AR1975420New constructionSingle-unit30 June 2023- Tkhinvala
Total floor area
525.4 m²
Building footprint
476.4 m²
Residential area
216.7 m²
Plot area
600 m²
Height
11.1 m
Depth below ground
3 m
Building volume
1,940 m³

Figures as the applicant entered them in the form; not verified.

Sign in to follow

Decision

Decision number
7452832
Decision date
22 April 2025
Outcome
Granted
The city's decision report ↗ (opens in a new tab)

Source: TAS, the city's permit system - as of 21 November 2026

Applicant

Name
მამუკა ბარათაშვილი
Developer (company ID)
402167114

People

  • Client
    Name
    მამუკა ბარათაშვილი
    Personal number
    *********74
  • Chief architect
    Name
    მამუკა ბარათაშვილი
    Personal number
    *********74

The people the applicant named in the application form.

Parcel

Cadastral code
01.72.58.033.110
Owner
შპს "ლისის განვითარების ფონდი" (402167114)
Area
600 m²
Land use
სასოფლო-სამეურნეო

Source: NAPR, the land registry - as of 1 October 2026

Plots and zoning

  • Zone
    Agricultural
    Sub-zone
    sofz
    K1
    0
    K2
    0
    Agricultural zone: the city map gives no K2 for this zone type (0 means "not published", not a building ban). Check the zoning regulation.
    K3
    0

from the city zoning map (snapshot 30 September 2026)

Document

Number
AR1975420
Status
Approved
Registered
30 June 2023
Type
New construction

Source: TAS, the city's permit system - read from TAS 1 October 2026

Case progress

Length of the case
7 days
from the last re-submission to the decision
Rounds of remarks
10

Who holds the case comes from its current status; calendar days, counted only for a stretch the record dates; a round is each answer of the city.

Timeline

Newest first.

  1. 22 April 2025City answer

    შეთანხმდეს ქ. თბილისში, ავთო ვარაზის I შესახვევი, N29 (D14) მამუკა ბარათაშვილის საკუთრებაში არსებულ მიწის ნაკვეთზე (ს/კ # 01.72.58.033.110 ) ინდივიდუალური ერთბინიანი საცხოვრებელი სახლის არქიტექტურული პროექტი.

  2. 22 April 2025Decision7452832 - Granted
  3. 16 April 2025City answer
  4. 15 April 2025City answer
  5. 15 April 2025Files uploaded
  6. 14 April 2025Files uploaded
  7. 11 April 2025Files uploaded
  8. 10 April 2025City answer
  9. 10 April 2025Files uploaded
  10. 9 April 2025Files uploaded
  11. 4 April 2025City answer
  12. 4 April 2025Files uploaded
  13. 4 April 2025Files uploaded
  14. 14 March 2025City answer
  15. 14 March 2025Files uploaded
  16. 14 March 2025Files uploaded
  17. 14 March 2025Files uploaded
  18. 6 March 2025City answer
  19. 6 March 2025Files uploaded
  20. 4 March 2025City answer
  21. 4 March 2025Files uploaded
  22. 4 March 2025Files uploaded
  23. 26 February 2025City answer
  24. 26 February 2025Files uploaded
  25. 26 February 2025Files uploaded
  26. 2 November 2023City answer
  27. 22 October 2023Deadline extendedby 15 days, new deadline: 15 November 2023
  28. 30 June 2023Files uploaded

Documents

Drawings and project files12

  • დვგ.dwg
  • დვგ.dwg
  • გენგეგმა.dwg
  • კად ფაილი.pla
  • kadi+.pla
  • კორექტირებულ1.pla
Show all (12)
  • გენი.dwg
  • kadi+-.pla
  • კადი ბოლო.pla
  • გენგეგმა.dwg
  • კადი 04.pla
  • kad faili dazustebuli.pla

Reports and surveys4

  • გეოლოგია 01.72.58.033.110 გაერთიანებული-.pdfOpen ↗
  • გეოლოგია-01.11.17.034.005.pdfOpen ↗
  • გეოლოგია 01.72.58.033.110 გაერთიანებული- (1).pdfOpen ↗
  • კონსტრუქციები.pdfOpen ↗

Other files55

Show all (55)

Files stay on the city's server. Personal documents (powers of attorney, ID) are not shown here.

All documents on docs.tbilisi.gov.ge ↗

Source: docs.tbilisi.gov.ge - This record reflects the public registry at fetch time and is not legal advice.Request removal