ქალაქი თბილისი , გამზირი ილია ჭავჭავაძე , N 49ბ , (ნაკვ. 8/6)

AR1644467Change to approved projectOther use18 December 2018- Tskneti
Total floor area
70,154.6 m²
Building footprint
5,172.5 m²
Plot area
5,820 m²
Height
157.7 m
Depth below ground
13.1 m
Building volume
811,872 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
4519273
Decision date
28 May 2019
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
ელგუჯა მხეიძე
Organization
17460
Developer (company ID)
405144703

People

  • Client
    Name
    ელგუჯა მხეიძე
    Personal number
    *********48
    Organization
    შპს ალიანსი თბილისი
    Company code
    405144703
  • Chief architect
    Name
    გიორგი ხმალაძე
    Personal number
    *********32
    Organization
    შპს ხმალაძე არქიტექტორები
    Company code
    404856376
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    ვიტალი დვალიშვილი
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    აკაკი გავაშელი
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გუგა ჭოხონელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    ზურაბ გუბელიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.14.07.008.123
Owner
შპს "ალიანსი" (445453526)
Area
5,820 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 21 November 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1644467
Status
Approved
Registered
18 December 2018
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 2 October 2026

Case progress

Length of the case
17 days
from the last re-submission to the decision
Rounds of remarks
6

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 28 May 2019City answer

    1. შეთანხმდეს: ქ. თბილისში, გამზირი ილია ჭავჭავაძე, N 49ბ, (ნაკვ. 8/6), საკუთრებაში არსებულ მიწის ნაკვეთზე (საკ. კოდი №01.14.07.008.123), მრავალფუნქციური კომპლექსის (საცხოვრებელი, საოფისე, კომერციული და სასტუმრო) კორექტირებული არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს TIME \@ "dd.MM.yyyy" 28.05.2019 წ-დან 28.01.2022 წ-ის ჩათვლით. 4. განემარტოს დამკვეთს, რომ ვალდებულია<spa

    Show more
  2. 28 May 2019Decision4519273 - Granted
  3. 22 May 2019City answer
  4. 11 May 2019City answer
  5. 11 May 2019Files uploaded
  6. 11 May 2019Files uploaded
  7. 11 May 2019Files uploaded
  8. 8 May 2019Deadline extendedby 15 days, new deadline: 17 May 2019
  9. 29 March 2019City answer
  10. 28 March 2019Files uploaded
  11. 27 March 2019Files uploaded
  12. 7 March 2019City answer
  13. 7 March 2019Files uploaded
  14. 6 March 2019Files uploaded
  15. 5 March 2019Files uploaded
  16. 1 March 2019Files uploaded
  17. 1 March 2019Files uploaded
  18. 1 March 2019Files uploaded
  19. 1 March 2019Files uploaded
  20. 14 February 2019City answer
  21. 14 February 2019Files uploaded
  22. 14 February 2019Files uploaded
  23. 14 February 2019Files uploaded
  24. 14 February 2019Files uploaded
  25. 14 February 2019Files uploaded
  26. 14 February 2019Files uploaded
  27. 14 January 2019Deadline extendedby 15 days, new deadline: 15 February 2019
  28. 10 January 2019Files uploaded
  29. 10 January 2019Files uploaded
  30. 17 December 2018Files uploaded
  31. 17 December 2018Files uploaded
  32. 17 December 2018Files uploaded
  33. 17 December 2018Files uploaded
  34. 17 December 2018Files uploaded
  35. 17 December 2018Files uploaded
  36. 17 December 2018Files uploaded
  37. 11 December 2018Files uploaded
  38. 11 December 2018Files uploaded
  39. 10 December 2018Files uploaded
  40. 10 December 2018Files uploaded
  41. 26 November 2018Files uploaded
  42. 26 November 2018Files uploaded
  43. 26 November 2018Files uploaded
  44. 24 November 2018Files uploaded
  45. 24 November 2018Files uploaded
  46. 21 November 2018Files uploaded
  47. 21 November 2018Files uploaded
  48. 21 November 2018Files uploaded
  49. 15 November 2018Files uploaded
  50. 15 November 2018Files uploaded
  51. 15 November 2018Files uploaded

Some older entries, and the rest of very long texts, are not shown here.

Documents

Drawings and project files31

  • 029_[number]_L_masterplan.dwg
  • 029_[number]_L_masterplan.pdfOpen ↗
  • 029_[number]_L_masterplan.dwg
  • 029_[number]_L_masterplan.pdfOpen ↗
  • 029_20181121_L_facades_F.pdfOpen ↗
  • 029_20181124_L_sections.pdfOpen ↗
Show all (31)
  • 029_20181125_L_sections.pdfOpen ↗
  • 029_20181126_L_plans.pdfOpen ↗
  • 029_20181126_L_dwg.dwg
  • 029_20181124_L_facades.pdfOpen ↗
  • 029_20181211_L_plans.pdfOpen ↗
  • 029_20181211_L_dwg.dwg
  • 029_20181124_L_facades.pdfOpen ↗
  • 029_[number]_L_plans.dwg
  • 029_[number]_L_plans.pdfOpen ↗
  • 029_[number]_L_masterplan.pdfOpen ↗
  • 029_[number]_L_Section.pdfOpen ↗
  • 029_20181217_L_facades.pdfOpen ↗
  • 029_[number]_L.dwg
  • 029_20190110_L_Sections.pdfOpen ↗
  • 029_20190214_plan_L.pdfOpen ↗
  • 029_20190214_L_dwg.dwg
  • 029_20190214_plan_L_1.pdfOpen ↗
  • 029_20190214_L_dwg_.dwg
  • 029_20190301_L_dwg_.dwg
  • 029_20190301_L.dwg.dwg
  • 029_20190301_L.dwg.dwg
  • 029_20190305_L.dwg.dwg
  • 029_20190307_L.dwg.dwg
  • 029_20190327_L.dwg.dwg
  • 029_20190512_L_asatvirti.dwg.dwg

Reports and surveys5

  • geologia.pdfOpen ↗
  • მშენაღმდგენ ამ საექსპერტო დასკვნა.pdfOpen ↗
  • ტექნიკური ექსპერტიზის დასკვნა.pdfOpen ↗
  • დასკვნა ჭავჭავაძის 49ბ.pdfOpen ↗
  • დასკვნა_კონსტრუქციული ნაწილის 20181221.pdfOpen ↗

Other files35

Show all (35)
  • 01 (5).jpgOpen ↗
  • mesakuTreta tanxmobebi.pdfOpen ↗
  • qvitrebi da brdzaneba mosakreblis.pdfOpen ↗
  • 029_20181115 _arsebuli potoebi.pdfOpen ↗
  • 029_20181126 _arsebuli potoebi.pdfOpen ↗
  • 029_20181126 _baneri.pdfOpen ↗
  • 029_20181210 _arsebuli potoebi.pdfOpen ↗
  • 029_20181210 _baneri.pdfOpen ↗
  • 029_20181210_kalendruli grafiki.pdfOpen ↗
  • 20181210_დამატებითი მასალები.zipOpen ↗
  • 20181211_დამატებითი მასალები.zipOpen ↗
  • 20181217_დამატებითი მასალები.zipOpen ↗
  • 029_20181217__დამატებითი მასალები.7zOpen ↗
  • 029_20181228_kalendruli grafiki.pdfOpen ↗
  • 029_20190214_kalendruli grafiki.pdfOpen ↗
  • 029_20190214_chrilebi_L.pdfOpen ↗
  • 029_20190214_chrilebi_L_.pdfOpen ↗
  • kontr 1.pdfOpen ↗
  • 029_20190214_kalendruli grafiki_1.pdfOpen ↗
  • kontr 2.pdfOpen ↗
  • 029_20190301_kalendruli grafiki.pdfOpen ↗
  • 029_20190301_kalendruli grafiki.pdfOpen ↗
  • 029_20190305_qvitari_20 lari.pdfOpen ↗
  • 029_20190307_kalendruli grafiki.pdfOpen ↗
  • 029_20190327_sagangebos werili.pdfOpen ↗
  • 029_20190325_kalendruli grafiki.pdfOpen ↗
  • 029_20190328_kalendruli grafiki.pdfOpen ↗
  • municipaluri inspeqciis rekomendacia.pdfOpen ↗
  • ინსპექციის წერილი, თამარაშვილის მიმდებარე გზის ნებართვა და ვადის გაგრძელება 1 წლით.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal