ქალაქი თბილისი , მდ. მტკვრის მარჯვენა სანაპირო , ბაქტერიოფაგისაკენ ჩასასვლელი გზის მიმდებარედ, ნაკვეთი 16/123, ქალაქი თბილისი, გიორგი სააკაძის II გასასვლელი, N 19
- Total floor area
- 13,406.6 m²
- Building footprint
- 14,232 m²
- Plot area
- 2,764 m²
- Height
- 26.7 m
- Depth below ground
- 6.4 m
- Building volume
- 100,282.2 m³
Figures as the applicant entered them in the form; not verified.
Decision
- Decision number
- 6478204
- Decision date
- 25 May 2023
- Outcome
- Granted
- Construction period
- 25 May 2023 – 25 November 2025
Source: TAS, the city's permit system - as of 21 November 2026
Applicant
- Name
- ლუკა ჩაგანავა
- Developer (company ID)
- 211328124
People
- Client
- Name
- ვახტანგ ფარჯიანი
- Personal number
- *********98
- Organization
- შპს ,, კომფორტი 50''
- Company code
- 211328124
- Chief architect
- Name
- ლუკა ჩაგანავა
- Personal number
- *********74
- Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
- Name
- თემურ მაცაბერიძე
- Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
- Name
- ბელა გოგოლაური
- Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
- Name
- ილია ცხომელიძე
- Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
- Name
- თემურ მაცაბერიძე
- Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
- Name
- ნინო მენთეშაშვილი
The people the applicant named in the application form.
Parcel
- Cadastral code
- 01.10.13.016.164
- Owner
- შპს "კომფორტი 50" (211328124)
- Area
- 2,764 m²
- Land use
- არასასოფლო სამეურნეო
Source: NAPR, the land registry - as of 1 October 2026
Plots and zoning
- 01.10.13.016.164Registry extract ↗ (opens in a new tab)
- Zone
- Commercial / business
- Sub-zone
- ssz-3
- K1
- 0.7
- K2
- 0
- K3
- 0.1
from the city zoning map (snapshot 30 September 2026)
Document
- Number
- AR1956360
- Status
- Approved
- Registered
- 24 March 2023
- Type
- New construction
Source: TAS, the city's permit system - read from TAS 1 October 2026
Case progress
- Length of the case
- 6 days
- from the last re-submission to the decision
- Rounds of remarks
- 10
Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.
Timeline
Newest first.
- 25 May 2023City answer
1. შეთანხმდეს ქ. თბილისში, მდ.მტკვრის მარჯვენა სანაპირო, ბაქტერიოფაგისაკენ ჩასასვლელი გზის მიმდებარედ, ნაკვეთი 16/123, ქალაქი თბილისი, გიორგი სააკაძის II გასასვლელი, N19- ში, კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (ს/კ: №01.10.13.016.164) ოფისის არქიტექტურული პროექტი. 2. გაიცეს მშენებლობის ნებართვა და გაცემულად ჩაითვალოს მშენებლობის სანებართვო მოწმობა. 3. მშენებლობის ვადა განისაზღვროს 2023 წლის 25 მაისიდან 2025 წლის 25 ნოემბრის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 4. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 1) სამშენებლო მოედნის მოწესრიგება: სილქნეთის ხაზოვანი ნაგებობის გადატანა და არსებული შენობების დემონტაჟი: 02/1, 03/1, 01/1, 04/1, 05/1, ჯიხურა და აუზი; 2) შენობა-ნაგებობის გრუნტზე დაკვალვა და ძირითადი ღერძების დაფიქსირება; 3) შენობა-ნაგებობების მიწის სამუშაოები, ნაწილობრივი გამაგრებით; შენობა-ნაგებობების ფუძის მოწყობის სამუშაოები; შენობა-ნაგებობების საძირკვლის მოწყობის სამუშაოები;ძირითადი კონსტრუქციული სისტემის მოწყობა შენობა-ნაგებობის ნულოვან ნიშნულამდე; 4) ძირითადი კონსრტუქციული სისტემის მოწყობა შენობა-ნაგებობის ნულოვანი ნიშნულიდან: 0.00-6.85მ-მდე; 6.85-13.65მ-მდე; 13.65-21.27მ-მდე; 21.27-23.75,მ-მდე; 5) შენობა-ნაგებობის სახურავისა და გადახურვის მოწყობა; 6)არამზიდი კონსტრუქციების მოწყობა; 7)შენობა-ნაგებობის ლოკალური საერთო სარგებლობის საინჟინრო-ტექნიკური ქსელების მოწყობა; 8)ტექნოლოგიური მოწყობილობების მონტაჟი; 9)შენობა-ნაგებობის გარე მოსაპირკეთებელი სამშაოები; 10)მიწის ნაკვეთის კეთილმოწყობის სამუშაოები; გაითვალისწინეთ: მშენებლობის ნებართვის მფლობელი (დამკვეთი) ვალდებულია “მშენებლობის ნებართვის გაცემისა და შენობა-ნაგებობის ექსპლუატაციაში მიღების წესისა და პირობების შესახებ” საქართველოს მთავრობის 2019 წლის 31 მაისის №255 დადგენილებით დამტკიცებული წესის შესაბამისად შეადგინოს მშენებლობის (ზედამხედველობის) ეტაპის დასრულების ოქმი და სამშენებლო/სანებართვო პირობებით დადგენილი მორიგი ეტაპის დასრულებამდე წერილობითი სახით წარადგინოს ქალაქ თბილისის მუნიციპალიტეტის მერიის მუნიციპალურ ინსპექციაში. აღნიშნული მოთხოვნის შეუსრულებლობა წარმოადგენს სანებართვო პირობების დარღვევას და იწვევს კანონმდებლობით გათვალისწინებულ პასუხისმგებლობას - დაჯარიმებას. 5. განემარტოს დამკვეთს, რომ ვალდებულია სამშენებლო სამუშაოების დაწყებამდე უზრუნველყოს თვალსაჩინო ადგილას საინფორმაციო დაფის განთავსება, საპროექტო შენობის ვიზუალიზაციით და შესაბამისი რეკვიზიტებით. 6. ტერიტორიაზე ხაზობრივი ნაგებობების არსებობის შემთხვევაში საპროექტო ობიექტის მშენებლობის საკითხი წინასწარ იქნას შეთანხმებული ხაზობრივი ნაგებობის მესაკუთრესთან. 7. მშენებლობის წარმოებისას დაცული იქნას ტერიტორიაზე არსებული ხე–ნარგავები, ხის მოჭრის ან გადარგვის საჭიროების შემთხვევაში საკითხი წინასწარ იქნას შეთანხმებული ქ. თბილისის მუნიციპალიტეტის მერიის გარემოს დაცვის საქალაქო სამსახურთან. 8.დაცული იქნას წრმოდგენილი სს „სილქნეტის“ 2023 წლის 12 აპრილის N1808/24-8 წერილის პირობები.
Show moreShow less
- 25 May 2023Decision6478204 - Granted
- 24 May 2023City answer
- 19 May 2023City answer
- 19 May 2023Files uploaded
- 16 May 2023City answer
- 16 May 2023Files uploaded
- 16 May 2023Files uploaded
- 16 May 2023Files uploaded
- 16 May 2023Files uploaded
- 11 May 2023City answer
- 11 May 2023Files uploaded
- 8 May 2023City answer
- 8 May 2023Files uploaded
- 8 May 2023Files uploaded
- 8 May 2023Files uploaded
- 3 May 2023City answer
- 3 May 2023Files uploaded
- 3 May 2023Files uploaded
- 3 May 2023Files uploaded
- 2 May 2023Files uploaded
- 1 May 2023Files uploaded
- 1 May 2023Files uploaded
- 1 May 2023Files uploaded
- 1 May 2023Files uploaded
- 1 May 2023Files uploaded
- 21 April 2023City answer
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 21 April 2023Files uploaded
- 13 April 2023City answer
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 13 April 2023Files uploaded
- 7 April 2023City answer
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 7 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 6 April 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
- 24 March 2023Files uploaded
Documents
Drawings and project files48
- 007_გენ-გეგმა 1_250.pdfOpen ↗
- ჭრილები+სპეციფიკაცია.pdfOpen ↗
- ფასადები.pdfOpen ↗
- 3D ვიზუალი.pdfOpen ↗
- 3D ვიზუალი (2).pdfOpen ↗
- 24.03.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
Show all (48)Show less
- 01 3D (1).jpgOpen ↗
- 02 3D (1).jpgOpen ↗
- 03 3D (1).jpgOpen ↗
- გეგმები.pdfOpen ↗
- 24.03.23_გენ-გეგმა_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- საოფისე შენობა_გეგმები1.pdfOpen ↗
- საოფისე შენობა_ფასადები1.pdfOpen ↗
- 06.04.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- 03 3D (3).jpgOpen ↗
- საოფისე შენობა_გეგმები (1).pdfOpen ↗
- 07.04.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- საოფისე შენობა_გეგმები (2).pdfOpen ↗
- 0საოფისე შენობა_გეგმები (3).pdfOpen ↗
- 0საოფისე შენობა_ჭრილები.pdfOpen ↗
- 0საოფისე შენობა_ფასადები (1).pdfOpen ↗
- 13.04.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- 13.04.2023_3D_ვიზუალი.pdfOpen ↗
- გეგმები.pdfOpen ↗
- გეგმები (1).pdfOpen ↗
- საოფისე შენობა_ჭრილები.pdfOpen ↗
- ფასადები.pdfOpen ↗
- გენ-გეგმა_500_19.04_საოფისე სააკაძეზე.pdfOpen ↗
- 01.05.23_სააკაძე გენ-გეგმა.dwg
- 01.05.23გეგმები.pdfOpen ↗
- 01.05.23_ჭრილები.pdfOpen ↗
- 01.05.23_ფასადები.pdfOpen ↗
- 01.05.2023_3D_ვიზუალი.pdfOpen ↗
- 01.05.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- 01.05.23_სააკაძე გენ-გეგმა-1-250 გენ-გეგმა.pdfOpen ↗
- 01.05.23_სააკაძე გენ-გეგმა(1).dwg
- 01.05.2023_3D_ვიზუალი (1).pdfOpen ↗
- 01.05.23 ვიზუალი.jpgOpen ↗
- 08.05.23_02 ვიზუალი.jpgOpen ↗
- 08.05.23გეგმები.pdfOpen ↗
- 08.05.23_ჭრილები.pdfOpen ↗
- 08.05.23_ფასადები.pdfOpen ↗
- 08.05.2023_3D_ვიზუალი.pdfOpen ↗
- 08.05.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
- 11.05.23გეგმები.pdfOpen ↗
- 11.05.23_ჭრილები.pdfOpen ↗
- 11.05.23_ფასადები.pdfOpen ↗
- 11.05.23_საოფისე შენობა გ.სააკაძის II გასასვლელი.dwg
Reports and surveys22
- სააკაძე_გავლენის დასკვნა_17022023.pdfOpen ↗
- კონსტრუქციები.pdfOpen ↗
- საინჟინრო.pdfOpen ↗
- დასკვნა 41-ეს (საოფისე შენობა).pdfOpen ↗
- სააკაძე გეოლოგია 164.pdfOpen ↗
- გეოლოგია+ექსპერტიზა.pdfOpen ↗
Show all (22)Show less
- გეოლოგია+ექსპერტიზა.pdfOpen ↗
- სააკაძე_კონსტრუქციული პროექტი.pdfOpen ↗
- ექსპერტიზა გეოლოგია.pdfOpen ↗
- სააკაძე_საინჟინრო ქსელები.pdfOpen ↗
- სააკაძე_კონსტრუქციული პროექტი.pdfOpen ↗
- კონსტრუქციები.pdfOpen ↗
- სააკაძე_კონსტრუქციული პროექტი (2).pdfOpen ↗
- სააკაძე_საინჟინრო ქსელები (2).pdfOpen ↗
- 041 დასკვნა ოფისი სააკაძეზე.pdfOpen ↗
- 0სააკაძე_საინჟინრო ქსელები (3).pdfOpen ↗
- დასკვნა+პროექტი.pdfOpen ↗
- სააკაძე_საინჟინრო ქსელები.pdfOpen ↗
- დასკვნა მისაწვდომობის_ექსპერტიზა20.04.pdfOpen ↗
- 01.05.23_დასკვნა 41-ს ოფისი_მისაწვდომობა.pdfOpen ↗
- 08.05.23_სააკაძე_კონსტრუქციული პროექტი.pdfOpen ↗
- 01სააკაძე-საინჟინრო ქსელები.pdfOpen ↗
Other files38
- სატრანსპორტო.pdfOpen ↗
- სიმაღლის სხივი.pdfOpen ↗
- გრუნტის ცვლილება.pdfOpen ↗
- ფოტოები.pdfOpen ↗
- MOP.pdfOpen ↗
- სატრასნსპორტო+კვლევა.pdfOpen ↗
Show all (38)Show less
- გამწვანება.pdfOpen ↗
- გრუნტის ზედაპირის ცვლილება (1).pdfOpen ↗
- სატრასნსპორტო+კვლევა.pdfOpen ↗
- გამწვანება.pdfOpen ↗
- წერილები.pdfOpen ↗
- ბანერი.pdfOpen ↗
- MOP_1.pdfOpen ↗
- ბანერი 01.pdfOpen ↗
- შენობის განთავსება ბენზინგასამართ სადგურთან მიმართებაში.pdfOpen ↗
- 0გრუნტის ზედაპირის ცვლილება (2).pdfOpen ↗
- სილქნეტის წერილი.pdfOpen ↗
- ტერაბანკი.pdfOpen ↗
- 01.jpgOpen ↗
- 02 (1).jpgOpen ↗
- 03.jpgOpen ↗
- 04.jpgOpen ↗
- 05.jpgOpen ↗
- 01.10.13.016.164_სააკაძის დაღმართი.pdfOpen ↗
- სილქნეტი.pdfOpen ↗
- 01mopi.pdfOpen ↗
- 01.05.23_სილქნეტი.pdfOpen ↗
- 01.05.23_სიმაღლის სხივი.pdfOpen ↗
- 02.05.23_მოპი_საოფისე შენობა სააკაძეზე.pdfOpen ↗
- 03.05.23_მოპი_საოფისე შენობა სააკაძეზე (1).pdfOpen ↗
- 03.05.23_გ.სააკაძის II გას.01.10.13.016.164.pdfOpen ↗
- 01-03.05.23_გ.სააკაძის II გას.01.10.13.016.164.pdfOpen ↗
- 08.05.23_მოპი_საოფისე შენობა სააკაძეზე (1).pdfOpen ↗
- transporti (2).zipOpen ↗
- transporti (2).zipOpen ↗
- 03.05.23_გ.სააკაძის II გას.01.10.13.016.164 (1).pdfOpen ↗
- 03.05.23_გ.სააკაძის II გას.01.10.13.016.164 (1).pdfOpen ↗
- სააკაძე ტრანსპროტი.zipOpen ↗
Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.
All documents on docs.tbilisi.gov.ge ↗Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal