ქალაქი თბილისი , ქუჩა რამაზ შენგელია , N 5

AR1713168Change to approved projectOther use16 October 2019- Mukhiani
Total floor area
7,769.3 m²
Building footprint
924.9 m²
Residential area
4,943 m²
Plot area
1,214 m²
Height
53.4 m
Depth below ground
3.2 m
Building volume
24,743.8 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Applicant

Name
დეა ბერია
Developer (company ID)
406035936

People

  • Client
    Name
    ზვიადი ჩანქსელიანი
    Personal number
    *********19
    Organization
    შპს 333
    Company code
    406035936
  • Chief architect
    Name
    ზურაბი ჭიღოლაშვილი
    Personal number
    *********68
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    ფელიქს კონტრიძე
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    დეა ბერია
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გუგა ჭოხონელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    შალვა დოლიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.11.13.002.210
Owner
ზვიადი ჩანქსელიანი (P/N: *********19)
Area
1,194 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 3 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1713168
Status
Interim decision
Registered
16 October 2019
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Waiting on
the applicant
since 16 January 2020 (2,503 days)
Rounds of remarks
3

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 16 January 2020City answer

    საჭიროა გაითვალისწინოტ და დააკორექტიროთ სამსახურის № 4777512 გადაწყვეტილებით დადგენილი ხარვეზები.

  2. 15 January 2020City answer
  3. 15 January 2020Files uploaded
  4. 15 January 2020Deadline extendedby 15 days, new deadline: 15 January 2020
  5. 2 December 2019City answer
  6. 2 December 2019Files uploaded
  7. 2 December 2019Files uploaded
  8. 2 December 2019Files uploaded
  9. 2 December 2019Files uploaded
  10. 2 December 2019Files uploaded
  11. 2 December 2019Files uploaded
  12. 2 December 2019Files uploaded
  13. 2 December 2019Files uploaded
  14. 28 November 2019Deadline extendedby 15 days, new deadline: 27 December 2019
  15. 16 October 2019Files uploaded
  16. 16 October 2019Files uploaded
  17. 16 October 2019Files uploaded
  18. 16 October 2019Files uploaded
  19. 16 October 2019Files uploaded
  20. 16 October 2019Files uploaded
  21. 16 October 2019Files uploaded

Documents

Drawings and project files9

  • gengegma.pla
  • simaglis gansazgvra Layout _ Layout.pdfOpen ↗
  • shengelia - koreqtireba 01 30.09.2019.pla
  • გენ-გეგმა.pdfOpen ↗
  • გენ-გეგმა.pla
  • ჭრილები.pdfOpen ↗
Show all (9)
  • ფასადები.pdfOpen ↗
  • კორექტირება.pla
  • გეგმები.pdfOpen ↗

Reports and surveys1

Other files25

Show all (25)
  • fasad.pdfOpen ↗
  • saviizito2.jpgOpen ↗
  • savizito3.jpgOpen ↗
  • savizito1.jpgOpen ↗
  • momijnavis.pdfOpen ↗
  • grafiki.pdfOpen ↗
  • combinepdf (4).pdfOpen ↗
  • სიმაღლის სქემა.pdfOpen ↗
  • მონტაჟები.pdfOpen ↗
  • სავიზიტო 1.jpgOpen ↗
  • სავიზიტო 2.jpgOpen ↗
  • სავიზიტო 3.jpgOpen ↗
  • ექსპერტიზა.pdfOpen ↗
  • არსებული.pdfOpen ↗
  • ქვითრები.pdfOpen ↗
  • მოთხოვნილი დოკუმენტაცია-min_compressed.pdfOpen ↗
  • შენგელია მშენებლობის გრაფიკი.pdfOpen ↗
  • განცხადება.pdfOpen ↗
  • ხარვეზების გამოსწორების ვადის გაგრძელების მოთხოვნა.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal