ქალაქი თბილისი, ალექსი გობრონიძის ქუჩა, N 5/რამაზ შენგელიას ქუჩა, N 10
- Total floor area
- 20,217.9 m²
- Building footprint
- 22,300.2 m²
- Plot area
- 14,911 m²
- Height
- 64.7 m
- Depth below ground
- 6.3 m
- Building volume
- 73,501.2 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 7427333
- Decision date
- 26 March 2025
- Outcome
- Granted
- Construction period
- 26 March 2025 – 26 March 2029
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ლევან მაღლაკელიძე
- Developer (company ID)
- 204573611
People
- Client
- Name
- თენგიზ წულაია
- Personal number
- *********94
- Organization
- სს "ქროსი"
- Company code
- 204573611
- Chief architect
- Name
- ლევან მაღლაკელიძე
- Personal number
- *********76
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- დემური ტაბატაძე
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- ბორის დგებუაძე
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- ია მშვიდობაძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- დემური ტაბატაძე
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- ნატო გოგორიშვილი
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.11.13.002.264
- Owner
- სააქციო საზოგადოება "ქროსი" (204573611)
- Area
- 14,911 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 1 October 2026
Plots and zoning
- 01.11.13.002.264Registry extract ↗ (opens in a new tab)
- Zone
- Residential
- Sub-zone
- sz
- K1
- 0
- K2
- 0
- K3
- 0
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR1942153
- Status
- Approved
- Registered
- 22 August 2024
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Length of the case
- 7 days
- from the last re-submission to the decision
- Rounds of remarks
- 20
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 26 March 2025City answer
1. შეთანხმდეს: ქ. თბილისში, ალექსი გობრონიძის ქუჩა, N 5/რამაზ შენგელიას ქუჩა, N 10-ში არსებულ მიწის ნაკვეთზე (ს/კ: № 01.11.13.002.264), შეთანხმებული განაშენიანების რეგულირების გეგმის საფუძველზე დამუშავებული მრავალფუნქციური კომპლექსი/შენობის არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2025 წლის 26 მარტიდან 2029 წლის 26 მარტის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 1) მოსამზადებელი სამუშაოები, ტერიტორიის მოწესრიგება, შესანარჩუნებელი მწვანე ნარგავების დაცვა, მიწისქვეშა საინჟინრო კომუნიკაციების გადატანა; 2) მიწის ნაკვეთის გრუნტის ცვლილება; 3) შენობა-ნაგებობის გრუნტზე დაკვალვა და ძირითადი ღერძების დაფიქსირება; 4) შენობა-ნაგებობების მიწის სამუშაოები; 5) შენობა-ნაგებობების ფუძის მოწყობის სამუშაოები; ხიმინჯების მოწყობის სამუშაოები; შენობა-ნაგებობების საძირკვლის მოწყობის სამუშაოები; ძირითადი კონსტრუქციული სისტემის მოწყობა შენობა-ნაგებობის ნულოვან ნიშნულამდე; შენობა-ნაგებობის ნულოვანი ნიშნულიდან ყოველ 7 მეტრს სიმღლეზე (სართულების ჯერადად) ძირითადი კონსტრუქციული სისტემის მოწყობა; 6) შენობა-ნაგებობების სახურავისა და გადახურვის მოწყობა; 7) არამზიდი კონსტრუქციების მოწყობა; 8) შენობა-ნაგებობების ლოკალური საერთო სარგებლობის საინჟინრო-ტექნიკური ქსელების მოწყობა; 9) ტექნოლოგიური მოწყობილობების მონტაჟი; 10) შენობა-ნაგებობების გარე მოსაპირკეთებელი სამუშაოები; 11) მიწის ნაკვეთის კეთილმოწყობის სამუშაოები. გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. საქართველოს სივრცის დაგეგმარების, არქიტექტურული და სამშენებლო საქმიანობის კოდექსის 1415 მუხლის შესაბამისად, შენობა-ნაგებობის მშენებლობისას მშენებლობის საჯარო ზედამხედველობის შესაბამისი ორგანოსთვის საეტაპო ოქმის დადგენილი წესით წარუდგენლობისთვის სამშენებლო სამართალდამრღვევს 2025 წლის 31 დეკემბრამდე არ დაეკისრება ამ კოდექსის 132-ე მუხლით გათვალიწინებული პასუხისმგებლობა. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან. 8. სსიპ საგანგებო სიტუაციების მართვის სამსახურის 16/12/2024 წლის MIA 4 24 03802316 წერილის შესაბამისად, დამკვეთის მიერ უზრუნველყოფილ იქნას ხანძარსაწინააღმდეგო დაცვის სისტემების მოწყობა და მათი დაპროექტების დოკუმენტაციის სსიპ საგანგებო სიტუაციების მართვის სამსახურში სამი თვის ვადაში წარდგენა.
Show moreShow less
- 26 March 2025Decision7427333 - Granted
- 25 March 2025City answer
- 19 March 2025City answer
- 19 March 2025Files uploaded
- 21 February 2025City answer
- 21 February 2025Files uploaded
- 30 January 2025City answer
- 30 January 2025Files uploaded
- 23 January 2025City answer
- 23 January 2025Files uploaded
- 23 January 2025Files uploaded
- 27 December 2024City answer
- 27 December 2024Files uploaded
- 27 December 2024Files uploaded
- 25 December 2024City answer
- 25 December 2024Files uploaded
- 23 December 2024City answer
- 23 December 2024Files uploaded
- 18 December 2024City answer
- 18 December 2024Files uploaded
- 16 December 2024City answer
- 16 December 2024Files uploaded
- 10 December 2024City answer
- 10 December 2024Files uploaded
- 14 November 2024City answer
- 14 November 2024Files uploaded
- 23 October 2024City answer
- 23 October 2024Files uploaded
- 16 October 2024City answer
- 16 October 2024Files uploaded
- 16 October 2024Files uploaded
- 16 October 2024Files uploaded
- 16 October 2024Files uploaded
- 3 October 2024City answer
- 3 October 2024Files uploaded
- 3 October 2024Files uploaded
- 3 October 2024Files uploaded
- 26 September 2024City answer
- 26 September 2024Files uploaded
- 3 September 2024City answer
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 3 September 2024Files uploaded
- 22 August 2024Files uploaded
- 22 August 2024Files uploaded
- 5 August 2024City answer
- 1 August 2024City answer
- 1 August 2024Files uploaded
- 1 August 2024Files uploaded
- 1 August 2024Files uploaded
- 1 August 2024Files uploaded
- 1 August 2024Files uploaded
- 29 December 2022Files uploaded
- 29 December 2022Files uploaded
- 28 December 2022Files uploaded
Documents
Drawings and project files54
- 210903_GDN-BA_Archi_A010_გენგეგმა.dwg
- 210903_GDN-BA_Archi_A010_გენგეგმა.pdfOpen ↗
- გეგმები.pdfOpen ↗
- ფასადები.pdfOpen ↗
- ჭრილი.pdfOpen ↗
- ჭრილი.pdfOpen ↗
Show all (54)Show less
- cad-file.dwg
- 220525_GDN-BA_Archi_A010_გენგეგმა.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა (1).dwg
- 01.08.2024 ჭრილები.pdfOpen ↗
- 01.08.2024 ფასადები.pdfOpen ↗
- 01.08.2024 ვიზუალიზაცია.pdfOpen ↗
- 01.08.24 გეგმები.pdfOpen ↗
- 08.01.24.DWG + კროკები.dwg
- 22.08.24 გეგმები + 41.pdfOpen ↗
- 08.22.24 ჭრილები.pdfOpen ↗
- 08.22.24 ფასადები.pdfOpen ↗
- 08.22.24.DWG + კროკები.dwg
- 08.22.24 ჭრილები.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა 1.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა 1.dwg
- 09.03.24.DWG + კროკები (კ1-კ2-კ3 კოეფიციენტი).dwg
- 03.09.24ჭრილები + 0 ნიშნულის დასადგენი განშლები.pdfOpen ↗
- 09.03.204 ფასადები -.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა 2.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა 2 (1).dwg
- 09.03.24 გეგმები + 41.pdfOpen ↗
- 26.09 გეგმები.pdfOpen ↗
- ფასადები 09.26.24.pdfOpen ↗
- 220525_GDN-BA_Archi_A010_გენგეგმა 5.dwg
- 09.25.24.DWG + კროკები.dwg
- 03.10.24 გეგმები + 41.pdfOpen ↗
- 16.10.24_A010_გენგეგმა.pdfOpen ↗
- 16.10.24_A010_გენგეგმა.dwg
- 16.10.24 კორექტირებული ფასადები.pdfOpen ↗
- 16.10.24 DWG + კროკები.dwg
- 16.10.24 გეგმები + 41.pdfOpen ↗
- 23.10.24 A010_გენგეგმა_სახანძროს ჩვენებით 1 (3).dwg
- 23.10.24 A010_გენგეგმა_სახანძროს ჩვენებით 1 (3).pdfOpen ↗
- 11.14.24.DWG + კროკები.dwg
- 14.11 ფასადები.pdfOpen ↗
- 14.11 გეგმები + 41.pdfOpen ↗
- გენგეგმა სახანძრო.pdfOpen ↗
- 12.10.24 გეგმები + 41.pdfOpen ↗
- 12.10.24 ფასადები.pdfOpen ↗
- 23.12.24 გეგმები + 41.pdfOpen ↗
- 25.12 გეგმები + 41.pdfOpen ↗
- 25.12 ჭრილები.pdfOpen ↗
- 25.12 ფასადები.pdfOpen ↗
- 27.12 გეგმები + 41.pdfOpen ↗
- 27.12 ფასადები.pdfOpen ↗
- 27.12.24 DWG + კროკები.dwg
- GDN-BA_Archi_A010_გენგეგმა 1.pdfOpen ↗
- GDN-BA_Archi_A010_გენგეგმა 1.dwg
Reports and surveys25
- 41-ე და მისაწვდომობა -დასკვნა გლდანი ბ ბლოკი.pdfOpen ↗
- გლდანი ბ ბლოკი-41-ე და მისაწვდომობა დასკვნა -22.08.2024.pdfOpen ↗
- საინჟინრო ქსელები ერთიანად.pdfOpen ↗
- ქ. თბილისი, გობრონიძის ქ.5-შენგელიას ქ.10 9002,264)-გეოლოგია.pdfOpen ↗
- 16.10.24 კორექტირებული საინჟინრო ქსელები.pdfOpen ↗
- დასკვნა 41 +მისაწვდომობა გლდანი ბ ბლოკი 15.10.2024.pdfOpen ↗
Show all (25)Show less
- 16.10.24 კონსტრუქცია.pdfOpen ↗
- 23.10.24 საინჟინრო ქსელები - კორექტირებული გაზმომარაგება.pdfOpen ↗
- 41-ე და მისაწვდომობა-დასკვნა გლდანი ბ ბლოკი-14.11.2024.pdfOpen ↗
- კონსტრუქციულ გავლენაზე დასკვნა.pdfOpen ↗
- კონსტრუქციული დასკვნა.pdfOpen ↗
- კონსტრუქციები - ერთიანად.pdfOpen ↗
- გავლენაზე დასკვნა.pdfOpen ↗
- გეოლოგია.pdfOpen ↗
- 23.12 კონსტრუქციები ერთიანად.pdfOpen ↗
- 23.12 კონსტრუქციული ზეგავლენის დასკვნა.pdfOpen ↗
- 23.12 გეოლოგია.pdfOpen ↗
- 23.12 კონსტრუქციული ზეგავლენის დასკვნა.pdfOpen ↗
- 23.12 კონსტრუქციული დასკვნა.pdfOpen ↗
- 25.12 კონსტრუქციები ერთიანად.pdfOpen ↗
- 25.12 კონსტრუქციული ზეგავლენის დასკვნა.pdfOpen ↗
- 25.12 GC-2436 - გეოლოგია ტექნიკური ანგარიში.pdfOpen ↗
- 25.12 კონსტრუქციული ზეგავლენის დასკვნა.pdfOpen ↗
- 25.12 კონსტრუქციული დასკვნა.pdfOpen ↗
- 27.12 GC-2436 - ტექნიკური ანგარიში (4C). 22.11.2024. (REV.3).pdfOpen ↗
Other files34
- ფოტოსურათები.pdfOpen ↗
- ---.pdfOpen ↗
- კვლევა -სქემა.pdfOpen ↗
- ---.pdfOpen ↗
- DownloadServlet (15).pdfOpen ↗
- ---.pdfOpen ↗
Show all (34)Show less
- 1-1.jpgOpen ↗
- 1-1.jpgOpen ↗
- 1-1.jpgOpen ↗
- ფოტოები 07.31.2024.pdfOpen ↗
- მონტაჟი 6.jpgOpen ↗
- r1 12.jpgOpen ↗
- r2 11.jpgOpen ↗
- r3 8.jpgOpen ↗
- 22.08.24 სიმაღლის განმსაზღვრელი სქემა.pdfOpen ↗
- A703-სიმაღლის სქემა.pdfOpen ↗
- A1455.pdfOpen ↗
- 16.10.24 პოსი + კალენდარული.pdfOpen ↗
- ფოტოფიქსაცია 16.10.24.pdfOpen ↗
- mont2.jpg.jpgOpen ↗
- r1.jpg-min.jpgOpen ↗
- r2.jpg-min.jpgOpen ↗
- r2.jpg-min.jpgOpen ↗
- 14.11 ბანერი.pdfOpen ↗
- საგანგებოსთვის შუალედური 12.10.rarOpen ↗
- საგანგებოს პასუხი.pdfOpen ↗
- გობრონიძის ქ. - 01.11.13.002.264 - საექსპერტო შეფასება-signed.pdfOpen ↗
- 25.12 გობრონიძის ქ. - 01.11.13.002.264 - საექსპერტო შეფასებაა-signed.pdfOpen ↗
- 27.12 გლდანი ბ ბლოკი-41-ე და მისაწვდომობა -27.12.2024.pdfOpen ↗
- შეთანხმებული სქემები (01.11.13.002.264).pdfOpen ↗
- შეთანხმებული სქემები (01.11.13.002.264).pdfOpen ↗
- სატრანსპორტო კვლევა.pdfOpen ↗
- ქროსი - გამწვანების პროექტი.pdfOpen ↗
- 03.19.25 - ქროსი - გამწვანების პროექტი.pdfOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal