OpenCAD
Interim decision

ქალაქი თბილისი , ქუჩა სოხუმი , N 4-6ა

AR1667577Construction permitOther use12 March 2019
Sign in to follow

Applicant

Name
ბაგრატ პაკელიანი
Developer (company ID)
202361951

Parcel

Cadastral code
01.13.06.015.012
Owner
ამხანაგობა "სოხუმის 4"
Area
2,947 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 3 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1667577
Status
Interim decision
Registered
12 March 2019
Type
Construction permit

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Waiting on
the applicant
since 29 October 2019 (2,582 days)
Rounds of remarks
12

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 29 October 2019City answer

    ქ. თბილისის მუნიციპალიტეტის სსიპ – ქ. თბილისის მუნიციპალიტეტის არქიტექტურის სამსახურმა განიხილა თქვენ მიერ ელექტრონულად ატვირთული განცხადება და მასზე თანდართული დოკუმენტაცია, პასუხად გაცნობებთ შემდეგს: ვინაიდან არ არის დოკუმენტაცია განახლებული, განცხადებას გიბრუნებთ შუალედური სახით. იხელმძღვანელეთ №4701300 (07/10/2019) შუალედური გადაწყვეტილების მითითებების შესაბამისად. გაცნობებთ, რომ ხარვეზების გამოსწორებისთვის გეძლევათ 15 სამუშაო დღე. მოცემულ ვადაში ხარვეზების შეუსრულებლობის შემთხვევაში განცხადება დარჩება განუხილველი. გაითვალისწინეთ, რომ სამსახურის მიერ მითითებული ხარვეზების გაუთვალისწინებლობის შემთხვევაში წინამდებარე განცხადება დარჩება განუხილველი.

    Show more
  2. 28 October 2019City answer
  3. 4 October 2019City answer
  4. 12 September 2019City answer
  5. 12 September 2019Files uploaded
  6. 26 August 2019City answer
  7. 26 August 2019Files uploaded
  8. 16 August 2019City answer
  9. 16 August 2019Files uploaded
  10. 12 August 2019City answer
  11. 19 July 2019City answer
  12. 19 July 2019Deadline extendedby 15 days, new deadline: 19 July 2019
  13. 26 June 2019City answer
  14. 26 June 2019Files uploaded
  15. 22 June 2019City answer
  16. 18 June 2019Deadline extendedby 7 days, new deadline: 21 June 2019
  17. 27 May 2019City answer
  18. 27 May 2019Files uploaded
  19. 24 May 2019Deadline extendedby 7 days, new deadline: 27 May 2019
  20. 1 May 2019City answer
  21. 1 May 2019Files uploaded
  22. 10 April 2019Deadline extendedby 15 days, new deadline: 1 May 2019
  23. 12 March 2019Files uploaded

Documents

Reports and surveys1

  • სამხარაულის დასკვნა_.pdfOpen ↗

Other files12

  • 12.03. UARIS BRDZANEBA+DANARTEBI.pdfOpen ↗
  • 12.03. PHOTOEBI.pdfOpen ↗
  • 12.03. TANXMOBEBI.pdfOpen ↗
  • 27.05. tanxmobebi+UARIS BRDZANEBA+DANARTEBI+damocmeba+samxarauli.pdfOpen ↗
  • 26.06. tanxmobebi+UARIS BRDZANEBA+DANARTEBI+damocmeba+samxarauli.pdfOpen ↗
  • 26.06. UARIS BRDZANEBA+DANARTEBI.pdfOpen ↗
Show all (12)
  • 16.08. TANXMOBEBI+MINDOBILOBA.pdfOpen ↗
  • 16.08. UARIS BRDZANEBA+DANARTEBI+damocmeba+samxarauli.pdfOpen ↗
  • 26.08. TANXMOBEBI+MINDOBILOBA.pdfOpen ↗
  • 26.08. UARIS BRDZANEBA+DANARTEBI+damocmeba+samxarauli.pdfOpen ↗
  • 12.09. TANXMOBEBI+MINDOBILOBA.pdfOpen ↗
  • 12.09. UARIS BRDZANEBA+DANARTEBI+damocmeba+samxarauli.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal