OpenCAD
Approved

ქალაქი თბილისი, პეტრე იბერის ქუჩა, N 22

AR1953034Change to approved projectOther use7 March 2023- Dighomi
Total floor area
11,593.7 m²
Building footprint
12,605.5 m²
Residential area
5,123.1 m²
Plot area
2,229 m²
Height
42.2 m
Depth below ground
1.4 m
Building volume
41,041.9 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
6525231
Decision date
23 June 2023
Outcome
Granted
Construction period
23 June 2023 – 23 October 2023
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
ზაზა ბოხუა
Developer (company ID)
401987374

People

  • Client
    Name
    ზაზა ბოხუა
    Personal number
    *********19
    Organization
    შ.პ.ს. "მაზა"
    Company code
    401987374
  • Chief architect
    Name
    ზაზა მემანიშვილი
    Personal number
    *********48
    Organization
    შ.პ.ს. ,,მაზა"
    Company code
    401987374
  • Co-authors
    Name
    დავით ბაირამაშვილი
  • Specialistკორექტირებული პროექტის მშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ბელა გოგოლაური
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გუგა ჭოხონელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    მალხაზ საველიძე
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    ეკა ჩხაიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.10.06.001.281
Owner
შპს "მაზა" (401987374)
Area
2,229 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1953034
Status
Approved
Registered
7 March 2023
Type
Change to approved project

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
1 day
from the last re-submission to the decision
Rounds of remarks
6

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 23 June 2023City answer

    1. შეთანხმდეს ქ. თბილისში, სექტორი-საბურთალო, პეტრე იბერის ქუჩა N 22, არსებულ მიწის ნაკვეთზე (ს/კ: №01.10.06.001.281) მრავალფუნქციური შენობა-ნაგებობის კორექტირებული არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2023 წლის 23 ივნისიდან 2023 წლის 23 ოქტომბრის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 9) შენობა-ნაგებობის გარე მოსაპირკეთებელი სამუშაოების დამთავრება. 10) მიწის ნაკვეთის კეთილმოწყობის სამუშაოები გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან.

    Show more
  2. 23 June 2023Decision6525231 - Granted
  3. 22 June 2023City answer
  4. 22 June 2023Files uploaded
  5. 21 June 2023Files uploaded
  6. 21 June 2023Files uploaded
  7. 21 June 2023Files uploaded
  8. 21 June 2023Files uploaded
  9. 21 June 2023Files uploaded
  10. 10 June 2023City answer
  11. 10 June 2023Files uploaded
  12. 10 June 2023Files uploaded
  13. 10 June 2023Files uploaded
  14. 10 June 2023Files uploaded
  15. 29 May 2023City answer
  16. 29 May 2023Files uploaded
  17. 29 May 2023Files uploaded
  18. 23 May 2023City answer
  19. 23 May 2023Files uploaded
  20. 23 May 2023Files uploaded
  21. 23 May 2023Files uploaded
  22. 23 May 2023Files uploaded
  23. 23 May 2023Files uploaded
  24. 3 May 2023City answer
  25. 3 May 2023Files uploaded
  26. 3 May 2023Files uploaded
  27. 2 May 2023Files uploaded
  28. 2 May 2023Files uploaded
  29. 2 May 2023Files uploaded
  30. 2 May 2023Files uploaded
  31. 2 May 2023Files uploaded
  32. 7 April 2023Deadline extendedby 15 days, new deadline: 3 May 2023
  33. 7 March 2023Files uploaded
  34. 6 March 2023Files uploaded
  35. 6 March 2023Files uploaded
  36. 6 March 2023Files uploaded
  37. 6 March 2023Files uploaded
  38. 6 March 2023Files uploaded
  39. 6 March 2023Files uploaded
  40. 6 March 2023Files uploaded
  41. 6 March 2023Files uploaded
  42. 6 March 2023Files uploaded

Documents

Drawings and project files9

  • Gengegma+m+servituti+1-500----220821--CAD.pla
  • petre+iberis+qucha-22-asatvirti+masala+--060323-05.pla
  • petre+iberis+qucha-22-asatvirti+masala+-030523-kor.pla
  • Gengegma+m+servituti+1-500----230523--CAD.pla
  • petre+iberis+qucha-22-asatvirti+masala+-230523.pla
  • petre+iberis+qucha-22-asatvirti+masala+-290523.pla
Show all (9)
  • petre+iberis+qucha-22-asatvirti CAD faili ant-100623.pla
  • petre+iberis+qucha-22-asatvirti CAD faili ant-100623-03.pla
  • petre+iberis+qucha-22-asatvirti+masala+-220623.pla

Reports and surveys1

Other files52

  • Bela posi-2023.pdfOpen ↗
  • Petre Iberis 22- ( kor 21)-Gengegmebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti--Cxrili+Gegmebi ertad-040323.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-280223-Chrilebi ertad.pdfOpen ↗
  • Petre Iberis 22- ( kor 23)-Sim Chrilebi ertad.pdfOpen ↗
  • Petre Iberis 22- ( kor 21)-Aqs&Monts ertad-Shetanxmebuli.pdfOpen ↗
Show all (52)
  • ექსპერტიზა კორექტირება 2023.pdfOpen ↗
  • maza koreqtirebulis eqspertiza -1.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-280223-Fasadiebi ertad.pdfOpen ↗
  • Arsebulis fotoebi ertad-280223.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti--Cxrili+Gegmebi ertad+detalebi-040323.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323_001.jpgOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323_002.jpgOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323_003.jpgOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323_004.jpgOpen ↗
  • petre+iberis+qucha-22-asatvirti--AQS&monts ertad-040323_005.jpgOpen ↗
  • საკრებულოს განკარგულება 43-2022 და კონსსტრუქციები+ექსპერტიზა მონოლითი+სმეჟნიკები..pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti--Cxrili+Gegmebi ertad+detalebi-060323.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-[number] -Cxrili+Gegmebi+detalebi.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-020523- Chrilebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-020523-Fasadebi erTad.pdfOpen ↗
  • axali fotoebi ertad-010523.pdfOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT.pdfOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT_001.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT_002.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT_003.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT_004.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebi koreqtirebuli vitrajebiT_005.jpgOpen ↗
  • საკრებულოს განკარგულება 43-2022 და კონსსტრუქციები+ექსპერტიზა მონოლითი+დენდრო+გატბობა+გაზი+წყალი+ელექტროობა+ვენტილაცია.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-[number] -Cxrili+Gegmebi+detalebi-022.pdfOpen ↗
  • eqspertiza 12 sart.shevsebuli p.iberi 22.2023.2 მაისი.docx.pdfOpen ↗
  • Petre Iberis 22- ( kor 21)-Gengegmebi ertad-230523.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-230523- Chrilebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-230523-Fasadebi erTad.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-230523 -Cxrili+Gegmebi+detalebi.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-[number] -Cxrili+Gegmebi+detalebi.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-290523- Chrilebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+Fasadebi ertad-090623.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-100623 -Cxrili+Gegmebi+detalebi.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-100623 -Cxrili+Gegmebi+detalebi-03.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-210623-Fasadi-ertad.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-210623- Chrilebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-Hor-210623 -- Chrilebi ertad.pdfOpen ↗
  • petre+iberis+qucha-22-asatvirti+masala+-210623+cxrili+Gegmebi +detalebi.pdfOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623.pdfOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623_001.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623_002.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623_003.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623_004.jpgOpen ↗
  • AQS&Mont ertad-shedarebiti aqsonometriebiertad-210623_005.jpgOpen ↗
  • eqspertiza 12 sart.shevsebuli p.iberi 22.2023.19 ივნისი.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal