ქალაქი თბილისი, ბიძინა კვერნაძის ქუჩა, N 33/პავლე ასლანიდის ქუჩა, N 40
- Total floor area
- 11,904.8 m²
- Building footprint
- 797.5 m²
- Residential area
- 6,169.9 m²
- Plot area
- 1,424 m²
- Height
- 53.2 m
- Depth below ground
- 6.1 m
- Building volume
- 44,364.2 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 5363288
- Decision date
- 12 April 2021
- Outcome
- Granted
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- შუქრი კაკაურიძე
- Developer (company ID)
- 205299737
People
- Client
- Name
- შუქრი კაკაურიძე
- Personal number
- *********08
- Organization
- ი.მ.ა "აკურის #27,29,33 ალმასიანის #34,40,42,46"
- Company code
- 205299737
- Chief architect
- Name
- პაატა ჭავჭანიძე
- Personal number
- *********48
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- სსიპ ლევან სამხარაულის სახელობის სასამართლო ექსპერტიზის ეროვნული ბიურო
- Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- პაატა ჭავჭანიძე
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- გუგა ჭოხონელიძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- მალხაზ საველიძე
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.10.13.035.053
- Owner
- ი.მ.ა "აკურის N27,29,33 ალმასიანის N34,40,42,46" (205299737)
- Area
- 1,424 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 1 October 2026
Plots and zoning
- 01.10.13.035.053Registry extract ↗ (opens in a new tab)
- Zone
- Commercial / business
- Sub-zone
- ssz-1
- K1
- 0.7
- K2
- 3.5
- K3
- 0.1
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR1698585
- Status
- Approved
- Registered
- 5 August 2019
- Type
- Change to approved project
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Length of the case
- 4 days
- from the last re-submission to the decision
- Rounds of remarks
- 18
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 12 April 2021City answer
1. შესრულებულად ჩაეთვალოს დამკვეთს ქ. თბილისის მუნიციპალიტეტის სსიპ – ქ. თბილისის არქიტექტურის სამსახურის №4641348 (21/08/2019 წ.) ბრძანების მეხუთე პუნქტით გათვალისწინებული პირობა. 2. AR1698585 (08.04.2021) განცხადებით წარმოდგენილი დოკუმენტაცია არის სამშენებლო დოკუმენტის განუყოფელი ნაწილი და განხილულ უნდა იქნას მასთან ერთად. 3. წინამდებარე ბრძანება განხილულ იქნას ქ. თბილისის მუნიციპალიტეტის სსიპ - ქ. თბილისის არქიტექტურის სამსახურის №4641348 (21/08/2019 წ.) და № 5315533 (09/03/2021 წ.) ბრძანებებთან ერთად.
Show moreShow less
- 12 April 2021Decision5363288 - Granted
- 8 April 2021City answer
- 8 April 2021Files uploaded
- 5 March 2021City answer
- 21 December 2020City answer
- 4 November 2020City answer
- 14 September 2020City answer
- 22 July 2020City answer
- 8 June 2020City answer
- 27 April 2020City answer
- 23 March 2020City answer
- 12 February 2020City answer
- 15 January 2020City answer
- 15 January 2020Files uploaded
- 30 December 2019City answer
- 30 December 2019Files uploaded
- 21 November 2019City answer
- 20 August 2019City answer
- 20 August 2019Files uploaded
- 19 August 2019City answer
- 19 August 2019Files uploaded
- 19 August 2019Files uploaded
- 15 August 2019City answer
- 15 August 2019Files uploaded
- 15 August 2019Files uploaded
- 13 August 2019City answer
- 13 August 2019Files uploaded
- 12 August 2019Files uploaded
- 12 August 2019Files uploaded
- 12 August 2019Files uploaded
- 5 August 2019Files uploaded
- 3 August 2019Files uploaded
- 3 August 2019Files uploaded
- 3 August 2019Files uploaded
- 3 August 2019Files uploaded
- 2 August 2019Files uploaded
- 2 August 2019Files uploaded
- 2 August 2019Files uploaded
- 2 August 2019Files uploaded
- 2 August 2019Files uploaded
Documents
Drawings and project files4
- akurii-axali nakveti-gengegma----AAA----02.08.2019.pla
- akuri-koreqtirebuli proeqti-coreqt. nakveti----02.08.2019.pla
- არსებული სიტუაციის ფოტოები1111.pdfOpen ↗
- akuri-kor. pr.- cor.pro.---shualeduri-AAA--tas.ge--12.08.19.pla
Other files30
- GENGEGMA-02.08.19.pdfOpen ↗
- GEGMEBI-02.08.19.pdfOpen ↗
- CHRILEBI-02.08.19.pdfOpen ↗
- FASADEBI-02.08.19.pdfOpen ↗
- simaglis angarishi-02.08.19.pdfOpen ↗
- FOTOMONTAJI-02.08.19.pdfOpen ↗
Show all (30)Show less
- FOTOMONTAJI-02.08.19.pdfOpen ↗
- FOTOMONTAJI-PERSPEQTIVI-22.09.18.pdfOpen ↗
- KONSTRUQCIULI DASKVNA-21.09.18.pdfOpen ↗
- 32. fotomontaji.jpgOpen ↗
- 33. fotomontaji.jpgOpen ↗
- 34. perspeqtivi.jpgOpen ↗
- 31. fotomontaji.jpgOpen ↗
- saeqsperto daskvna-choxonelidze.pdfOpen ↗
- saeqsperto daskvna-choxonelidze.pdfOpen ↗
- fudze-sadzirkvlebi-daskvna.pdfOpen ↗
- kalendaruli grafiki--20.12.18.pdfOpen ↗
- BANERI-01.08.2019.pdfOpen ↗
- arsebuli foto-11.08.2019.pdfOpen ↗
- gegmebi-12.08.19.pdfOpen ↗
- fotomontaji-11.08.19.pdfOpen ↗
- fasadebi-11.08.19.pdfOpen ↗
- image****-**-**-****52.pdfOpen ↗
- baneri-14.08.19.pdfOpen ↗
- savelidzis daskvna-12.08.19.pdfOpen ↗
- კ2 -ის მოსაკრებლის განმარტება.pdfOpen ↗
- kalendaruli -20.08.2019.pdfOpen ↗
- ვადის გაგრძელებასთან დაკავშირებით 30.12.19.pdfOpen ↗
- პირველ მარტამდე ვადის გაგრძელებასთან დაკავშირებით.pdfOpen ↗
- 2021_04_08_09_21_47.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal