OpenCAD
Approved

ქალაქი თბილისი , ვაკის რაიონი

AR1964844New constructionMulti-unit residential8 May 2023- Saburtalo
Total floor area
28,336.5 m²
Building footprint
29,890 m²
Residential area
12,702.6 m²
Plot area
12,961 m²
Height
49.2 m
Depth below ground
10.4 m
Building volume
92,793 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
6598916
Decision date
4 August 2023
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
გიორგი ტვილდიანი
Developer (company ID)
211374289

People

  • Client
    Name
    გიორგი გედევანიშვილი
    Personal number
    *********58
    Organization
    შპს"04"
    Company code
    211374289
  • Chief architect
    Name
    გიორგი ტვილდიანი
    Personal number
    *********24
  • Co-authors
    Name
    თორნიკე სამხარაძე
  • Specialistსაჭიროების შემთხვევაში მომიჯნავე შენობა-ნაგებობის კონსტრუქციული დასკვნა
    Name
    თამაზ გეგეჭკორი
  • Specialistმშენებლობის ორგანიზების კალენდარული გრაფიკი
    Name
    ლიანა მექვაბიშვილი
  • Specialistსაინჟინრო-გეოლოგიური კვლევის საექსპერტო შეფასება
    Name
    გუგა ჭოხონელიძე
  • Specialistფუძეების, საძირკვლებისა და სხვა ძირითადი კონსტრუქციების საექსპერტო შეფასება
    Name
    თამაზ გეგეჭკორი
  • Specialistარქიტექტურული ნაწილების შესაბამისობა „ტექნიკური რეგლამენტის - შენობა-ნაგებობის უსაფრთხოების წესების დამტკიცების თაობაზე “ საქართველოს მთავრობის 2016 წლის 28 იანვრის N41 დადგენილებით დამტკიცებულ რეგლამენტთან
    Name
    ოთარ სულაბერიძე

The people the applicant named in the application form.

Parcel

Cadastral code
01.14.05.009.137
Owner
შპს "იდეა პანორამა" (211374289)
Area
12,961 m²
Land use
არასასოფლო სამეურნეო

Source: NAPR, the land registry - as of 13 November 2026

Plots and zoning

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1964844
Status
Approved
Registered
8 May 2023
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
1 day
from the last re-submission to the decision
Rounds of remarks
11

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 4 August 2023City answer

    1. შეთანხმდეს: ქ. თბილისი, გიორგი დანელიას ქუჩა, N57, კერძო საკუთრებაში არსებულ მიწის ნაკვეთზე (ს/კ: №01.14.05.009.137) მრავალბინიანი საცხოვრებელი სახლის არქიტექტურული პროექტი და გაიცეს მშენებლობის ნებართვა. 2. მშენებლობის ვადა განისაზღვროს 04/08/2023 წლიდან 04/08/2026 წლის ჩათვლით, კალენდარული გრაფიკის შესაბამისად. 3. მშენებლობის ეტაპები განისაზღვროს შემდეგნაირად: 1) მოსამზადებელი სამუშაოები, რომლებიც დაკავშირებულნი არიან სამშენებლო ნაკვეთის მოწესრიგებასთან; 2) მიწის ნაკვეთის გრუნტის ზედაპირის ცვლილება; 3) გრუნტის ზედაპირის ცვლილების შემდეგ შენობა-ნაგებობის გრუნტზე დაკვალვა და ძირითადი ღერძების დაფიქსირება; 4) ა) შენობა-ნაგებობის მიწის სამუშაოები, ქვაბულის კედლების გამაგრება; ბ) შენობა-ნაგებობების ფუძის მოწყობის სამუშაოები; გ) შენობა-ნაგებობების საძირკვლის მოწყობის სამუშაოები; ძირითადი კონსტრუქციული სისტემის მოწყობა შენობა-ნაგებობის ნულოვან ნიშნულამდე (-3,24); 5) შენობა-ნაგებობის ნულოვანი ნიშნულიდან 2 პირველი სართულის ძირითადი კონსტრუქციული სისტემის (არამზიდი კონსტრუქციების გამოკლებით) მოწყობა (-0,00 - +3,24); 6) შენობა-ნაგებობის 2 შემდგომი სართულის ძირითადი კონსტრუქციული სისტემის (არამზიდი კონსტრუქციების გამოკლებით) მოწყობა; (+6,48 - +9,72); 7) შენობა-ნაგებობის 2 შემდგომი სართულის ძირითადი კონსტრუქციული სისტემის (არამზიდი კონსტრუქციების გამოკლებით) მოწყობა (+12,96 - +16,20); 8) შენობა-ნაგებო

    Show more
  2. 4 August 2023Decision6598916 - Granted
  3. 3 August 2023City answer
  4. 3 August 2023Files uploaded
  5. 19 July 2023City answer
  6. 19 July 2023Files uploaded
  7. 14 July 2023City answer
  8. 14 July 2023Files uploaded
  9. 12 July 2023City answer
  10. 12 July 2023Files uploaded
  11. 12 July 2023Files uploaded
  12. 9 July 2023Files uploaded
  13. 9 July 2023Files uploaded
  14. 30 June 2023City answer
  15. 30 June 2023Files uploaded
  16. 30 June 2023Files uploaded
  17. 30 June 2023Files uploaded
  18. 30 June 2023Files uploaded
  19. 29 June 2023City answer
  20. 29 June 2023Files uploaded
  21. 29 June 2023Files uploaded
  22. 25 June 2023City answer
  23. 25 June 2023Files uploaded
  24. 25 June 2023Files uploaded
  25. 19 June 2023City answer
  26. 19 June 2023Files uploaded
  27. 18 June 2023Files uploaded
  28. 18 June 2023Files uploaded
  29. 18 June 2023Files uploaded
  30. 18 June 2023Files uploaded
  31. 17 June 2023Files uploaded
  32. 17 June 2023Files uploaded
  33. 17 June 2023Files uploaded
  34. 16 June 2023Files uploaded
  35. 7 June 2023City answer
  36. 7 June 2023Files uploaded
  37. 4 June 2023Files uploaded
  38. 4 June 2023Files uploaded
  39. 4 June 2023Files uploaded
  40. 4 June 2023Files uploaded
  41. 4 June 2023Files uploaded
  42. 25 May 2023City answer
  43. 25 May 2023Files uploaded
  44. 24 May 2023Files uploaded
  45. 8 May 2023Files uploaded
  46. 5 May 2023Files uploaded
  47. 5 May 2023Files uploaded
  48. 5 May 2023Files uploaded
  49. 5 May 2023Files uploaded
  50. 5 May 2023Files uploaded
  51. 5 May 2023Files uploaded
  52. 5 May 2023Files uploaded

Some older entries, and the rest of very long texts, are not shown here.

Documents

Drawings and project files45

  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_05.05.2023.dwg
  • Na#1_გეგმები_05.05.2023.pdfOpen ↗
  • Na#1_ჭრილები_05.05.2023.pdfOpen ↗
  • Na#1_ფასადები_05.05.2023.pdfOpen ↗
  • Na#1_ ვექტორული_05.05.2023.dwg
  • renderebi_compressed_Page_1.jpgOpen ↗
Show all (45)
  • renderebi_compressed_Page_2.jpgOpen ↗
  • renderebi_compressed_Page_3.jpgOpen ↗
  • renderebi_compressed_Page_4.jpgOpen ↗
  • Na#1_გეგმები_24.05.2023.pdfOpen ↗
  • Na#1_ჭრილები_24.05.20235.pdfOpen ↗
  • Na#1_ფასადები_05.05.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_04.06.2023.dwg
  • Na#1_გეგმები_04.06.2023.pdfOpen ↗
  • Na#1_ჭრილები_დეტ_04.06.2023.pdfOpen ↗
  • Na#1_ფასადები_04.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_04.06.2023.dwg
  • Na#1_გრუნტის ცვლილების გეგმა_04.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_16.06.2023.dwg
  • Na#1_გეგმები_16.06.2023.pdfOpen ↗
  • Na#1_ჭრილები_დეტალები_16.06.2023.pdfOpen ↗
  • Na#1_ფასადები_16.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_10.06.2023.dwg
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_16.06.2023.dwg
  • Na#1_გეგმები_16.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_16.06.2023.dwg
  • Na#1_ჭრილები_დეტალები_16.06.2023.pdfOpen ↗
  • Na#1_ფასადები_16.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_24.06.2023.dwg
  • Na#1_გეგმები_24.06.2023.pdfOpen ↗
  • Na#1_ფასადები_დეტალები_24.06.2023.pdfOpen ↗
  • Na#1_ჭრილები_24.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_24.06.2023.dwg
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_29.06.2023.dwg
  • Na#1_გეგმები_29.06.2023.pdfOpen ↗
  • Na#1_ფასადები_დეტალები_29.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_29.06.2023.dwg
  • Na#1_ფასადები_დეტალები_30.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_30.06.2023.dwg
  • Na#1_გეგმები_30.06.2023.pdfOpen ↗
  • Na#1_გეგმები_30.06.2023.pdfOpen ↗
  • Na#1_ ვექტორული_30.06.2023.dwg
  • Na#1_ფასადები_დეტალები_09.07.2023.pdfOpen ↗
  • Na#1_ ვექტორული_09.07.2023.dwg
  • Na#1_გეგმები_09.07.2023_compressed.pdfOpen ↗

Reports and surveys22

  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_05.05.2023..pdfOpen ↗
  • საექსპერტო დასკვნები _41-ე და 732-ე დადგენილება_05.05.2023.pdfOpen ↗
  • Na#1_დასკვნა-კონსტრუქც_05.05.2023.pdfOpen ↗
  • Nა#1_გეოლოგია_ექსპერტიზა_კვლევა_05.05.2023.pdfOpen ↗
  • Na#1_კონსტრუქციული პროექტი_05.05.2023.pdfOpen ↗
  • Na#1_კონსტრუქციული_საინჟინრო_05.05.2023.pdfOpen ↗
Show all (22)
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_04.06.2023..pdfOpen ↗
  • საექსპერტო დასკვნები _41-ე და 732-ე დადგენილება_03.06.2023.pdfOpen ↗
  • დასკვნა კონსტრუქც _ ნაფეტვრები _ მომიჯნავით (pdf).pdfOpen ↗
  • Na#1_დასკვნა-კონსტრუქც_საინჟ_04.06.2023.pdfOpen ↗
  • Na#1_დასკვნა-კონსტრუქც_საინჟ_04.06.2023.pdfOpen ↗
  • Na#1_დასკვნა კონსტრუქც _ ნაფეტვრები _ მომიჯნავით_16.06.2023.pdfOpen ↗
  • Na#1_კონსტრუქციული_საინჟინრო_16.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_16.06.2023.pdfOpen ↗
  • საექსპერტო დასკვნები _41-ე და 732-ე დადგენილება_16.06.2023.pdfOpen ↗
  • Na#1_დასკვნა კონსტრუქც _ ნაფეტვრები _ მომიჯნავით_16.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_16.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_24.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_29.06.2023.pdfOpen ↗
  • საექსპერტო დასკვნები _41-ე და 732-ე დადგენილება_29.06.2023.pdfOpen ↗
  • Na#1_მიწის ნაკვეთის გეგმა_ტოპო_29.06.2023.pdfOpen ↗
  • საექსპერტო დასკვნები _41-ე და 732-ე დადგენილება_09.07.2023.pdfOpen ↗

Other files24

  • NA#1_არსებული ფოტოები_05.05_2023.pdfOpen ↗
  • Na#1_სიმაღლის განსაზღვრა_05.05.2023.pdfOpen ↗
  • Na#1_ფოტომონტაჟები_05.05.2023.pdfOpen ↗
  • Na#1_სატრანსპორტო კვლევა_05.05_2023.pdfOpen ↗
  • Na#1_საგზაო მოძრაობის ორგანიზების სქემა_05.05_2023.pdfOpen ↗
  • Na#1_გამწვანების პროექტი_05.05.2023_.pdfOpen ↗
Show all (24)
  • Na_ბანერი_05.05.2023.pdfOpen ↗
  • NA#1_არსებული ფოტოები_05.05_2023.pdfOpen ↗
  • ppposi A blokis nafetrvebi.pdfOpen ↗
  • mindobiloba da urbanulis pasuxi.pdfOpen ↗
  • 07.06.2023 gamtsvaneba.pdfOpen ↗
  • Na#1_სიმაღლის განსაზღვრა_16.06.2023.pdf.pdfOpen ↗
  • 1test.jpgOpen ↗
  • 2test.jpgOpen ↗
  • 3Orth (1).jpgOpen ↗
  • Na#1_ფოტომონტაჟები_16.06.2023_Optimized.pdfOpen ↗
  • telasi konstruqcia sainjinro.pdfOpen ↗
  • Na#1_ფოტომონტაჟები_24.06.2023_Optimized.pdfOpen ↗
  • FINAL 30.06.2023.pdfOpen ↗
  • 2023. 07.12 gamtsvaneba.pdfOpen ↗
  • 2023.07.12 allllllllllllllllllll.pdfOpen ↗
  • FFF 2023. 07.14 Final.pdfOpen ↗
  • 2023.07.19 nafeeeeeeeeee.pdfOpen ↗
  • platsioshkaaaaaaa.pdfOpen ↗

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal