint
- 783.2 m²
- Plot area
- 1,653 m²
- Height
- 60.3 m
- Depth below ground
- 3 m
- Building volume
- 35,802.6 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 3689817
- Decision date
- 17 November 2017
- Outcome
- Granted
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ზვიად სურგულაძე
- Developer (company ID)
- 402031868
People
- Client
- Name
- გიორგი ბერიანიძე
- Personal number
- *********31
- Organization
- შ.პ.ს. "კიტ 2016"
- Company code
- 402031868
- Chief architect
- Name
- ზვიად სურგულაძე
- Personal number
- *********66
- Organization
- შ.პ.ს. "სურგულა"
- Company code
- 404479391
- Co-authors
- Name
- დავით ვეშაპიძე
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- იუზა გეფერიძე
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- ბელა გოგოლაური
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- გუგა ჭოხონელიძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- გივი დანელია
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.17.01.138.126
- Owner
- შპს ,,კიტ 2016,, (402031868)
- Area
- 1,653 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 3 October 2026
Plots and zoning
- 01.17.01.138.126Registry extract ↗ (opens in a new tab)
Document
- Number
- AR1514775
- Status
- Approved
- Registered
- 16 June 2017
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 3 October 2026
Case progress
- Length of the case
- 1 day
- from the last re-submission to the decision
- Rounds of remarks
- 5
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 17 November 2017City answer
1. შესრულებულად ჩაეთვალოს მოქ. ზვიად სურგულაძის ქ. თბილისის მუნიციპალიტეტის სსიპ – ქ. თბილისის არქიტექტურის სამსახურის 10.11.2017 წ. №3674596 ბრძანების მე-5 პუნქტით გათვალისწინებული მოთხოვნა. 2. 16.06.2017 წ AR1514775 განცხადებით წარმოდგენილი დოკუმენტაცია არის სამშენებლო დოკუმენტის განუყოფელი ნაწილი და განხილულ იქნას მასთან ერთად. 3. წინამდებარე ბრძანება <span lang="GEO/KAT" style="font-family:"Sylfaen","ser
Show moreShow less
- 17 November 2017Decision3689817 - Granted
- 16 November 2017City answer
- 16 November 2017Files uploaded
- 9 November 2017City answer
- 9 November 2017Files uploaded
- 9 August 2017Files uploaded
- 9 August 2017Files uploaded
- 7 August 2017City answer
- 7 August 2017Files uploaded
- 7 August 2017Files uploaded
- 2 August 2017City answer
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 2 August 2017Files uploaded
- 10 July 2017Deadline extendedby 15 days, new deadline: 8 August 2017
- 4 July 2017Files uploaded
- 4 July 2017Files uploaded
- 4 July 2017Files uploaded
- 3 July 2017Files uploaded
- 3 July 2017Files uploaded
- 3 July 2017Files uploaded
- 3 July 2017Files uploaded
- 3 July 2017Files uploaded
- 30 June 2017Files uploaded
- 30 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
- 16 June 2017Files uploaded
Some older entries, and the rest of very long texts, are not shown here.
Documents
Drawings and project files12
- V01 GENGEGMA.dwg
- V01 RENDER MONTAJ.pdfOpen ↗
- V01 PARK HOTEL.dwg
- V02 GENGEGMA.dwg
- V02 RENDER MONTAJ.pdfOpen ↗
- V02 GENGEGMA.dwg
Show all (12)Show less
- V02 GENGEGMA.dwg
- V02 PARK HOTEL.dwg
- V03 RENDER MONTAJ.pdfOpen ↗
- V03 PARK HOTEL.dwg
- V03 GENGEGMA.dwg
- V03++GENGEGMA.dwg
Other files49
- V01 GENGEGMA.pdfOpen ↗
- V01 GEGMA.pdfOpen ↗
- V01 CHRILI.pdfOpen ↗
- V01 FASADI.pdfOpen ↗
- V01 SIMAGLE.pdfOpen ↗
- V01 KAL GRAFIKI.pdfOpen ↗
Show all (49)Show less
- V01 FOTO.pdfOpen ↗
- V7-005.jpgOpen ↗
- V7-006.jpgOpen ↗
- V7-007.jpgOpen ↗
- V7-008.jpgOpen ↗
- V7-001.jpgOpen ↗
- V01 KONSTRUQCIA DASKVNA.pdfOpen ↗
- V01 MIND.pdfOpen ↗
- V01 BANERI.pdfOpen ↗
- V02 KAL GRAFIKI.pdfOpen ↗
- brzaneba 1-1000.pdfOpen ↗
- V02 GENGEGMA.pdfOpen ↗
- V02 GENGEGMA.pdfOpen ↗
- V02 FOTO.pdfOpen ↗
- V02 CHRILI.pdfOpen ↗
- V02 FASADI.pdfOpen ↗
- V02 GEGMA.pdfOpen ↗
- V8-005.jpgOpen ↗
- V8-006.jpgOpen ↗
- V8-007.jpgOpen ↗
- V8-008.jpgOpen ↗
- V8-001.jpgOpen ↗
- V02 MOMIJNAVE SHEN DASKVNA.pdfOpen ↗
- V02 KONSTRUQCIA DASKVNA.pdfOpen ↗
- meris gankarguleba.pdfOpen ↗
- V02 GENGEGMA.pdfOpen ↗
- V02 GENGEGMA.pdfOpen ↗
- V02 FOTO.pdfOpen ↗
- V02 GEGMA.pdfOpen ↗
- V02 FASADI.pdfOpen ↗
- V02 GEGMA.pdfOpen ↗
- V02 CHRILI.pdfOpen ↗
- V02 FASADI.pdfOpen ↗
- V02 MERIS BRZANEBA.pdfOpen ↗
- V02 XAZOVANI NAG.pdfOpen ↗
- V03 GEGMA.pdfOpen ↗
- V03 CHRILI.pdfOpen ↗
- V03 FASADI.pdfOpen ↗
- V03 GENGEGMA.pdfOpen ↗
- V03 XAZOVANI NAG.pdfOpen ↗
- gen-gegma.pdfOpen ↗
- GWP.pdfOpen ↗
- GWP 2.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal