ქალაქი თბილისი , დავით აღმაშენებლის ხეივანი N91ა
- Total floor area
- 90.9 m²
- Building footprint
- 66.5 m²
- Plot area
- 2,381 m²
- Height
- 7.3 m
- Depth below ground
- 3.3 m
- Building volume
- 339.8 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 4032827
- Decision date
- 25 June 2018
- Outcome
- Granted
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- გულნაზი ლომსაძე
- Developer (company ID)
- 205151262
People
- Client
- Name
- გულნაზი ლომსაძე
- Personal number
- *********33
- Organization
- შპს მარანი
- Company code
- 205151262
- Chief architect
- Name
- ოთარ კობიძე
- Personal number
- *********91
- Specialistსარეკონსტრუქციო შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- დავით მანჯგალაძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.13.01.015.105
- Owner
- შპს "მარანი" (205151262)
- Area
- 2,381 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 3 October 2026
Plots and zoning
- 01.13.01.015.105Registry extract ↗ (opens in a new tab)
- Zone
- Residential
- Sub-zone
- sz-3
- K1
- 0.5
- K2
- 1.5
- K3
- 0.2
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR1582102
- Status
- Approved
- Registered
- 8 March 2018
- Type
- Extension / extension with added floors
Source: TAS, the city's permit system - read from TAS 2 October 2026
Case progress
- Length of the case
- 1 day
- from the last re-submission to the decision
- Rounds of remarks
- 6
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 25 June 2018City answer
შეთანხმდეს ქ. თბილისში, სექტორი–დიდუბე, დავით აღმაშენებლის ხეივანი № 91ა-ში, შპს "მარანი"-ს კუთვნილ მიწის ნაკვეთზე (ს/კ № 01.13.01.015.105) არსებული №2/1 შენობის (მაღაზიის) რეკონსტრუქციის (დაშენების) არქიტექტურული პროექტი.
- 25 June 2018Decision4032827 - Granted
- 24 June 2018City answer
- 24 June 2018Files uploaded
- 20 June 2018City answer
- 20 June 2018Files uploaded
- 20 June 2018Files uploaded
- 8 June 2018Files uploaded
- 8 June 2018Files uploaded
- 8 June 2018Files uploaded
- 8 June 2018Files uploaded
- 8 June 2018Files uploaded
- 8 June 2018Files uploaded
- 7 June 2018Files uploaded
- 30 May 2018City answer
- 30 May 2018Files uploaded
- 30 May 2018Files uploaded
- 21 May 2018City answer
- 21 May 2018Files uploaded
- 21 May 2018Files uploaded
- 21 May 2018Files uploaded
- 21 May 2018Files uploaded
- 21 May 2018Files uploaded
- 21 May 2018Files uploaded
- 26 April 2018City answer
- 25 April 2018Files uploaded
- 25 April 2018Files uploaded
- 17 April 2018Deadline extendedby 7 days, new deadline: 8 May 2018
- 8 March 2018Files uploaded
- 8 March 2018Files uploaded
- 8 March 2018Files uploaded
- 8 March 2018Files uploaded
- 8 March 2018Files uploaded
- 6 March 2018Files uploaded
- 6 March 2018Files uploaded
- 6 March 2018Files uploaded
- 6 March 2018Files uploaded
- 6 March 2018Files uploaded
- 5 March 2018Files uploaded
Documents
Drawings and project files50
- d. aRmaSeneblis xeivani #91a_TOPO.DWG
- გეგმები.pdfOpen ↗
- ჭრილი.pdfOpen ↗
- ფასადები.pdfOpen ↗
- ვიზუალიზაცია ზომების და ნიშნულების ჩვენებით.pdfOpen ↗
- გენგეგმა.pdfOpen ↗
Show all (50)Show less
- გენგეგმა.dwg
- ჭრილი.pdfOpen ↗
- გეგმები C1.pdfOpen ↗
- ჭრილი C1.pdfOpen ↗
- ფასადები C1.pdfOpen ↗
- ჭრილი C1.pdfOpen ↗
- გენგეგმა C1.dwg
- CAD FAILI.dwg
- 0. არსებული ( გენგეგმა ).pdfOpen ↗
- ფასადები C1.pdfOpen ↗
- გეგმები C2.pdfOpen ↗
- ჭრილები C2.pdfOpen ↗
- CAD FAILI C2.dwg
- გენგეგმა C2.dwg
- გეგმები C3.pdfOpen ↗
- ჭრილები C3.pdfOpen ↗
- ფასადები C2.pdfOpen ↗
- ჭრილები C4.pdfOpen ↗
- ფასადები C3.pdfOpen ↗
- გეგმები C4.pdfOpen ↗
- Drawing C3.dwg
- გეგმები C8 +განაშენიანების კოეფიციენტები.pdfOpen ↗
- ჭრილები C8.pdfOpen ↗
- ფასადები C8.pdfOpen ↗
- Drawing C8.dwg
- გენგეგმა + ტოპო C9.dwg
- გეგმები + განაშენიანების კოეფიციენტები C9.pdfOpen ↗
- ჭრილები C9.pdfOpen ↗
- ფასადები C9.pdfOpen ↗
- Drawing C9.dwg
- გეგმები + განაშენიანების კოეფიციენტები C9.1.pdfOpen ↗
- გეგმები + განაშენიანების კოეფიციენტები C9.pdfOpen ↗
- გეგმები+განაშენიანების კოეფიციენტები C9.pdfOpen ↗
- გეგმები + განაშენიანების კოეფიციენტები C9.pdfOpen ↗
- Drawing - C9.dwg
- გეგმები + განაშენიანების კოეფიციენტები C9.pdfOpen ↗
- გენგეგმა + ტოპო C9.5.dwg
- გეგმები + განაშენიანების კოეფიციენტები C9.5.pdfOpen ↗
- ჭრილები C9.5.pdfOpen ↗
- ფასადები C9.5.pdfOpen ↗
- Drawing - C9.5.dwg
- გეგმები + განაშენიანების კოეფიციენტები C9.6.pdfOpen ↗
- Drawing - C9.6.dwg
- Drawing - C9.5.dwg
Consents and orders1
- თანხმობა C1.pdfOpen ↗
Reports and surveys9
Other files9
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal